Cisco Systems Cisco ONS 15454 SDH manual Turn Up Node, Before You Begin

Page 1

C H A P T E R 4

Turn Up Node

This chapter explains how to provision a single Cisco ONS 15454 SDH node and turn it up for service, including node name, date and time, timing references, network attributes such as IP address and default router, users and user security, and card protection groups.

If you are provisioning an ONS 15454 SDH for dense wavelength division multiplexing (DWDM) or as a hybrid node (DWDM and TDM), you will not complete some procedures until directed to do so in Chapter 5, “Turn Up a DWDM Node.” These procedures are identified in the procedures list in the following section.

Before You Begin

Complete the procedures applicable to your site plan from the following chapters:

Chapter 1, “Install the Shelf and FMECs”

Chapter 2, “Install Cards and Fiber-Optic Cable”

Chapter 3, “Connect the PC and Log into the GUI”

This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs).

1.NTP-D24 Verify Card Installation, page 4-2—Complete this procedure first.

2.NTP-D30 Create Users and Assign Security, page 4-4—Complete this procedure to create Cisco Transport Controller (CTC) users and assign their security levels.

3.NTP-D25 Set Up Name, Date, Time, and Contact Information, page 4-6—Continue with this procedure to set the node name, date, time, location, and contact information.

4.NTP-D279 Set Power Monitor Thresholds, page 4-8—Continue with this procedure to set the node battery power thresholds.

5.NTP-D169 Set Up CTC Network Access, page 4-9—Continue with this procedure to provision the IP address, default router, subnet mask, and network configuration settings.

6.NTP-D27 Set Up the ONS 15454 SDH for Firewall Access, page 4-19—Continue with this procedure if the ONS 15454 SDH will be accessed behind firewalls.

7.NTP-D28 Set Up Timing, page 4-22—Continue with this procedure to set up the node’s SONET timing references. If you are turning up a DWDM or hybrid node, do not complete this procedure until directed to do so in Chapter 5, “Turn Up a DWDM Node.”

Cisco ONS 15454 SDH Procedure Guide, R4.6

 

January 2004

4-1

 

 

 

Image 1
Contents Before You Begin Turn Up NodeInstall Cards and Fiber-Optic Cable NTP-D24 Verify Card InstallationStop. You have completed this procedure DLP-D74 Create a New User-Single Node NTP-D30 Create Users and Assign SecurityDLP-D75 Create a New User-Multiple Nodes Required/As Needed PurposeClick the Provisioning General tabs Confirmation dialog box, click Yes Node view, click the Provisioning General Power Monitor tabs NTP-D279 Set Power Monitor ThresholdsNTP-D169 Set Up CTC Network Access Click the Provisioning Network tabs DLP-D249 Provision IP SettingsCisco ONS 15454 SDH Procedure Guide, R4.6 Reboot Activity Active TCC2 LEDs Standby TCC2 LEDs Slot-0 Status=IpAddress Next Done Mod Cisco ONS 15454 SDH Reference Manual DLP-D65 Create a Static RouteClick the No Authentication button DLP-D250 Set Up or Change Open Shortest Path First ProtocolType- Choose Simple Password January DLP-D251 Set Up or Change Routing Information Protocol NTP-D27 Set Up the ONS 15454 SDH for Firewall Access Iiop port Port Function DLP-D68 Provision the Iiop Listener Port on the CTC Computer NTP-D28 Set Up TimingStop . You have completed this procedure DLP-D69 Set Up External or Line TimingUnframed , FAS , FAS + CAS DLP-D70 Set Up Internal Timing NTP-D170 Create Protection Groups Type Cards Description and Installation Requirements DLP-D71 Create a 11 Protection Group Click the Provisioning Protection tabs DLP-D72 Create a 1N Protection GroupDLP-D73 Create a 1+1 Protection Group Creating a Y-Cable Protection Group DLP-D252 Create a Y-Cable Protection GroupBox Figure NTP-D34 Set Up SnmpCreating an Snmp Trap Without Proxy January