Cabletron Systems ESX-1320 manual PRE-NETWORK Installation Test

Page 35

Pre-Network Installation Test

3.Observe the LCD and LANVIEW LEDs. As the ESX progresses through bootup, the following messages will be displayed:

“Cabletron Test in progress”

The CPU LED illuminates amber.

“Boot from Flash”

The CPU LED blinks amber and goes off.

“Decompress Image”

“Cabletron ESX-1320” or “Cabletron ESX-1380” (depending on the ESX model)

The CPU LED starts blinking green, indicating that the ESX booted successfully. If the ESX does not boot successfully, all transmit LEDs flash amber for several seconds. If the CPU LED is not green, contact Cabletron Systems for assistance. Refer to Chapter 1, Getting Help.

3.8PRE-NETWORK INSTALLATION TEST

Before connecting the ESX to a live network, you may want to test the ESX in a controlled situation to ensure that it is switching packets. You can perform this test using two workstations and an ESX. To perform this test, refer to Figure 3-13 and proceed as follows:

NOTE

Except for the difference in the type of cables (media) needed to connect to ports 1 through 12, the following procedure applies to both the ESX-1320 and the ESX-1380.

1.Install and power up the ESX as described in the previous sections.

2.Connect the first workstation to any ESX interface (except the BRIM interface).

3.Connect the second workstation to any other ESX interface (except the BRIM interface).

ESX-1320/ESX-1380 Installation Guide

3-17

Image 35
Contents Installation Guide Page ESX-1320/ESX-1380 Installation Guide DOC Notice Cabletron Software Program License Declaration of Conformity Contents Contents Chapter Introduction ESX-1320 and ESX-1380 SwitchesFeatures Using this ManualFeatures Following conventions are used throughout this document Document ConventionsGetting Help Related ManualsAnonymous Lanview LEDs Chapter Controls and IndicatorsReset Button Network Management Capabilities Simplex or Full Duplex Mode OperationLCD Display Simplex or Full Duplex Mode Operation ESX-1320/ESX-1380 Installation Guide Chapter Installation Unpacking the ESX Removing the Chassis Cover Screws Removing the Chassis Cover Setting Mode SwitchesESX Mode Switch Location/Component Layout Setting Mode Switches Nvram Reset Switch Nvram Reset SwitchLocating SIMMs Simm UpgradesInstalling SIMMs Installing the Flash Simm Installing the Sdram or Ldram Simm Brim Connection Installing the ESXTabletop or Shelf Installation Tabletop or Shelf InstallationRackmount Installation Rack Mounting the ESX 12 Installing the ESX in the Rack Connecting to the Power SourcePRE-NETWORK Installation Test 13 Pre-Installation Test Connecting a Twisted Pair Segment to the ESX-1320 Connecting to the Network14 ESX-1320 Twisted Pair Connection 15 Cable Pinouts RJ45 Crossover Cable Connecting a 10BASE-F Segment to the ESX-138016 ST Connector Insertion Using Lanview Chapter TroubleshootingTroubleshooting Using Lanview Troubleshooting Checklist Troubleshooting Checklist Reset Button Using the Reset ButtonLCD Using the LCDUnsaved Initialization Messages From the last Static System message Static System MessagesStatic System Messages Displayed Messages Comments From the product name display Alarm MessagesDisplayed Messages Comments Saved System MessagesFrom an Alarm Message display Failure or Error Messages COM Port 1 and COM Port Appendix a SpecificationsFunctionality Physical Properties Electrical SpecificationsEnvironmental Requirements Regulatory10BASE-T Twisted Pair Network Appendix B Ethernet Cabling RequirementsNetwork Requirements Appendix B Ethernet Cabling Requirements Multimode Fiber Optic Network ESX-1320/ESX-1380 Installation Guide Numerics IndexIndex-2 ESX-1320/ESX-1380 Installation Guide ESX-1320/ESX-1380 Installation Guide Index-3 Index Index-4 ESX-1320/ESX-1380 Installation Guide Power Supply Cord