The FB1000 detects and reports several events and conditions that are considered errors. The FB1000 will stop any run in process and display "ERROR XX" where XX is one of the below listed errors. When the FB1000 is displaying an error indication, press the gray ON/OFF key to clear the error and return to setup mode, or press the Run key to resume the run (after correcting the cause of the error). Note that loss of AC power during a run is considered an error condition. Always stop a run before turning off AC power to the FB1000.

'XX'

Condition and possible remedy

00

Minimum load current detected. The output is not connected, or the

20

electrophoresis apparatus is not set up properly. Check your setup and

connections.

 

01

Maximum load current exceeded. The output is short circuit, or the

21

electrophoresis apparatus is not set up properly. Check your setup and

connections

 

02

Step load current change. The FB1000 has detected a large change in load

 

current. Check your setup and connections

04

Loss of AC power, automatic recovery from power fail disabled, run not

 

completed. The FB1000 detected loss of AC power and didn’t complete run.

05

Loss of AC power; run not timed. The FB1000 detected loss of AC power.

06-99

The FB1000 detected an internal error condition. Contact technical support

 

for instructions.

Before servicing the unit, be sure to always turn off AC power using the switch at the rear of the unit, and then disconnecting the AC line cord. The FB1000 power supply requires no periodic servicing and should provide years of trouble free operation. Should you need to replace the fuses proceed as follows:

Replacing a fuse

CAUTION: The FB1000 uses double pole neutral fusing.

Turn off AC power using the switch at the rear of the unit, and then disconnecting the AC line cord. Remove the fuse holder assembly using a small flat blade screwdriver. Always replace both fuses with appropriate replacement fuses: 5A, 250V, 5X20mm, type T fuse (T5A,250V) (Fisher catalog number FB-FUSE-3).

FB1000-2 MANUAL

Page 10

7608177 Rev. A 8/9/02

Image 11
Contents Operator’s Manual FB1000-2 Electrophoresis Power SupplyTable of Contents Fisher Biotech FB1000 Electrophoresis Power SupplySafety Considerations Introduction Unpacking the Power SupplyEnvironmental SpecificationsAC input Power DC output PowerGetting Started Using the Power SupplyConstant Current Operations Constant Power OperationsConstant Voltage Operations Programming Automatic Power-fail RestartTimed Operations Volt-Hour OperationsFB1000-2 Manual 100V / 200mA Prev CleaningMethod Next Steps Prev Edit Method 1 1/2 NextReplacing a fuse Troubleshooting and Error IndicationsCompliance FB1000 Warranty StatementReplacement Parts Table des matières Considérations de sécurité Caractéristiques Déballage de l’alimentation électriqueCourant de sortie CC SpécificationsCourant d’entrée CA EnvironnementUtilisation de l’alimentation électrique Mise en routeOpérations à intensité constante Opérations à tension constanteOpérations en volts-heures Opérations à puissance constanteOpérations à durée déterminée Programmation Redémarrage automatique en cas de coupure de courantFB1000-2 Manual 150W Add NettoyageMethod Next Steps PrevDépannage et indications d’erreur Remplacement d’un fusibleFisher Scientific Park Lane Pittsburgh, PA 15275 USA Garantie du FB1000Conformité Pièces de rechangeInhaltsverzeichnis Fisher Biotech FB1000 Elektrophorese-NetzteilSicherheitstechnische Hinweise Auspacken des Netzteils EinführungGleichstromausgangsleistung Technische DatenNetzeingangsleistung UmfeldbedingungenVerwenden des Netzteils EinstiegBetrieb bei Dauerstrom Betrieb bei DauerspannungVoltstundenbetrieb Betrieb bei DauerleistungZeitgesteuerter Betrieb Programmierung Automatischer Neustart bei StromausfallMethod 1 1/2 Next 100V / 200mA Prev 150W Add 010 Edit 150W Hinzuf 010 Bearbeiten ReinigungAuswechseln einer Sicherung Fehlersuche und FehlermeldungErsatzteile FB1000 GarantieerklärungKompatibilität Contenido Consideraciones de seguridad Desembalaje de la fuente de alimentación IntroducciónPotencia de salida de CC EspecificacionesPotencia de entrada de CA MedioambientalesUso de la fuente de alimentación Para empezarOperaciones a corriente constante Operaciones a voltaje constanteReinicio automático tras un fallo en la alimentación Operaciones a potencia constanteOperaciones temporizadas Operaciones en voltios-horaProgramación FB1000-2 Manual Método 1 1/2 Next LimpiezaMétodo Next Pasos PrevCondición y posible solución Diagnóstico e indicaciones de errorConformidad Conformidad EMC Compatibilidad electromagnética Declaración de garantía del FB1000Fisher Scientific Park Lane Pittsburgh, PA 15275, EE.UU Piezas de repuestoFB1000-2 Electrophoresis Power Supply Part No Rev a