Liebert XDH manual Installation Considerations, Room Preparation

Page 7

Introduction

2.5Installation Considerations

The Liebert XDH is designed for placement within a row of computer cabinets in the data center in a hot-aisle-cold-aisle arrangement. The Liebert XDH is 12" (305mm) wide, so it takes up little space. For installation arrangement, see 4.2 - Installing the Liebert XDH Within the Enclosure Row. Be sure to follow all applicable codes.

Determine whether the Liebert XDH includes the condensate detection option (factory-installed). This option will require separate low voltage connections to a monitoring unit. A front panel alarm and indicator alert the user to condensation inside the unit. To minimize the possibility of condensa- tion, insulate all piping between the Liebert XDH and the Liebert XDP or Liebert XDC.

If the Liebert XDH is installed at the end of a row, Liebert recommends using uni-directional air dif- fusers to direct cooling air into the cold aisle, toward the equipment racks. If the Liebert XDH is installed between racks within a row, Liebert recommends using bi-directional air diffusers, directing the cooling air toward the equipment racks on either side of the Liebert XDH.

Table 1

Application limits

 

 

 

 

 

Input Voltage

Range of Return Air Conditions to Unit

 

 

 

 

Minimum

Maximum

Dry Bulb Temperature

Relative Humidity

 

 

 

 

-10%

+10%

60° to 100°F (16° to 38°C)

20% to 80%

 

 

 

 

2.5.1Room Preparation

The room should be well-insulated and must have a sealed vapor barrier. The vapor barrier in the ceiling and walls can be a polyethylene film. Paint on concrete walls and floors should contain either rubber or plastic.

NOTE

The vapor barrier is the single most important requirement for maintaining environmental control in the conditioned space.

Outside or fresh air should be kept to a minimum when temperature and humidity must be tightly controlled. Outside air adds to the cooling, heating, dehumidifying and humidifying loads of the site. Doors should be properly sealed to minimize leaks and should not contain ventilation grilles.

3

Image 7
Contents Liebert XDH Fluorinated Greenhouse Gas Requirements-European Union General Safety GuidelinesTable of Contents Specifications MaintenanceOperation Liebert XDH component locations Example XDH32BKParts Included With the Liebert XDH Pre-Installation ChecksProduct Description ReferencesRoom Preparation Installation ConsiderationsChecking and Unpacking Product/System DescriptionRecyclable Packaging Equipment InspectionUnpacking the Unit Unit HandlingPrepare ramp to remove the Liebert XDH from shipping pallet Taking the Unit off the PalletAttaching ramp, removing the Liebert XDH from pallet Installing the Liebert XDH Within the Enclosure Row Determining Placement in the Conditioned SpaceXDH Airflow DirectionChange airflow direction Install Air Diffusers for Best Airflow DirectionEuropean Union Fluorinated Greenhouse Gas Requirements System Connection ConfigurationTypical Liebert XDH piping-non-interlaced connection Indirect system configuration-hydraulic system schematic Connection Methods and Points Hard pipe connection diagramPiping Considerations-Hard-Piped Connections Venting the Holding Charge and Connecting to MainsRear of Liebert XDH Brazing Preparations Connecting Methods-One-Shot ConnectionsConnection Methods for Hard Pipe Recommended Piping SizeDegree Connection Header System Connecting Liebert XD Flex Pipes to Liebert XDH ModulesTools Required Liebert XD prefabricated piping assembly Tools Required Insulation Return Line Service Valve SupplyElectrical Connecting High Voltage WiringCondensate wiring entry points Connecting Low Voltage Wiring-OptionalCharging with Refrigerant and Starting the Liebert XD System Checklist for Proper InstallationOperation Start the Liebert XDHFluorinated Greenhouse Gas Requirements Internal AccessRemove fan tray Remove Fan TraySpecifications Liebert XD Flex Pipe assemblies, supply and return Page Ne t