Liebert manual Piping Considerations-Hard-Piped Connections, Rear of Liebert XDH

Page 20

Piping

5.4Piping Considerations—Hard-Piped Connections

Refrigerant enters and exits the Liebert XDH through connections on the top of the unit (see Figure 16).

The supply piping for each refrigeration circuit is 1/2" OD copper pipe. The return piping for each cir- cuit is 7/8" OD copper. Each Liebert XDH has two supply connections and two return connections, one for each refrigeration circuit.

The Liebert XDH units that are intended for hard-piping connections will have copper caps soldered in place and a holding charge of nitrogen.

Figure 16 Supply and return—hard-piping connections

Top of Liebert XDH

6"

 

 

 

 

 

 

 

 

(153mm)

3-5/8"

1/2" Supply, Upper

7/8" Return, Upper

 

(92mm)

 

Refrigeration Circuit

 

 

Refrigeration

 

 

 

 

Circuit

 

 

1-3/8" (35mm)

 

 

 

Detail “A”

 

 

2-1/8"

 

 

 

 

 

 

 

 

(54mm)

 

 

 

 

4-1/8"

 

 

 

 

(105mm)

5"

Rear of

 

 

(127mm)

 

 

 

 

Liebert XDH

 

 

 

 

7/8" Return, Lower Refrigeration Circuit

Rear of Liebert XDH

1/2" Supply, Lower

Detail "A" Refrigeration Circuit

5.4.1Venting the Holding Charge and Connecting to Mains

After the piping for the supply and return mains has been installed, the Liebert XDH units may be connected. The Liebert XDH is shipped with a low-pressure holding charge (about 30 psi) of nitrogen to prevent oxidation and moisture. Holding charges must be vented from the upper refrigeration circuit and from the lower refrigeration circuit.

To vent the holding charge:

1.Find the four Schrader valves that retain the nitrogen holding charge in the Liebert XDH. The valves are inside the rear door, one on each supply line and one on each return line. Three are near the top of the Liebert XDH; one Schrader valve is in the bottom half of the Liebert XDH.

2.Vent the holding charge in the upper refrigeration circuit by depressing the pin in a Schrader valve on either the supply or return line for that circuit. (The upper circuit’s lines are on the left side of the unit.)

3.Replace and secure the cap on the Schrader valve that was opened.

4.Vent the holding charge in the lower refrigeration circuit by depressing the pin in a Schrader valve on either the supply or return line for that circuit. (The lower circuit’s lines are on the right side of the unit.)

5.Replace and secure the cap on the Schrader valve that was opened.

6.Use a torch to unsweat the caps on unit’s piping connections.

7.Pipe the Liebert XDH’s supply and return connections to the mains. See 5.4.2 - Brazing Preparations for precautions about connecting the Liebert XDH to the piping mains.

16

Image 20
Contents Liebert XDH General Safety Guidelines Fluorinated Greenhouse Gas Requirements-European UnionTable of Contents Operation MaintenanceSpecifications Example XDH32BK Liebert XDH component locationsPre-Installation Checks Product DescriptionReferences Parts Included With the Liebert XDHInstallation Considerations Room PreparationProduct/System Description Checking and UnpackingEquipment Inspection Recyclable PackagingUnit Handling Unpacking the UnitTaking the Unit off the Pallet Prepare ramp to remove the Liebert XDH from shipping palletAttaching ramp, removing the Liebert XDH from pallet Determining Placement in the Conditioned Space Installing the Liebert XDH Within the Enclosure RowAirflow Direction XDHInstall Air Diffusers for Best Airflow Direction Change airflow directionSystem Connection Configuration European Union Fluorinated Greenhouse Gas RequirementsTypical Liebert XDH piping-non-interlaced connection Indirect system configuration-hydraulic system schematic Hard pipe connection diagram Connection Methods and PointsRear of Liebert XDH Venting the Holding Charge and Connecting to MainsPiping Considerations-Hard-Piped Connections Connecting Methods-One-Shot Connections Connection Methods for Hard PipeRecommended Piping Size Brazing PreparationsDegree Connection Tools Required Connecting Liebert XD Flex Pipes to Liebert XDH ModulesHeader System Liebert XD prefabricated piping assembly Tools Required Return Line Service Valve Supply InsulationConnecting High Voltage Wiring ElectricalConnecting Low Voltage Wiring-Optional Condensate wiring entry pointsChecklist for Proper Installation Charging with Refrigerant and Starting the Liebert XD SystemStart the Liebert XDH OperationInternal Access Fluorinated Greenhouse Gas RequirementsRemove Fan Tray Remove fan traySpecifications Liebert XD Flex Pipe assemblies, supply and return Page Ne t