Step Task (continued)
3.Slide the power supplies into their slots until the module front is flush with the shelf front.
Figure 13 Insert power supply
4.Connect the Power Supply cord to the designated socket (Figure 11).
5.
6.Secure the retainer by tighten the locking screws on either side of the retainer.
Danger: Leakage Current (High Touch Current) in
AC Power Supply and Fan Operability Test
Once your power supplies and fan trays are installed, verify their operability by supplying power to the chassis and verifying the status LEDs.
Before you begin this power test, inspect your equipment rack and chassis. Verify that:
•Each Power Supply is properly installed and plugged into the assigned slot.
•The
Danger: Prevent exposure and contact with hazardous voltages. Do not attempt to operate this system without the
•Your power cables connect to an appropriate AC power supply in a manner that complies with your local electrical codes. For AC systems, a Main Disconnect must be provided for each AC cord.
Installing and Maintaining the E1200i System | 37 |