Chapter 2
Installation
This chapter describes the basic installation procedures for the MBE unit, including:
•Site requirements and prerequisites
•Package contents
•Equipment needed
•Installation and setup.
| 2.1 Introduction |
| MBE is delivered completely assembled. For instructions on installation of a single |
| unit or two units in a |
| guide that comes with the RM kit. |
| After installing the unit, see Chapter 3, Operation for operating instructions. |
| In case a problem is encountered, refer to Chapter 4 for fault isolation and |
| troubleshooting instructions. |
Note |
|
Any adjustments, maintenance or repairs should be performed only by a skilled | |
| technician who is aware of the hazards involved. |
| Always observe standard safety precautions during installation, operation, and |
| maintenance of this product. |
2.2 Site Requirements and Prerequisites
Inspect the equipment container before unpacking. Note and report evidence of damage immediately to your RAD distributor.
Install the MBE unit within 1.5m (5 ft) of a grounded AC outlet furnishing 240V (115V).
Allow at least 90 cm (36") of frontal clearance for operator access. Allow at least 10 cm (4") clearance at the rear of the unit for interface cable connections.
The ambient temperature should be regulated between 0° to 50°C
(32°F to 122°F) at a relative humidity of up to 90%,
| Site Requirements and Prerequisites | |