Nortel Networks 555-7101-217, P0605618 manual To connect the 1001rp DC server to power

Page 71

May 2003

Installing the server and connecting the peripheral devices

To connect the 1001rp DC server to power

DANGER

Risk of electrical shock

ÑOnly qualified personnel can alter electrical connections.

Ensure the PDU is turned off until you are instructed to turn it on.

1Connect the DC power cable to the server, as shown below:

 

Receptacle for

 

positive and

 

negative plug

Negative

Positive

cable (black)

cable (red)

 

Posts for

Ground wire

ground wire

 

(green)

 

 

G101737

Part 2: 1001rp Server Hardware Installation

71

Image 71
Contents CallPilot P0605618 CallPilot Page Publication history Publication history Contents Index Installing the server and connecting the peripheralDevices A p t e r 1001rp server description49.5 cm 19.5 Server featuresServer dimensions and weight IntroductionAlarm board Front panel features front view without the front bezelRear panel diagram Overhead view of empty server showing PCI and ISA connectors 1001rp slot assignments Slot assignmentsSlot definition and slot numbering Clan Network card Slot 12b Single Board Computer SlotReserved for COM1 COM2 I/O bracket Slot Elan Network card SlotBRD20 IRQ mapping table IRQ Network connectivity Customer LAN optional Sample network setup MeridianTelephony LAN/Customer LAN 10/100BaseT or 100BaseT Sample network setup Succession CSECallPilot Elan and Clan network setup Switch connectivityNetwork requirements Remote access connectivityAlso supported, but has been replaced by the 56 Kbps Supported peripheral devicesModem Kbps external modem NTRH9078 provides Since the modem is an external device, it requires its ownPreparing for installation Installation checklist Installation overviewMay 2003Preparing for installation Conventions for warnings To unpack the equipment Follow this procedure to unpack the server and peripheralsUnpacking the 1001rp server What’s next? About the front bezel doors Removing the front bezel and server coverTo remove the front bezel Continue with Inspecting the server interior on To remove the server coverHigh current inside the chassis can cause severe injury To replace the front bezel after installation is complete To inspect the server interior Inspecting the server interiorPreparing for installationStandard Power supply installation Equipment handling guidelines Safety precautionsSafety information Section a Installing the power supply modules AC or DC AC versus DC systems Installing the second power supply module AC or DCAbout the power supply module Power supply modules Do one of the following To install the power supply moduleSection B Setting up DC power source for a 1001rp DC server DC wire gauge tables Metric wire conversion DC rack cabling Following diagram shows typical rack power cabling48VDC power distribution rationale Multiple PDUs About the Power Distribution UnitDC power input PDU terminal blocks and wiring diagramTo bring DC power and ground into the PDU Bringing power and ground into the PDUMay Power supply installation Installing the server and connecting the peripheral devices To install the server Installing the serverRequired equipment Preparing the modemDIP Modem DIP switchesTo set the modem DIP switches OFF Disables command recognition dumb OFF The modem sends a CD signal when itOFF Loads Y or Y1 configuration from AT command set recognitionRear panel connections Connecting peripherals to the serverTo connect the modem to the server To connect the mouse, keyboard, and monitor to the serverContinue with Connecting the server to the Elan on To connect the server to the Elan Connecting the server to the ElanMedia Access Control address Feature key adapter dongle. See To connect the server to the Clan Connecting the server to the Clan optionalWhat’s next? Installing the Nortel Networks software feature key adapter Requirements To install the software feature key adapterFor installation, you require a Phillips No screwdriver Continue with Connecting the server to power onBefore you begin Connecting the server to powerCallPilot server To connect the 1001rp AC server to power Connect the DC power cable to the server, as shown below To connect the 1001rp DC server to powerTo start the server Binder Installing the server and connecting the peripheral devices Index Clan Elan May Index Index Page Product release Document release Standard Date May