In this fashion, with dual hot-swappable power supplies, there is no single point of failure in the power system. For example, you can remove any power supply, including a PDU, and everything continues to work.
This is applicable to either North American or European installation sites Ñ(with a 230 VAC Inverter).
The secondary rack supports four servers and follows a similar scheme.
Each server receives a feed from each PDU and a different branch circuit.
ÑEach PDU receives four branch circuits.
DC-powered configuration fits into this scheme as follows:
The customer must be able to shut off any branch, and every unit at the Ñsite will continue to function properly.
Ñ
Minimum installation is one Power Distribution Unit (PDU) with four 48VDC branch circuits fused at 20 amperes.

May 2003

Power supply installation

-48VDC power distribution rationale

Part 2: 1001rp Server Hardware Installation

47

Image 47
Contents CallPilot P0605618 CallPilot Page Publication history Publication history Contents Index Installing the server and connecting the peripheralDevices A p t e r 1001rp server description49.5 cm 19.5 Server featuresServer dimensions and weight IntroductionAlarm board Front panel features front view without the front bezelRear panel diagram Overhead view of empty server showing PCI and ISA connectors 1001rp slot assignments Slot assignmentsSlot definition and slot numbering Clan Network card Slot 12b Single Board Computer SlotReserved for COM1 COM2 I/O bracket Slot Elan Network card SlotBRD20 IRQ mapping table IRQ Network connectivity Customer LAN optional Sample network setup MeridianTelephony LAN/Customer LAN 10/100BaseT or 100BaseT Sample network setup Succession CSECallPilot Elan and Clan network setup Switch connectivityNetwork requirements Remote access connectivityAlso supported, but has been replaced by the 56 Kbps Supported peripheral devicesModem Kbps external modem NTRH9078 provides Since the modem is an external device, it requires its ownPreparing for installation Installation checklist Installation overviewMay 2003Preparing for installation Conventions for warnings To unpack the equipment Follow this procedure to unpack the server and peripheralsUnpacking the 1001rp server What’s next? About the front bezel doors Removing the front bezel and server coverTo remove the front bezel Continue with Inspecting the server interior on To remove the server coverHigh current inside the chassis can cause severe injury To replace the front bezel after installation is complete To inspect the server interior Inspecting the server interiorPreparing for installationStandard Power supply installation Equipment handling guidelines Safety precautionsSafety information Section a Installing the power supply modules AC or DC AC versus DC systems Installing the second power supply module AC or DCAbout the power supply module Power supply modules Do one of the following To install the power supply moduleSection B Setting up DC power source for a 1001rp DC server DC wire gauge tables Metric wire conversion DC rack cabling Following diagram shows typical rack power cabling48VDC power distribution rationale Multiple PDUs About the Power Distribution UnitDC power input PDU terminal blocks and wiring diagramTo bring DC power and ground into the PDU Bringing power and ground into the PDUMay Power supply installation Installing the server and connecting the peripheral devices To install the server Installing the serverRequired equipment Preparing the modemDIP Modem DIP switchesTo set the modem DIP switches OFF Disables command recognition dumb OFF The modem sends a CD signal when itOFF Loads Y or Y1 configuration from AT command set recognitionRear panel connections Connecting peripherals to the serverTo connect the modem to the server To connect the mouse, keyboard, and monitor to the serverContinue with Connecting the server to the Elan on To connect the server to the Elan Connecting the server to the ElanMedia Access Control address Feature key adapter dongle. See To connect the server to the Clan Connecting the server to the Clan optionalWhat’s next? Installing the Nortel Networks software feature key adapter Requirements To install the software feature key adapterFor installation, you require a Phillips No screwdriver Continue with Connecting the server to power onBefore you begin Connecting the server to powerCallPilot server To connect the 1001rp AC server to power Connect the DC power cable to the server, as shown below To connect the 1001rp DC server to powerTo start the server Binder Installing the server and connecting the peripheral devices Index Clan Elan May Index Index Page Product release Document release Standard Date May