American Power Conversion AP9604S manual Intersystem Synchronization Unit

Page 55

Options/Accessories

6.3Intersystem Synchronization Unit

Intersystem Synchronization Unit System (ISU System)

The ISU system consists of inter-connected ISUs. One ISU system may consist of up to 5 ISUs, regardles of ISU configuration. The ISU system synchronizes the voltage of parallel operation systems running in battery operation.

The ISU system may also include one or more external synchronization sources, e.g. a gen-set or a non-APC Silcon UPS system.

Synchronization accuracy of the ISU is better than 2o.

Schematic overview of ISU system (example):

UPS 1A

UPS 3A

UPS 1B

Parallel

Operation

System 1

ISU

1

ISU

3

Parallel

Operation

System 3

UPS 1C

UPS 2A

 

ISU System

UPS 3C

UPS 2B

Parallel

Operation

System 2

ISU

2

ISU

4

ISU

5

UPS 2C

UPS 4

Ext. sync Source

UPS 3B

Intersystem Synchronization Unit (ISU)

The ISU is an active part of an ISU system, serving as the interface to the sources and the ISU system.

The ISU can be connected to a parallel UPS configuration, using the standard parallel communication controller in the parallel operation system.

(See Intersystem Synchronization Unit User’s Manual for further details.)

6.4

990-4056

Installation Guide APC Silcon 240-320kW 400V UPS

55

Image 55
Contents 240-320kW 400V UPS Installation Guide Safety Symbols used in this manual Installation Guide APC Silcon 240-320kW 400V UPSThank You Tools IntroductionIntroduction Tools and EquipmentUnpacking UnpackingHeight mm Width mm Depth mm InstallationInstallation Requirements on SiteFootprint 2 825mm Cabinet for Isolation Transformer or Switch Gear1 1600mm Cabinet for 240-320kW UPS 3 1600mm Cabinet for 320kW Isolation Transformer Right side view Connecting the UPSExternal Connection External ConnectionOutput External External PE MaximumInput Cable External Fuses* FMSystem Integration Interface Connections X005 Output Relays Terminal Blocks X003/X004 Anxiliary ContactsParallel Board Parallel BoardExternal Control Cables Power CablesRelays Relay BoardRelay Board/Relay Functions Relay Number Message Alarm-trigging EventsSee .2 System configuration Communication Interface Board Connecting of APC Silcon Tripel Chassis Monitoring Port Safety WarningsAPC Silcon Triple Chassis Product DescriptionIf the LED is… Then the Silcon Triple Chassis… Optional Power InputInstalling Management Peripherals LEDsDaisy-chaining the APC Silcon Triple Chassis Installing Management Peripheral CardsOrder of Management Peripheral Cards Management Peripheral Priority Position CardManagement Peripheral Draw mA Problem Possible Cause Solution TroubleshootingIf Problems Persist Product Specifications Monitoring Port Pin Assignments External Connection Specification Power, Physical, and Environmental SpecificationsImportant Safety Instructions APC Silcon Battery CabinetsInstallation of Batteries Battery Breaker Box/Fuse-boxSilcon Battery Breaker Box Circuit Ampere Connection Max Dimensions Weight Rating CableAPC Battery Breaker Box Connection Diagram 120-480kW HxWxD mmExternal Connection Parameters Parameter Setting CommentsProgramming Parameters Programming ParametersProgramming Keys Programming Example Switch to Bypass Operation System ConfigurationSystem Configuration Parameters password protected Programming Example Change Charge Voltage to Programming Parameters Programming Parameters for Advanced Parallel Operation Description of SettingsProgramming example Battery MonitorProgramming Parameters Options/Accessories Options/AccessoriesService Bypass Panel for Single Operation Options/Accessories Lamp indication On Service Bypass PanelAction Display showsLamp indication On Servive Bypass Panel Switching from External Bypass to Normal UPS OperationService Bypass Panel for Parallel Redundant Operation Two Parallel Systems with Service Bypass Panel Options/Accessories Options/Accessories Display shows H002a Lamp indication On Service Bypass Panel Following can be carried out on any UPS Switching Back to Normal Parallel/Redundant Operation Isolating One UPS for Service/MaintenanceIntersystem Synchronization Unit System ISU System Intersystem Synchronization UnitIntersystem Synchronization Unit ISU Extension of Remote Display Communication Distance Remote DisplayStandard Short-haul RS232 Modem Async Pin Connections for cable from host to ME800A-R2 Host Connections Without ConverterHost DTE Remote Display DTE Connections With ConverterRemote Display Cables Remote Display Power SupplyRemote Display Use Communication FaultRemote Display Setting AlarmsIsolation Transformer Height Width Depth WeightIsolation Example of Transformer Configuration Yyno 630 200 150 Connecting Isolation TransformerPE Cable 370kWOptions/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories Dimensions / Weight System SpecificationsSystem Specifications Technical DataWarranty WarrantyAPC Silcon Series Limited Factory Warranty Appendix Installation Planning DataAppendix Appendix APC Denmark How to Contact APCHow to Contact APC APC Corporate