Stack configuration

The UPS and the XLBBP(s) must be connected with ground wires. Refer to the XLBP user manual for details.

Always place the UPS above the XLBP(s) in a stack configuration.

Total stack configuration height is recommended NOT to exceed 18U. This is the equivalent of two XLBPs and one UPS.

Four screws must be used to secure each tie bracket to the units, (see diagram).

For detailed instructions on installing batteries, the battery doors, refer to the Rack-mount configuration section of this manual.

Refer to the Rack-mount configuration section in this manual for cable routing and bezel installation details.

8x

Tie Brackets (included with XLBP)

Rack-mount configuration

Install rack-mount brackets

Four flat head screws must be used to secure each rack-mount bracket to the unit.

4x

Install rail cleats

Two pan head screws must be used to secure each rail cleat to the unit.

2x

Install rails in rack.

For details on rail installation refer to the instructions included in the rail kit package.

Mount units in rack

The UPS and XLBP should be installed at or near the bottom of the rack. Always place the UPS above the XLBP(s). Batteries must be removed from the XLBP(s) prior to installing the unit(s) in a rack. Refer to the instructions on the packaging for details on removing the batteries from the XLBP.

4

Smart-UPS RT 15000/20000 VA 230 Vac Stack/Rack-Mount 6U User Manual

Image 8
Contents XLI/XLICH Page Contents Page Unpack package contents About this UPSSpecifications Environmental SpecificationsPhysical Specifications Maximum Number of XLBPs Supported by the Smart-UPS XLInstallation Stack or rack-mount front panelStack configuration Rack-mount configurationInstall units in rack Install and connect battery modulesRoute ethernet cable and install bezels Accessories Optional accessoriesInstall the wiring trays, refer to graphics below Install input and output wiring trays in UPS rear panel XlbpWiring Specifications Adhere to national and local electrical codes when wiringInput wiring options Input/Output Jumper ConfigurationsSingle phase input, single phase output, single feed Single phase input, single phase output, dual feedThree phase input, single phase output, single feed Three phase input, three phase output, single feedThree phase input, single phase output, dual feed Three phase input, three phase output, dual feedOutput wiring options L3 L2 L1 OSJSingle phase output connection to battery pack PDU PowerView Interface Display OperationNavigating menu screens Main Menu ScreenMenu Tree Navigating sub menu screensSub menu screens SystemExternal Battery Pack Communication Ports Connect power to UPS and loadConnect load to UPS Emergency Power Off EPO ConnectorTroubleshooting Display Messages Output Jumper Configurations tablePage Refer to Contact Information in this Option 2 Correct bypass input Service Maintenance, Transport, and ServiceReplace battery modules Two-Year Warranty Terms of warrantyRegulatory Agency Approvals and Radio Frequency Warnings ModelsDate of product declaration