8e6 Technologies HL-022-002, HL-002-002 Install the SL or HL Server Bezel, Front of bezel

Page 18

Install the SL or HL Server Bezel

After rack mounting an SL or HL server, the bezel should be installed on the front end of the chassis.

NOTE: This portion of the installation process requires you to unpack the bezel. The bezel has been packaged separately from the unit to prevent damage during shipping.

A. Hold the bezel upright and facing towards you (Fig. 1).

Fig. 1 - Front of bezel

B. Note that each end of the bezel contains two raised bumps (Fig. 2).

Fig. 2 - Bumps on right end of bezel

Fig. 3 - Grooves in right U-shaped handle

C.Align these bumps along the two parallel grooves inside each U-shaped aluminum chassis handle affixed to the front end of the chassis rail (Fig. 3).

D.Push the bezel towards the front of the chassis, inserting the USB B-type plug on the back of the bezel (Fig. 4) into the USB port on the chassis.

Fig. 4 - Section of back of bezel with USB B-type plug

14

8e6 Enterprise Reporter Quick Start Guide

Image 18
Contents Guide 8e6 Enterprise Reporter Quick Start Guide Contents Regulatory Specifications and Disclaimers Appendix Scsi Connected Storage DeviceIndex ER Enterprise Reporter Introduction About this Document Conventions Used in this DocumentProcedures 8e6 Corporate Headquarters USA8e6 Taiwan Unpack the Unit from the Carton Select a Site for the Server Rack Setup Precautions Rack Mount the ServerInstall the Outer Rails Rack Setup SuggestionsInstall the Inner Rails Rack Mount Instructions for HL Servers8e6 Enterprise Reporter Quick Start Guide Install the Server into the Rack Install the Server into a Telco Rack Install the Inner Slides Install the Outer SlidesRack Mount Instructions for SL Servers Install the Slide Assemblies to the Rack Install the Chassis into the Rack Install the SL or HL Server Bezel Front of bezelCheck the Power Supply Power Supply PrecautionsGeneral Safety Information Server Operation and Maintenance PrecautionsAC Power Cord and Cable Precautions Electrical Safety PrecautionsMotherboard Battery Precautions Administrator Console Setup Requirements Setup ProceduresQuick Start Setup Requirements LCD Panel Setup RequirementsMonitor and Keyboard Setup Quick Start Setup ProceduresStorage Device Setup for Attached Storage Units Serial Console SetupDiagram of SL chassis front panel, power button at far right HyperTerminal Setup Procedures 8e6 Enterprise Reporter Quick Start Guide 8e6 Enterprise Reporter Quick Start Guide Login screen Quick Start menu screenQuick Start menu administration menu System Status screen Log Off, Disconnect the PeripheralsConsole Setup Procedures Preliminary SetupWorkstation Configurations Left Boot Up Process Network Setup Access the InternetLog in to the Administrator Console Network Settings 8e6 Enterprise Reporter Quick Start Guide Regional Setting Time Zone Regional Setting Language Regional Setting NTP ServersPhysically Connect the ER to the Network LCD Panel Setup Procedures LCD Menu8e6 menu Current Patch Level LAN 1 Link StatusGateway DNS 1Regional Setting Time Zone, date, time Host NameLCD Options menu Reset Admin Console PasswordReboot ShutdownHeartbeat BacklightLCD Controls Change User Name and Password, Set Self- Monitoring Access the InternetChange User Name and Password Enter a User Name and PasswordEnter the Master Administrator’s E-Mail Address Set Self-MonitoringR3000 Configuration Select 8e6 Enterprise Reporter, and then click SaveClient Workstation Configuration Launch the ER Client Enter the Password, and Confirm Password Conclusion Administrator Console, Expiration Screen ER Client, ER Server Statistics Window LED Indicator Key LED Indicator Color Condition DescriptionSL Unit HL Unit Rear LED Indicators for Hardware Status Monitoring HL and SL Units RAIDElectromagnetic Compatibility EMC Safety ComplianceDeclaration of the Manufacturer or Importer Models HL-022-002, HL-002-002, SL-002-002Electromagnetic Compatibility Class a Notice EC Declaration of Conformity Preliminary Setup Procedures Other Required Installation ItemsUnpack the Unit from the Carton Rack Setup Precautions Rack Mount the ServerRack Mount Components Step Step Step Install the Unit Link the ER Unit with the Scsi Connected DeviceShut Down, Restart Procedures Shut Down the Storage Device UnitRestart the Storage Device Unit Physical Components Temperature and Ventilation Status Power Supply StatusLED Display Silence Button Management AlarmDisc Drive Alarm Disk Drive ActivityIndex 8e6 Enterprise Reporter Quick Start Guide