SECTION 10: WIRING

SECTION 10: WIRING

DANGER

Electrical Shock Hazard

Disconnect electric before service.

Heater must be properly grounded.

Failure to follow these instructions can result in death or electrical shock.

FIGURE 22: Zone Sensor Wiring Diagram

Heater must be grounded in accordance with applicable codes: United States: refer to National

Electrical Code® NFPA 70 - latest revision Canada: refer to Canadian Electrical Code, CSA C22.1 Part I - latest revision.

If any of the original internal wiring must be replaced, it must be replaced with wiring materials having a temperature rating of at least 105°C and 600 Volts.

10.1 Standard Heater Configuration

From the factory, the heater is configured for zone sensor control. Connect zone sensor to the heater control as shown on Page 39, Figure 22.

If additional heaters are in the same heating zone, control wiring must be installed between the heaters’ controls as shown on Page 39, Figure 22.

For additional details or for use with heat demand control devices other than the zone sensor, see Page 40, Section 10.2 through Page 48, Section 10.4.9.

ZONE SENSOR

CENTRAL HEATER CONTROL

* Separate on/off switch is optional for

ON

OFF

SET SEN +FAN-

-LCD+

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

THERMOSTAT

 

 

T24

 

 

 

 

R

 

T25

 

 

 

 

W

 

T26

 

 

 

 

+

ANALOG

 

T27

INPUT

 

 

 

 

-

 

T13

 

THERMISTOR

 

T14

GND

 

 

 

T15

SLIDE BAR

 

T16

 

GND

 

 

 

 

 

T17

HIGH WIPER

 

 

T18

EXT. POT

 

T19

 

 

GND

 

 

T28

 

 

 

 

+

FIRING RATE

 

T29

IN

 

 

-

 

T30

 

 

 

T31

FIRING RATE + OUT -

A B

 

 

 

 

 

J10

"satellite" heaters (install at user level). On/

Off switch is used to disable heater operation

or reset a heater that is in "lockout" mode. If

on/off switch is not desired, leave jumper wire

between R and W terminals in place.

*OPTIONAL

SATELLITE HEATER CONTROL

SWITCH

 

 

 

 

THERMOSTAT

 

 

T24

 

 

 

 

R

 

T25

 

 

 

 

W

 

T26

 

 

 

 

+

ANALOG

 

T27

INPUT

 

 

 

 

-

 

T13

 

THERMISTOR

 

T14

GND

 

 

 

T15

SLIDE BAR

 

T16

 

GND

 

 

 

 

 

T17

HIGH WIPER

 

 

T18

EXT. POT

 

T19

MODULATION CONTROL WIRING

TO SATELLITE HEATERS

Description

Part Number

Zone Sensor, 40° - 75°

10081530

 

 

 

GND

 

 

 

 

 

 

 

 

 

 

 

 

 

T28

 

 

 

 

 

 

 

 

+

FIRING RATE

 

 

 

 

 

 

 

 

 

 

 

 

T29

IN

 

 

 

 

 

 

-

 

 

 

 

 

 

 

 

 

 

 

 

 

T30

 

 

 

 

 

 

 

 

+

 

 

 

 

 

 

 

FIRING RATE OUT -

A B

 

T31

 

 

 

 

J10

 

 

 

 

 

MODULATION CONTROL WIRING

TO ADDITIONAL SATELLITE

HEATERS CONTROL TERMINALS

T28 and T29.

39 of 71

Image 45
Contents Gas-Fired, Low Intensity Unitary Heater Page Roberts-Gordon LLC Page Table of Figures Page Manpower Requirements Heater SafetySafety Labels and Their Placement California PropositionTop and Bottom Panel Label Placement Side and Back Panel Label Placement Wall Tag Installer ResponsibilityCorrosive Chemicals National Standards and Applicable CodesInches Centimeters Model Maintain clearances to combustibles at all times for safetyONE Side Reflector Tube TUBE, Standard ReflectorUnapproved Foot Deco Grille and Protective GrilleNational Standards and Applicable Codes Major Components Model Tubing Length Core Packages Minimum Aluminized Standard Parts ListHeater Installation Typical Suspension Details Linear Heater Assembly Overview Linear Heater Layout Overview Tube Clamp Package Installation Burner Tube InstallationInsert tubes into coupling Tighten coupling to join tubes Coupling and Tube AssemblyTurbulator Installation 2 Coupling and Tube AssemblyHanger Burner Tube Reflector Reflector InstallationDescription Part Number Reflector Support Package 1 Reflector, U-Clip and Reflector Support InstallationWindow facing down Burner InstallationTube Configuration Optional Heater AccessoriesTube Heater Assembly Overview Tube Heater Layout Overview Elbow Package Configuration .2.1 Elbow Installation 2 Elbow Installation3 Reflector Joint Installation Reflector Joint Detail 4 Reflector Joint Installation 5 Reflector Joint DetailReflector Side Extension 2 Side Reflector InstallationScr ews 2 Frame Shield Installation 3 Grille Installation 2 Grille End Cap InstallationUnited States Requirements Canadian RequirementsUnvented Operation Vertical Venting Horizontal VentingUnvented Operation Tube Termination Length RequirementsCommon Side Wall Venting Vertical Ventilation 4 10 cm PipeCommon Vertical Venting Vertical Outside Air Supply for Single Heater Installation Outside Combustion Air SupplySide View TOP View Vertical Outside Air Supply for Double Heater InstallationGAS Piping Correct Positions Standard Heater Configuration WiringCentral and Satellite Heaters Zoning Capability Central Heater ConfigurationSatellite Heater Jumper Setting Satellite Heater ConfigurationCommunication Wiring within a Zone of Heaters Communication Wiring within a Zone of Heaters Heat Demand Control Wiring Zone SensorThermostat Analog Signal Modulating Thermostat P/N MS/TP WiringSequence of Operation for Modulating Thermostats Power Requirements Remote Analog SignalCable Termination Analog Control Signal Wiring Diagram Potentiometer Control Device Potentiometer Control Wiring DiagramThermostat, modulating Description Part Number Modulating Thermostat Wiring Diagram with BACnet optional Internal Wiring Ladder Diagram Electrical Connection to the Burner Line Voltage Power WiringLow Voltage Control Wiring Installation Pre-Season Maintenance and Annual Inspection Operation and MaintenanceSequence of Operation To Shut Off HeaterVicinity of the Heater Installation Code and Annual InspectionsVehicles and Other ObjectsSafety Labels MA wiring Suspension PointsGas Line Burner ObservationTroubleshooting General LED Codes Control LEDTroubleshooting Troubleshooting Flow Chart Troubleshooting Manifold Gas Pressure Measurement Pneumatic Connections Replacement Parts Replacement Parts Description Part Number Dimensions General SpecificationsGAS Pressure AT Manifold Pipe ConnectionPage ROBERTS-GORDON will PAY for Warranty is Void ifROBERTS-GORDON will not PAY for Limitations on Authority RepresentativesPage Page Page