SterlingTEK A0551797 manual Making Tank Piping Connections, From Process

Page 22

To Process

The chilled water supply outlet leading to the process being controlled.

From Process

The chilled water return for water returning back to the chiller from the process to be cooled and recirculated.

3-5 Making Tank Piping Connections

If you have purchased the SSC Series central chilling station with the integral pump tank, please proceed with this section.

Return

Bring the chilled water returning from the process to the pump tank warm From Process side. This line is sized according to the flow rate from the process to the pump tank. See Section 3-3 on Page 21 for more information on piping considerations.

Important!

Do not use the SSC Series unit to support piping.

Makeup

Connect a city water source to maintain water level in the pump tank.

Overflow

Connect the OVERFLOW outlet to an approved, trapped drain to permit excess water in the pump tank to overflow to the drain. The overflow line is sized according to the size of the pump tank.

To Drain

Connect to a 1½” line (approx. 63 mm) leading to an approved, trapped drain. You can drain the pump tank if necessary.

Page 22 of 86

SSC Series Central Chilling Stations

Image 22
Contents SSC Series Central Chilling Stations SSC Series Central Chilling Stations Safety Considerations Wear Safety Glasses and Work GlovesTable of Contents Startup Checklists Getting Started on the SSC Series Advanced TouchscreenCharts and Figures Introduction Necessary DocumentsStandard Features Models CoveredStandard Features on Remote Condensers Available OptionsModel Number Nomeclature Typical Two-Circuit 60-100 Ton Water Cooled Chiller Model SSCW-xxxCooling Capacity tons @ 50F 10 C LWT 73.1 81.4 Typical Two-Circuit 60-100 Ton Remote Air Cooled Chiller Model SSCR-xxxSscr Series Remote Condenser Models Unpacking and Inspection Event of Shipping DamagesIf the Shipment is Not Correct If the Shipment is Not CompleteReturns Uncrating Your New Chiller SSC Series Central Chilling Stations Installation Location Considerations 3Installation Making Electrical Connections SSC Series Central Chilling Stations Making Process Water Connections Piping ConsiderationsAll Models Making Tank Piping Connections From ProcessWater Treatment Considerations Water Connection Sizing ConsiderationsGalvanic Corrosion Considerations Making Water-Cooled Condenser ConnectionsInstalling the Remote Air-Cooled Condenser Condenser WaterChecking Motor Direction CompressorSSC Series Central Chilling Stations Lead-Lag Compressors AlarmsStaging Lead-Lag PumpsRefrigeration Circuit Chilled Water CircuitFreezestat Control Volume Freezing Protection CurveHigh Pressure Cutout Flow SwitchLow Pressure Cutout Chilled Water Manifold Control NippleControl Probe Condenser Water ManifoldSSC Series Central Chilling Stations Startup Checklists Water-Cooled SSC Series Startup ChecklistSSC Series Central Chilling Stations Remote Air-Cooled SSC Series Startup Checklist Water-Cooled SSC Series StartupSSC Series Central Chilling Stations Remote Air-Cooled SSC Series Startup Determining Flow Rate ShutdownSSC Series Central Chilling Stations SSC Series Central Chilling Stations Indicator Lights and Control Switches MMI Graphic Panel DevicesSSC Series Central Chilling Stations Touchscreen Interface Using the StandardTouchscreen Interface Introduction MMI Using the SSC Series Standard Touchscreen Interface SSC Series Standard Control PanelMain Menu Screen Viewing Compressor Status Viewing and Operating Chiller CompressorsCompressor Status Screen Chiller Configuration Screen Operating the chiller compressorsCompressor Enable Screen Compressor Lead/Lag ScreenViewing Compressor Run Times Compressor Run Time Display ScreenViewing Chiller Pump Status Viewing and Operating Chiller PumpsPump Status Screen Pump Enables Screen Operating Chiller PumpsPump Lead/Lag Screen Viewing Pump Run TimesPump Run Time Display Screen Viewing Active Alarms and Handling Alarm Conditions Alarm Condition ScreenOr Death Viewing and Setting System Temperatures Setting System TemperaturesSSC Series Central Chilling Stations Using the Advanced Using the SSC Series Advanced Touchscreen Interface Main Menu Screen Viewing and Operating Chiller Compressors Chiller Status Screen Operating the chiller compressors Viewing Compressor Run Times Viewing and Operating Chiller Pumps Viewing Chiller Pump Status Operating Chiller Pumps Hourmeters Pump Run Time screen displays Viewing Active Alarms and Handling Alarm Conditions Alarm Condition Screen Or Death System Status Screen Temperature Input Display Screen Condenser Maintenance LubricationMakeup Valve Evaporator MaintenancePump Motor Seal Recommended Pump Tank Spare PartsPreventive Maintenance Service SSC Series Central Chilling Stations 10Troubleshooting Problem Possible Cause SolutionAllow time to cool and reset Verify proper rotation if Service Notes Index Water Treatment Service Notes Service Notes Service Notes Parts Department Sterling Th Street New Berlin, WI 262 641-8610 ∙ Fax 262