C100 Installation Guide

Section 3 – Pre Installation Information

Physical installation of the console is normally carried out by a specialised transportation company. In some cases this will have been arranged by the local SSL office, in other cases by the facility.

The cables that run between console and processor can be shipped in advance of the console in a separate kit (the pre-install kit). These cables should be installed by the facility engineers. Instructions for installing these cables are found on pages 29 to 31 of this manual.

Note: Cables for the connection of ancillary functions, Meters, talkback, oscillator and any custom switches etc. are not supplied by SSL and will need to be provided by the facility. See pages 43–45 for wiring information.

Before the console is installed all building work should be completed and the environment MUST be clean otherwise the warranty will be rendered invalid.

Before commissioning can take place the following MUST be completed:

• Air Conditioning installed, tested, blown-through and working

• Lighting installed and tested

• Cable Trunking installed

• Wall and floor finishes completed

• Power Distribution installed and tested

• Cables installed and tested

• Monitor loudspeakers installed and working

• Other utilities (telephone, water etc.) available

Services provided by SSL

Commissioning

All C100 systems include on-site commissioning by an SSL engineer. This is usually expected to take from 2 to 4 days depending on system size, configuration and options. Large systems, or consoles split for shipment, may require an additional 1–2 days of commissioning time.

You will be contacted by your local SSL office or agent shortly before delivery to arrange a commissioning date.

Training

Two days of standard operator training are provided with each C100 system. If required, this is scheduled to take place immediately following the commissioning period and is usually carried out by the commissioning engineer. A further day of advanced operator training is available at additional cost.

On-site maintenance training is also available at additional cost. This can be either one day for a basic overview or two days for more advanced training.

Training should be requested at time of order. For all training, we recommend that no more than five persons attend each session. If the use of an interpreter is necessary the training period may need to be extended (at additional cost). Note that travel and subsistence costs are not normally included. Please contact SSL’s Training Department at: support@solid-state-logic.com.

Warranty

All systems normally include 13 months warranty from date of shipment. This does not include consumable items such as magnetic media, disks etc. Further details may be found in SSL’s Conditions of Trading (printed on the reverse of all SSL invoices).

Page 6

Image 10
Contents Installation Guide Page Solid State Logic Solid State Logic Contents Introduction Installation Instructions Safety Considerations Electrical Safety Warning Voltage Selection and FusingPhysical Safety Safety Earth ConnectionMains Supply and Phases Mains Isolation and Over-Current ProtectionCE Certification FCC CertificationWarranty Pre Installation InformationServices provided by SSL CommissioningRack Mounting Equipment Centuri, NetBridge and Stageboxes Physical RequirementsConsole Control Surface Acoustic IsolationSide Profile Showing Service Access Channel FootprintAir Conditioning Requirements Service AccessCable Ducting Centuri Processor Crate side view Showing Card Access SB Crate side view Showing Card AccessVideo Sync Source Power Connections Mains Input Voltage & CurrentTechnical Requirements GroundingC100 Channel Bay Layout EVSSystem Components C100 ConsoleCenturi Processor Crate Front View Centuri Processor Crate Rear ViewCenturi Processor System Disk Console Routing/Link Card InterfaceCenturi CPU Card Centuri DSP CardCenturi Disk Card Centuri Console Interface CardMic Input Analogue I/O Digital I/O +5VCenturi Digital I/O Card Centuri Micamp CardCenturi Analogue I/O Card Centuri Madi Card Copper versionSB Stagebox Front View Morse Router Morse 3U StageboxSB Stagebox option Morse System optionNetBridge Rear View NetBridge Front ViewNetBridge PSU Voltage Selection NetBridge option Location Of Bellypanel USB Connectors Loudspeaker Shelf option External Keyboard / Trackball optionsScript Tray option TFT External Input optionCenturi Mains Inlet Panel Console Mains Inlet PanelNetBridge Rear Panel Installation Wiring Power Supply ConnectionsAudio Console Connector Panel Control Surface Wiring Block DiagramCPU Card Control Card Centuri to Console Surface Connections PSU Status Wiring Diagram CPU CardPSU Status Sync SourceMicamp Input Card Analogue I/O CardMicAmp Card SSL ref Analogue input/output Card SSL refDigital I/O Card D25 version Madi I/O Card Copper versionDigital Input/Output Card 110Ω SSL ref XF Digital Input/Output Card 75Ω SSL ref XJGPI I/O Card GPI Output circuit GPI I/O SSL ref XAGPI Input circuit Centuri Link Card Fibre Link Connectors and PanelsSB Cabling Diagrams SB CPU CardStageboxes & Fibre Links NetBridge Installation TCP/IPRemote Diagnostics NetBridge InstallationAccess ConnectionC100 Console Talkback system Block DiagramCenturi Chassis Talkback Connections Talkback and OscillatorOscillator Connections Meter and Phasescope wiring RTW Meter and Phasescope wiring MSD 600CCenturi Crate Meters and Phasescope Gold is 1.9 times heavier than Lead Appendix a Specifications Centuri Processor Crate Net Bridge SB Micamp Rack PlugSocket Appendix B Connector DetailsDL 96-Pin Hood Varicon 56-pin Hood Free SocketType Multipin XLR 3-PinDIN 5-Pin 25-wayAppendix C Connector Pinouts C100 Console Meter Inputs AnaloguePhase Scope Digital MSD Diag Diagnostics / Remote ControlTimecode Connector Pinouts Centuri ProcessorMachine Control ExpansionTtya TTYD, Ttyf Ttyh RS422 SerialTtye RS232 Mic Input Card ‘908 Mic in 1Analogue I/O Card ‘904 Analogue in / Analogue OUTAES/EBU Out 1-8 9-16, 17-24 Digital I/O Card ‘902AES/EBU In 1-8 9-16, 17-24 BNC Breakout PanelGPI I/O Card ‘907 GPI Outputs 1 12 13 24, 25 36, 37 48, 49Serial 1-8 RS232 Connector Pinouts NetBridgeNetBridge Diagnostic Cable TerminalC100 Installation Guide Appendix D Audio Interfacing Connecting to Unbalanced EquipmentBalanced Circuits C100 Installation Guide Appendix E Environmental Specification +4dBu = 1.229V rms dBu = 0.775V rms. -6dBu = 0.388V rms Appendix F Additional Information for Installing Stageboxes Design Requirements for a FlightcaseThis page is blank intentionally Appendix G Cables and accessories Cables and Accessories by Part DescriptionDescription SSL Part No Video & Sync Miscellaneous/HardwareAppendix G Part Numbers More Notes