Lincoln Electric SVM179-B service manual Figure F.5 Control BOX Assembly

Page 62

Return to Section TOC

Return to Section TOC

TOC

Return to Master TOC

Return to Master TOC

TOC

F-18

TROUBLESHOOTING & REPAIR

F-18

 

MOTOR OVERLOAD TEST (CONTINUED)

FIGURE F.5 – CONTROL BOX ASSEMBLY

CASE

CONTROL BOX ASSEMBLY

Return to Section

Return to Section TOC

Return to Master

Return to Master TOC

PROCEDURE

1.Perform the Case Removal Procedure.

2.Remove the 5 #10-24 x .50 screws holding the control box cover to access the contactor leads. See Figure F.2.

3.Remove the five #10-24 screws holding the control box cover, and locate the two motor leads and 3 tach leads. See the Wiring Diagram.

4.Apply the correct input voltage (15-110vdc) to the unit.

5.With the trigger activated and the motor run- ning check the motor armature current. Normal armature current is less then 3 amps.

6.If the amperage exceeds 3.2 amps for more than 8 seconds the motor will be disabled.

7.If the motor armature current is normal and the motor still shuts down the control board may be faulty.

8.If the current is high check for restrictions in the feed system. They can be caused by a clogged liner, spindle tightness, drive rolls to tight, fault drive motor or a faulty gearbox.

9.After testing replace faulty parts and reassem- ble the feeder in reverse order of disassembly.

LN-25™ PRO

Image 62
Contents LN-25PRO Wire Feeder Safety LN-25 PROElectric Shock can kill ARC Rays can burn Iii Welding CuttingFor Electrically Précautions DE Sûreté Sûreté Pour Soudage a L’ArcMaster Table of Contents for ALL Sections Table of Contents Installation Section Installation Location Safety PrecautionsHigh Frequency Protection ELECTRIC SHOCK can KillShielding GAS Connection Wire Drive ConfigurationCable Connections Changing the GUN Receiver BushingProcedure to Install Drive Rolls Wire GuidesGUN Connection Pressure ARM AdjustmentLoading Spools of Wire Description Power Source to LN-25 PRO Cable Connection DiagramsAcross the ARC SET-UPS Figure A.7 Table of Contents Operation Section Safety Precautions OperationGeneral Description Analog Voltmeter Wire Feed Speed KnobDescription Wire Feed Speed, CC Operation See Figure B.2 or Figure B.2Table B.2 VV CC Wire Speed Setting Constant Current VS Constant Voltage Wire Welding Figure B-3Work Sense Lead PIN GUN Trigger Connector See Figure B.1Wire Feed Speed Range Switch K2613-5 and K2613-7 only Thermal LED, Motor Overload See Figure B.1Internal Controls Figure B.4Internal Controls Description Step Trigger Interlock SwitchCV/CC Switch Cold Feed PushbuttonOptional PREFLOW, Burnback Postflow Timer KIT K2330-2 Preflow TimerRear Controls Figure B.5Flow Meter POWER-UP SequenceGAS Purge Pushbutton ScfhLN-25 PRO Table of Contents Accessories Section Wire Type AccessoriesFactory Installed Equipment Drive Roll KitsAccessories Accessories K435 Spindle Adapter, for mounting Installation of the K590-6 Water Cooling KIT Table of Contents Maintenance Section Periodic Maintenance MaintenanceRoutine Maintenance Calibration SpecificationBoard Wire Feed SpeedCover Figure D.3. Major Component Location 1TABLE of CONTENTS-THEORY of Operation Section E-1 Control BoardTheory of Operation Figure E.2 General DescriptionInput Power TRIGGER CIRCUITFeedback and Control CIR- Cuits Figure E.4 Feedback & Control CircuitsOptional Circuits Figure E.5 Optional Circuits & Digital Display BoardLN-25 PRO Table of Contents Troubleshooting & Repair Troubleshooting & Repair HOW to USE Troubleshooting GuidePC Board Troubleshooting Procedures Fault Code Description Possible Adjustment Motor Solenoid Test Recommended Course of Action Problems SymptomsPossible Areas Misadjustments LN-25 PRO Materials Needed Case Removal ProcedureTest Description Procedure Figure F.1 Case RemovalGAS Solenoid Test GAS Solenoid Control BOX Control BOX Cover Contactor Test Control BOX Contactor Drive Motor and Tach Feedback Test Case Control BOX Assembly Motor Overload Test Figure F.5 Control BOX Assembly Contactor Removal and Replacement Procedure Removal Procedure Figure F.6 Control BOXReplacement Procedure Figure F.7 Buss BAR and Mounting BlockLN-25 PRO Front Panel Removal and Replacement Procedure Front Panel Troubleshooting & Repair Gas Hose Control BOX Wire Drive Panel Drive Gear Cover LN-25 PRO PC Board Removal and Replacement Procedure PC BOARD Removal and Replacement Procedure Figure F.11 Control PC Board LocationGAS Solenoid Removal and Replacement Procedure GAS Solenoid GAS Hose Control BOX Lock NUT Retest a machine SET UPRetest After Repair Operation VerificationLN-25 PRO Table of Contents Diagram Section Wiring Diagram LN-25 PRO WiriNG DiaGram lN-25 prO CODEs 11507, 11508 G5681-1 Wiring DIAGRAM- LN-25 PRO Analog WiriNG DiaGram lN-25 prO CODEs 11746, 11747 G5681-3 LN-25 PRO Wire Feeder G5683LN-25 PRO Wire Feeder ElECTriCal DiaGrams G5683-1 Pushbutton G5683-2 LN-25 PRO AnalogG5683 G5683-3 Circuitryconfidential Equipmenttype Xres RXD Work 624 4783-1C0 Flexiblepowerfeede R 50V OF05 Circuitryconfidential S27505-1B0 R2 CW