TROUBLESHOOTING & REPAIR

F-33

 

RETEST AFTER REPAIR

Retest a machine :

If it is rejected under test for any reason that requires you to remove any part which could affect the machine’s electrical charac- teristics.

OR

If you repair or replace any electrical components.

SET UP

1.Connect a supply of filtered compressed air at 80 psi to the gas inlet.

2.Supply 15 to 110 VAC to the machine.

3.Connect the gun to the connector block and connect the trigger.

 

OPERATION VERIFICATION

WIRE FEED SPEED (Standard)

50 through 700 IPM

WIRE FEED SPEED (Ext. Torque)

50 through 400 IPM

VOLTMETER (Analog)

..............Must read Inpit Voltage +/-2%

VOLTMETER (Digital)

Must operate at 3 TO 12 VDC input volts

GAS SOLENOID

Must operate when Gun Trigger is activated.

CONTACTOR

Must operate when Gun Trigger is activated

 

or after Pre-flow time if Timer Kit is installed.

LN-25™ PRO

Image 77
Contents LN-25PRO Wire Feeder LN-25 PRO SafetyElectric Shock can kill ARC Rays can burn Iii Welding CuttingFor Electrically Sûreté Pour Soudage a L’Arc Précautions DE SûretéMaster Table of Contents for ALL Sections Table of Contents Installation Section Installation High Frequency Protection Safety PrecautionsLocation ELECTRIC SHOCK can KillCable Connections Wire Drive ConfigurationShielding GAS Connection Changing the GUN Receiver BushingWire Guides Procedure to Install Drive RollsGUN Connection Pressure ARM AdjustmentLoading Spools of Wire Description Power Source to LN-25 PRO Cable Connection DiagramsAcross the ARC SET-UPS Figure A.7 Table of Contents Operation Section Operation Safety PrecautionsGeneral Description Analog Voltmeter Wire Feed Speed KnobDescription Figure B.2 Wire Feed Speed, CC Operation See Figure B.2 orTable B.2 VV CC Wire Speed Setting Figure B-3 Constant Current VS Constant Voltage Wire WeldingWire Feed Speed Range Switch K2613-5 and K2613-7 only PIN GUN Trigger Connector See Figure B.1Work Sense Lead Thermal LED, Motor Overload See Figure B.1Figure B.4 Internal ControlsCV/CC Switch Step Trigger Interlock SwitchInternal Controls Description Cold Feed PushbuttonPreflow Timer Optional PREFLOW, Burnback Postflow Timer KIT K2330-2Figure B.5 Rear ControlsGAS Purge Pushbutton POWER-UP SequenceFlow Meter ScfhLN-25 PRO Table of Contents Accessories Section Factory Installed Equipment AccessoriesWire Type Drive Roll KitsAccessories Accessories K435 Spindle Adapter, for mounting Installation of the K590-6 Water Cooling KIT Table of Contents Maintenance Section Routine Maintenance MaintenancePeriodic Maintenance Calibration SpecificationBoard Wire Feed SpeedCover Figure D.3. Major Component Location Control Board 1TABLE of CONTENTS-THEORY of Operation Section E-1Figure E.2 General Description Theory of OperationTRIGGER CIRCUIT Input PowerFigure E.4 Feedback & Control Circuits Feedback and Control CIR- CuitsFigure E.5 Optional Circuits & Digital Display Board Optional CircuitsLN-25 PRO Table of Contents Troubleshooting & Repair HOW to USE Troubleshooting Guide Troubleshooting & RepairPC Board Troubleshooting Procedures Fault Code Description Possible Adjustment Motor Solenoid Test Recommended Course of Action Problems SymptomsPossible Areas Misadjustments LN-25 PRO Materials Needed Case Removal ProcedureTest Description Figure F.1 Case Removal ProcedureGAS Solenoid Test GAS Solenoid Control BOX Control BOX Cover Contactor Test Control BOX Contactor Drive Motor and Tach Feedback Test Case Control BOX Assembly Motor Overload Test Figure F.5 Control BOX Assembly Contactor Removal and Replacement Procedure Figure F.6 Control BOX Removal ProcedureFigure F.7 Buss BAR and Mounting Block Replacement ProcedureLN-25 PRO Front Panel Removal and Replacement Procedure Front Panel Troubleshooting & Repair Gas Hose Control BOX Wire Drive Panel Drive Gear Cover LN-25 PRO PC Board Removal and Replacement Procedure Figure F.11 Control PC Board Location PC BOARD Removal and Replacement ProcedureGAS Solenoid Removal and Replacement Procedure GAS Solenoid GAS Hose Control BOX Lock NUT Retest After Repair SET UPRetest a machine Operation VerificationLN-25 PRO Table of Contents Diagram Section Wiring Diagram LN-25 PRO WiriNG DiaGram lN-25 prO CODEs 11507, 11508 G5681-1 Wiring DIAGRAM- LN-25 PRO Analog WiriNG DiaGram lN-25 prO CODEs 11746, 11747 G5681-3 G5683 LN-25 PRO Wire FeederLN-25 PRO Wire Feeder ElECTriCal DiaGrams G5683-1 Pushbutton LN-25 PRO Analog G5683-2G5683 G5683-3 Circuitryconfidential Equipmenttype Xres RXD Work 624 4783-1C0 Flexiblepowerfeede R 50V OF05 Circuitryconfidential S27505-1B0 R2 CW