Xantrex Technology 815-3524, 815-2524-02 manual Mounting to the Negative Battery Terminal

Page 48

Installing the Inverter/Charger

Mounting to the Negative Battery Terminal

To mount the sensor on the negative battery terminal:

Negative (–)

battery terminal

Figure 11 BTS Mounted on the Negative Battery Terminal

1.Select the battery to be monitored. The BTS should be connected to the battery bank that is directly connected to the inverter/charger.

34

2.Switch off all devices operating from the battery, or open the battery switch (if present) to disconnect the battery.

3.Wait 10 minutes for any explosive battery gases to dissipate.

4.Remove the nut that connects existing wiring ring terminals to the battery negative terminal stud.

5.Move or reorient the existing wiring ring terminals on the battery negative terminal stud, so there is a flat surface on which to seat the BTS mounting plate.

You may need to bend the ring terminal crimp and/or wires slightly downward to allow the sensor to seat flush to the top surface of the upper ring terminal.

6.Mount the sensor directly on top of the ring terminal, as shown in Figure 11, and firmly tighten the terminal nut.

FIRE HAZARD

In this procedure, you must install the DC wire on the battery terminal, then install the sensor on top of the DC wire. This sequence is required to provide the best connection to the battery and to ensure correct performance of the sensor.

Failure to follow these instructions can result in death or serious injury.

7.Check to ensure that the sensor and all wires are held firmly and cannot be moved.

Freedom SW 230V Installation Guide

Image 48
Contents Freedom SW Sine Wave Inverter/Chargers Page This guide for use by qualified About This Guide PurposeImportant Safety Instructions Electrical Shock and Fire HazardElectrical Shock Hazard Fire and Burn Hazard Explosion HazardPrecautions When Working With Batteries Exposure to Chemicals and Gases Hazard Risk of Damage to the INVERTER/CHARGERRegulatory Limitations on USEPage Contents Page This guide for use by qualified installers only Page Introduction Materials List Freedom SW 230V Installation Guide Materials ListInstallation Information Before You Begin the InstallationInstallation Codes Electrical Shock and Fire HazardsAbout the Xanbus System Xanbus SystemXanbus-enabled Products and Accessories About the Xanbus SystemPlanning the Installation Two Key Performance FactorsSize and Length of DC Cables Mounting Location of the Freedom SWPlanning Preparations AC, DC, and Network ComponentsPlanning Preparations Planning Preparations AC Components AC InputAC Disconnect and Over-Current Protection Device AC OutputAC Wiring Distribution PanelsModels Freedom SWDC Components BatteriesDC Cabling Fire HazardDC Disconnects and Over-Current Devices DC GroundingMarine Applications1 Heavy Item To unpack and inspectInstallation Tools and Materials ToolsMaterials Installing the Inverter/Charger OverviewChoosing a Location for the Inverter/Charger Fire and Explosion HazardHeat Hazard Safe Mounting the Inverter/Charger ConsiderationsTo mount the inverter/charger Approved Mounting Orientation Orientation? Comment Orientation Approved Mounting Orientation? Comment This guide for use by qualified Connecting the AC Input and AC Output Wires General AC Wiring ConsiderationsFIRE, Electrical SHOCK, and Energy Hazards Connecting AC Input Wires Correct Batter Polarity will Cause Damage toInstalling the Inverter/Charger Connecting the AC Output Wires To make the AC output wiring connectionsEquipment Damage Connecting the DC Cables DC Connection PrecautionsRecommended Cable Sizes and Lengths and Fuse Size Preparing the CablesGuidelines for Routing the DC Cables Connecting the DC Cables to the Inverter/Charger Equipment Damage DUE to Reverse PolarityTo connect the DC cables DC Cable Connections To connect the chassis ground Connecting the Battery Temperature Sensor BTS Mounting OptionsMounting to the Negative Battery Terminal To mount the sensor on the negative battery terminalBTS port Mounting to the Side of the Battery Case To mount the sensor on the battery caseConnecting to the Network To connect the Freedom SW 230V to the Xanbus networkPerforming Checks Prior to Initial Start-Up Testing Your Installation Testing in Invert ModeTesting in Charge Mode and AC Bypass Mode Installation CompleteTo verify that the Freedom SW 230V starts charging Stacking Features Parallel Stacking DC Connections for Stacked Inverters Connect the stacked system as followsNeutral Wiring for Stacked Inverters Configuring System for Stacked Operation To configure the system for stackingSearch Mode Operation in Parallel Stacking Wiring SchematicDisabling Search Mode on the Master Unit Setting Search Mode on the Slave UnitCharger Settings in a Dual Freedom SW Configuration CalculationsTo set the Max Chg Rate % setting in each Freedom SW ExamplesTo set the Max Chg Rate % setting in each Freedom SW To set the Max Chg Rate % setting in each Freedom SW Inverter/Charger Physical Specifications Freedom SW Physical SpecificationsBattery Information Battery Bank SizingEstimating Battery Requirements Calculating Battery SizeBattery AMP-HOURS Used = AC WATT-HOURS÷10 Watts = Volts × AmpsDaily watt-hours needed Battery Banks Battery Bank Sizing WorksheetRestrictions on Motor Size Battery Information Battery Sizing Worksheet Battery Cabling and Hook-up Configurations Battery Series ConnectionBattery Series-Parallel Connections Specifications Environmental SpecificationsInverter Specifications Charger Specifications Transfer and General Specifications Inverter Drip Shield Installation To install the drip shieldShock Hazard Drip Shield Placement Desktop Mount 20 mm No clearance required here Page Page Schneider Electric Solar Inverters USA Inc