Xantrex Technology 815-3524 manual Examples, To set the Max Chg Rate % setting in each Freedom SW

Page 62

Stacking Features

each parallel branch of batteries. Therefore, the above generalizations of maximum charge rate (%) can be made for the entire battery bank.

The Freedom SW 230V’s Max Chg Rate (%) setting defaults to

100(adjustable from 0 to 100). So if the Freedom SW 3524-230 charger with a maximum possible 90A charger capacity is set to a Max Chg Rate of 100 (%) then its full 90A of current can be delivered into the battery bank. However, if this is too high, the installer/operator may reduce the Max Chg Rate setting to suit the system battery type and bank requirements (and limitations), to avoid overheating the battery bank.

The user/installer is responsible of configuring the charger to ensure that the battery manufacturer’s recommended maximum charge rate current (in Amps) is not exceeded to prolong battery life and to exhibit best performance.

Examples

Example 1: System composed of two stacked Freedom SW 2524- 230s. Each Freedom SW 2524-230 has a maximum charge capacity of 65A.

The industry’s commonly accepted practice suggests a typical Flooded battery bank capacity (C) of 400Ah should not be charged beyond 25% of its capacity (100A). Therefore, when configuring the two stacked Freedom SW chargers, each charger may have a maximum allowable charger output current of 50A (400 × 25% × 1/2) into the common battery bank as described in the Calculations section. Also, the System Total BULK output current is calculated as 100A (50A + 50A).

To set the Max Chg Rate (%) setting in each Freedom SW 2524-230:

1.Divide the maximum allowable charger output current of 50A by the Freedom SW 2524-230’s maximum charge capacity of 65A.

So, 50 ÷ 65, gets an approximate value of 0.77 (or 77%) which can be roughly reduced to 75%.

2.Set the Max Chg Rate (%) setting to 75 which means 75%.

In this example, the actual output current is limited to 75% of 65A which is 48A. Therefore, the actual System Total BULK output current comes out to just under 100A.

48

Freedom SW 230V Installation Guide

Image 62
Contents Freedom SW Sine Wave Inverter/Chargers Page This guide for use by qualified About This Guide PurposeElectrical Shock Hazard Important Safety InstructionsElectrical Shock and Fire Hazard Fire and Burn Hazard Explosion HazardPrecautions When Working With Batteries Exposure to Chemicals and Gases Hazard Risk of Damage to the INVERTER/CHARGERRegulatory Limitations on USEPage Contents Page This guide for use by qualified installers only Page Introduction Materials List Freedom SW 230V Installation Guide Materials ListInstallation Codes Installation InformationBefore You Begin the Installation Electrical Shock and Fire HazardsAbout the Xanbus System Xanbus SystemXanbus-enabled Products and Accessories About the Xanbus SystemSize and Length of DC Cables Planning the InstallationTwo Key Performance Factors Mounting Location of the Freedom SWPlanning Preparations AC, DC, and Network ComponentsPlanning Preparations Planning Preparations AC Disconnect and Over-Current Protection Device AC ComponentsAC Input AC OutputAC Wiring Distribution PanelsModels Freedom SWDC Cabling DC ComponentsBatteries Fire HazardMarine Applications1 DC Disconnects and Over-Current DevicesDC Grounding Heavy Item To unpack and inspectMaterials Installation Tools and MaterialsTools Installing the Inverter/Charger OverviewHeat Hazard Choosing a Location for the Inverter/ChargerFire and Explosion Hazard Safe To mount the inverter/charger Mounting the Inverter/ChargerConsiderations Approved Mounting Orientation Orientation? Comment Orientation Approved Mounting Orientation? Comment This guide for use by qualified FIRE, Electrical SHOCK, and Energy Hazards Connecting the AC Input and AC Output WiresGeneral AC Wiring Considerations Connecting AC Input Wires Correct Batter Polarity will Cause Damage toInstalling the Inverter/Charger Equipment Damage Connecting the AC Output WiresTo make the AC output wiring connections Recommended Cable Sizes and Lengths and Fuse Size Connecting the DC CablesDC Connection Precautions Preparing the CablesGuidelines for Routing the DC Cables To connect the DC cables Connecting the DC Cables to the Inverter/ChargerEquipment Damage DUE to Reverse Polarity DC Cable Connections To connect the chassis ground Connecting the Battery Temperature Sensor BTS Mounting OptionsMounting to the Negative Battery Terminal To mount the sensor on the negative battery terminalBTS port Mounting to the Side of the Battery Case To mount the sensor on the battery caseConnecting to the Network To connect the Freedom SW 230V to the Xanbus networkPerforming Checks Prior to Initial Start-Up Testing Your Installation Testing in Invert ModeTo verify that the Freedom SW 230V starts charging Testing in Charge Mode and AC Bypass ModeInstallation Complete Stacking Features Parallel Stacking DC Connections for Stacked Inverters Connect the stacked system as followsNeutral Wiring for Stacked Inverters Configuring System for Stacked Operation To configure the system for stackingDisabling Search Mode on the Master Unit Search Mode Operation in Parallel StackingWiring Schematic Setting Search Mode on the Slave UnitCharger Settings in a Dual Freedom SW Configuration CalculationsTo set the Max Chg Rate % setting in each Freedom SW ExamplesTo set the Max Chg Rate % setting in each Freedom SW To set the Max Chg Rate % setting in each Freedom SW Inverter/Charger Physical Specifications Freedom SW Physical SpecificationsBattery Information Battery Bank SizingBattery AMP-HOURS Used = AC WATT-HOURS÷10 Estimating Battery RequirementsCalculating Battery Size Watts = Volts × AmpsDaily watt-hours needed Restrictions on Motor Size Battery BanksBattery Bank Sizing Worksheet Battery Information Battery Sizing Worksheet Battery Cabling and Hook-up Configurations Battery Series ConnectionBattery Series-Parallel Connections Specifications Environmental SpecificationsInverter Specifications Charger Specifications Transfer and General Specifications Shock Hazard Inverter Drip Shield InstallationTo install the drip shield Drip Shield Placement Desktop Mount 20 mm No clearance required here Page Page Schneider Electric Solar Inverters USA Inc