Cisco Systems STEV SRT-M-66, 2654T6 appendix Tools and Equipment, Safety Recommendations

Page 6

Appendix A Repackaging the Router

Repackaging the Routers

REVIEW DRAFT — CISCO CONFIDENTIAL

Tools and Equipment

You need the following items to remove the router from the equipment rack and repackage it for shipping:

ESD-preventive wrist strap

Flat-blade screwdrivers

Number 1 and number 2 Phillips screwdrivers

3/8-inch (10-mm) nutdriver (for systems equipped with the DC-input power shelf)

9/16-inch (14-mm wrench) wrench

3/4-inch (19-mm) socket and ratchet wrench

Safety hand truck with retractable safety leg wheels and security strap, such as the Stevens Appliance Truck Company “Escort,” Model STEV SRT-M-66 (distributed by McMaster-Carr as Model 2654T6), or an equivalent safety hand truck.

Antistatic sacks or other ESD-preventive storage environment

The original router shipping package supplied by Cisco. If you do not have the original router shipping package, contact your Cisco service representative for assistance.

Safety Recommendations

Before you begin the procedures in this appendix, review the following safety information:

The safety recommendations listed in the“Safety Recommendations” section on page 2-2in Chapter 2, “Preparing for Installation.”

The safety warnings listed in the publication Regulatory Compliance and Safety Information for the Cisco 12000 Series Internet Router that accompanied your router

 

Cisco XR 12416 Router Chassis Installation Guide

A-6

OL-xxxxx-xx

Image 6
Contents Repackaging the Router Router Shipping Package Review Draft Cisco Confidential Figure A-1 Router Shipping Package Components Figure A-2 Router Accessories Package Safety Recommendations Tools and EquipmentPowering Down the Router Removing the Router from the RackDisconnecting Power Cables from the Power Shelf Disconnecting RP CablesDisconnecting Alarm Card Cables Removing the Front CoversRemoving Components from the Chassis to Reduce Weight Removing Power ModulesDetaching the Supplemental Bonding and Grounding Connection Removing the Blower ModulesRemoving the Cards from the Chassis Card Cages Removing the Router from the Equipment Rack Figure A-3 Preparing the Scissor-Jack Platform See Figure A-5 See Figure A-6 Chassis anchor Clip and bolt On each side Installing the Router on the Shipping Pallet Pallet body Pallet front bar Top view of pallet partsReview Draft Cisco Confidential Review Draft Cisco Confidential Reinstalling the Cards in the Switch Fabric Card Cage Reinstalling Components in the RouterReinstalling the Cards in the Upper and Lower Card Cages Reinstalling the Power ModulesRepackaging the Router Accessories Reinstalling the Front CoversRepackaging the Rack-Mounting Platform Repackaging the Vertical Cable-Management Troughs Repackaging the Center-Mount Rack-Mounting BracketsRepackaging the Miscellaneous Accessories Reassembling the Accessories PackageCompleting the Repackaging Repackaging the Replaced Router Chassis Router Replacement Chassis Shipping Container Reinstalling the Replaced Chassis on the Shipping PalletRepackaging the Replaced Chassis for Shipment