HP Performance Optimized Data Center (POD) 40cp manual Electrical, POD Shut Down Required

Page 65

Electrical

Maintenance of the electrical components might require the following:

Expose personnel to high voltage.

Allow personnel to come into direct contact with high voltage.

Power down the POD during the execution of the maintenance item.

You must explicitly state and acknowledge if a POD power down will be possible. If a power down is not possible, LLS inspections will be conducted and further action will be taken at your discretion.

Component to be inspected

Task

Frequency

Capable Party

 

 

 

 

 

 

Electrical connections

Use LLS to check for major

Quarterly

Licensed electrician

 

 

electrical connections (torque

 

 

 

 

marks, sizzle, and acrid odor):

 

 

 

 

Main/House Power Feeds

 

 

 

 

Busway End Feeds, Drop

 

 

 

 

 

Boxes (including cables and

 

 

 

 

 

cord caps)

 

 

 

 

Electrical panels, breakers,

 

 

 

 

 

and disconnects

 

 

 

 

 

 

 

 

POD SHUT DOWN REQUIRED

Annually

Licensed electrician

 

 

Conduct torque checks on the

 

 

 

 

following:

 

 

 

 

Main, house, and critical IT

 

 

 

 

 

power feeds

 

 

 

 

Electrical panels, breakers,

 

 

 

 

 

and disconnects

 

 

 

 

Busway end feeds, busway

 

 

 

 

 

sections, and drop box locking

 

 

 

 

 

mechanism (bolt)

 

 

 

 

 

 

 

 

Grounding

Grounding system residence test

Every 2 years

Licensed electrician

 

 

using the DUCTOR method

 

 

 

POD SHUT DOWN REQUIRED

Every 2 years

Licensed electrician

 

 

Ground and grounding

 

 

 

 

connection/lug located internal to

 

 

 

 

each electrical panel torque test.

 

 

 

 

Clean and re-tighten as necessary.

 

 

 

Service entrance grounding

Every 2 years

Licensed electrician

 

 

ground-rod/ground well and

 

 

 

 

grounding connection/lug located

 

 

 

 

external to the POD torque test.

 

 

 

 

Clean and re-tighten as necessary.

 

 

 

POD SHUT DOWN REQUIRED

Every 2 years

Licensed electrician

 

 

Service entrance ground

 

 

 

 

connection/lug located on the

 

 

 

 

switchboard (or landing location)

 

 

 

 

torque test. Clean and re-tighten as

 

 

 

 

necessary.

 

 

 

Grounding system bonding

Every 2 years

Licensed electrician

 

 

jumpers that connect racks to the

 

 

 

 

POD structure and rack to rack

 

 

 

 

torque test. Clean and re-tighten as

 

 

 

 

necessary.

 

 

 

 

 

 

 

Periodic maintenance 65

Image 65
Contents Abstract Page Contents Periodic maintenance Contacting HP Parts and part number identification Illustrated parts catalogStructural component identification Life safety component identification Component Description Electrical power component identificationExternal panel labels Front view shown Callout Electrical safety label Description Control cabinet component identification Electrical safety label DescriptionHP POD 40c NA racks Cooling system component identificationCold aisle clearance Aisle clearancesHot aisle clearance Replaceable componentsOperator safety Removal and replacement proceduresSafety considerations Removing the air filter Fire detection and suppressionAir filter Replacing the air filter Removing the busway drop box Busway drop boxReplacing the busway drop box Differential pressure sensor Replacing the differential pressure sensor Removing the differential pressure sensorReplacing the door position contact Door position contactRemoving the door position contact Removing the drain pan sensor Drain pan sensorReplacing the drain pan sensor Removal and replacement procedures Removing the ECS touchscreen ECS touchscreenReplacing the ECS touchscreen EPO buttonRemoving the EPO button Replacing the EPO button Removing the EPO LED indicator EPO LED indicatorsReplacing the EPO LED indicator Replacing the EPO thermister EPO thermisterRemoving the EPO thermister Removing the external chilled water flow actuator External chilled water flow actuatorRemoval and replacement procedures Replacing the external chilled water flow actuator External chilled water flow valveReplacing the external chilled water flow valve External pressure gauge isolation valveRemoving the external chilled water flow valve Replacing the external pressure gauge isolation valve FanRemoving the external pressure gauge isolation valve Removing the fan Replacing the fan Removing the fan bank Fan bankReplacing the fan bank Removing the fire strobe light Fire strobe lightReplacing the fire strobe light HumidifierRemoving the humidifier Removal and replacement procedures Replacing the humidifier Removing the humidistat HumidistatReplacing the humidistat Removal and replacement procedures Removing the humidity sensor Humidity sensorRemoval and replacement procedures Replacing the humidity sensor Removing the LED light LED lightReplacing the LED light Temperature sensor cold aisleRemoving the cold aisle temperature sensor Replacing the cold aisle temperature sensor Removing the hot aisle temperature sensor Temperature sensor hot aisleRemoval and replacement procedures Replacing the hot aisle temperature sensor Removing the Vesda filter Vesda filterReplacing the Vesda filter Periodic maintenance overview Periodic maintenanceCooling system maintenance schedule Qualified personnelLeak detection maintenance ECS Humidifier if installedPOD Shut Down Required ElectricalVesda Fire alarm and suppression systemHP POD 40c NA structure Life safetyThird-party components Access controlPeriodic maintenance Electrical specifications SpecificationsGeneral specifications Rack specifications Water specificationsEnvironmental specifications Thermal and air flow performanceOptional features specifications HP contact information Contacting HPBefore you contact HP Regulatory information Safety and regulatory complianceWarranty information AHJ GlossaryPDU Documentation feedback Index Temperature sensor