Thermal insulation process

Apply thermal insulation for the pipes separately at liquid side and gas side.

For the thermal insulation to the pipes at gas side, be sure to use the material with heat-resisting temperature 248 °F (120 °C) or higher.

Using the attached thermal insulation material, apply the thermal insulation to the pipe connecting section of the indoor unit securely without gap.

REQUIREMENT

Apply the thermal insulation to the pipe connecting section of the indoor unit securely up to the root without exposure of the pipe. (The pipe exposed to the outside causes water leak.)

Wrap heat insulator with its slits facing up (ceiling side).

Wrap the pipe with the attached heat insulator without any gap between the indoor unit.

Indoor unit

The seam must be faced upward (ceiling side).

Heat insulation

Flare nut

Heat insulator

Union

of the pipe

pipe

 

(Accessory)

 

 

13-EN

– 13 –

Image 14
Contents RAV-SP360CT-UL RAV-SP420CT-UL AIR CONDITIONER SPLIT TYPERAV-SP180CT-UL RAV-SP240CT-UL RAV-SP300CT-UL EnglishContents ADOPTION OF NEW REFRIGERANTUnder Ceiling Type 1 ACCESSORY PARTS„Accessory parts 2 PRECAUTIONS FOR SAFETY Under Ceiling TypeUnder Ceiling Type „Height of ceiling 3 SELECTION OF INSTALLATION PLACE„Installation space Avoid installing in the following places2 Removing wire guard „Wireless remote control„Before installation Under Ceiling TypeInstallation Manual4 Removal of protective vinyl „External view3 Removal of side panel 5 Removal of protectorInstallation Manual Unit in mm Under Ceiling Type„Pipe knockout hole „Installation of hanging bolts„Draw-outdirection of pipe/ wire Using attached installation patternInstallation Manual „Installation of indoor unit„Installation of remote control Sold separately There is ceiling material„Pipe size 4 REFRIGERANT PIPING AND EVACUATING„Refrigerant Piping „Permissible Piping Length and Height DifferenceRefrigerant amount to be added „EvacuationTightening connection Piping with outdoor unitREQUIREMENT Thermal insulation processUnder Ceiling Type „Drain up 5 DRAIN PIPING WORK„Piping/Heat insulating material Under Ceiling Type„Connection of drain pipe „Connection of drain hose„Thermal insulating process Under Ceiling TypeWiring 6 ELECTRICAL CONNECTIONRemote control wiring Under Ceiling TypeUnder Ceiling Type REQUIREMENT „Wire connectionUnder Ceiling Type Under Ceiling Type Connected at backsideConnected at upside 19-EN„Wiring Diagram „System interconnection Wires and Ground Wire„Remote Control Wiring Single systemProcedure „Changing applicable control setting7 APPLICABLE CONTROLS Procedure1 → 2 → 3 → 4 → 5 → „Installation to high ceiling„Using wireless remote control Procedure„Group control „Filter sign setting„To secure better effect of heating Procedure exampleProcedure ProcedureProcedure ProcedureProcedure ProcedureProcedure ProcedureUnder Ceiling Type „Remote control switch monitoring functionInstallation Manual „Before test run 8 TEST RUN2, 4 1,5 „Execute a test runProcedure Wireless remote controlProcedure Procedure„Confirmation and check 9 TROUBLESHOOTING„Confirmation of error history Procedure30-EN „Check codes and parts to be checkedUnder Ceiling Type Under Ceiling Type 31-ENUnder Ceiling Type 32-ENEH99864801