York Comprehensive Guide to Efficient Heat Pumps with BP090 Features

Page 31

66307-YIM-B-0606

Predator 50 Hz Heat Pump Units

Indoor Coil Pressure Drop vs. Airflow

0.7

 

 

 

 

 

 

 

0.6

 

 

 

 

 

 

 

0.5

 

 

 

 

 

 

 

0.4

 

 

 

 

 

 

 

0.3

 

 

 

 

 

 

 

0.2

 

 

 

 

 

 

 

0.1

 

 

 

 

 

 

 

0

 

 

 

 

 

 

 

2000

2500

3000

3500

4000

4500

5000

5500

Airflow (CFM)

FIGURE 23 - DRY COIL DELTA P

7.5T 50 Hz HP

10T50HzHP

SUPPLY AIR DRIVE ADJUSTMENT

Before making any blower speed changes review the installation for any installation errors, leaks or undesirable systems effects that can result in loss of airflow.

Even small changes in blower speed can result in substantial changes in static pressure and BHP. BHP and AMP draw of the blower motor will increase by the cube of the blower speed. Static pressure will increase by the square of the blower speed. Only qualified personnel should make blower speed changes, strictly adhering to the fan laws.

At unit start-up, the measured CFM may be higher or lower than the required CFM. To achieve the required CFM, the speed of the drive may have adjusted by changing the datum diameter (DD) of the variable pitch motor sheave as described below:

( Required CFM )• Existing DD = New DD Measured CFM

Use the following tables and the DD calculated per the above equation to adjust the motor variable pitch sheave.

EXAMPLE

A 12.5 ton unit was selected to deliver 4,000 CFM with a 3 HP motor, but the unit is delivering 3,800 CFM. The variable pitch motor sheave is set at 2 turns open.

Use the equation to determine the required DD for the new motor sheave,

( 4,0003,800 CFMCFM ) • 4.0 In. = 4.21 In.

Use Table 32 to locate the DD nearest to 4.21 in. Close the sheave to 1 turn open.

New BHP

=(Speed increase)3 • BHP at 3,800 CFM

=(Speed increase)3 • Original BHP

=New BHP

New motor Amps

=(Speed increase)3 • Amps at 3,800 CFM

=(Speed increase)3 • Original Amps

=New Amps

Unitary Products Group

31

Image 31
Contents Single Package Heat Pump High Efficiency Installation Manual 50 HzTable of Contents List of Figures List of Tables General Safety ConsiderationsInspection Renewal Parts ReferenceApprovals Nomenclature Ton York Model Number NomenclatureInstallation Safety Information InstallationPreceding Installation Location Unit Voltage LimitationsPoint Load Weight Unit WeightsRigging and Handling Unit Clearances ClearancesDetail B BttomPower Rear Duct Dimensions Ductwork Duct Covers Predator Roof Curb Dimensions Filters Thermostat WiringControl Wire Sizes CompressorsElectronic Thermostat Field Wiring Power Wiring DetailGroundlug Electrical Data 10 TON HP Electrical Data 7-1/2 TON HPElectric Heat Option Factory Installed Options Field Installed AccessoriesElectric Heat Accessory Physical DataElectric Heat Minimum Supply AIR Indoor AIR Quality AQ Enthalpy SET Point ChartSupply AIR Limitations Blower RotationBelt Tension Belt Adjustment Blower Performance 7-1/2 TON Standard Motor Side Duct Metric Blower Performance 10 TON Standard Motor Side Duct Metric Blower Performance 10 TON Standard Motor Side Duct ImperialBlower Performance 10 TON Optional Motor Side Duct Metric Blower Performance 10 TON Optional Motor Side Duct ImperialBlower Performance 7-1/2 TON Standard Motor Downshot Metric Blower Performance 10 TON Standard Motor Downshot Imperial Blower Performance 7-1/2 TON Optional Motor Downshot MetricBlower Performance 10 TON Standard Motor Downshot Metric Blower Performance 10 TON Optional Motor Downshot Imperial Indoor Blower SpecificationsBlower Performance 10 TON Optional Motor Downshot Metric Method TWO AIR BalanceChecking AIR Quantity Method ONEDRY Coil Delta P Supply AIR Drive AdjustmentM3S Additional Static Resistance ImperialAdditional Static Resistance Metric CFMCooling Sequence of Operation OperationMotor Sheave Datum Sequence of Operations OverviewCooling Operation Errors Heating Sequence of Operation Safety ControlsReset Compressor ProtectionSTART-UP Post Start Check List Operating InstructionsSuperheat Charging Method Cooling Superheat 7-1/2 TON Superheat ChargingCooling Superheat 10 TON TroubleshootingPredator Flash Codes Unit Control Board Unit Control Board Flash CodesCooling Troubleshooting Guide Page Page Unitary 5005 Norman Products York Group Drive 73069