York BP 090, BP120 installation manual Rigging and Handling, Unit Weights, Point Load Weight

Page 10

66307-YIM-B-0606

RIGGING AND HANDLING

Exercise care when moving the unit. Do not remove any packaging until the unit is near the place of installation. Rig the unit by attaching chain or cable slings to the lifting holes provided in the base rails. Spreader bars, whose length exceeds the largest dimension across the unit, MUST be used across the top of the unit.

If a unit is to be installed on a roof curb other than a YORK roof curb, gasketing must be applied to all surfaces that come in contact with the unit under- side.

Before lifting, make sure the unit weight is distrib- uted equally on the rigging cables so it will lift evenly.

Units may be moved or lifted with a forklift. Slotted openings in the base rails are provided for this purpose.

LENGTH OF FORKS MUST BE A MINIMUM OF 60 INCHES (1524 mm).

All panels must be secured in place when the unit is lifted.

The condenser coils should be protected from rig- ging cable damage with plywood or other suitable material.

TABLE 3: UNIT WEIGHTS

Model

 

Shipping Weight lb. (kg)

Operating Weight lb. (kg)

 

 

 

 

BP090

 

1108 (503)

1103 (500)

 

 

 

 

 

 

BP120

 

1212

(550)

1207

(547)

 

 

 

 

Econ.

 

85 (39)

84 (38)

 

 

 

 

 

 

w/ PE

 

150

(68)

148

(67)

 

 

 

 

 

 

Elec.

 

49 (22)

49 (22)

Heat*

 

 

 

 

 

 

*.

54kW heater.

 

 

 

TABLE 4: 4 POINT LOAD WEIGHT

Model

 

Location lbs. (kg)

 

 

 

 

 

A

B

C

D

 

 

 

 

 

 

BP090

242 (109)

207 (94)

301 (137)

353 (160)

 

 

 

 

 

BP120

265 (120)

226 (103)

330 (150)

386 (175)

 

 

 

 

 

TABLE 5: 6 POINT LOAD WEIGHT

Model

 

 

Location lbs. (kg)

 

 

 

 

 

 

 

 

 

 

A

B

 

C

D

 

E

F

 

 

 

 

 

 

 

 

 

 

 

 

BP090

166

149

 

134

196

 

217

242

(75)

(68)

 

(61)

(89)

 

(98)

(110)

 

 

 

 

 

 

 

 

 

 

 

 

BP120

181

163

 

147

214

 

237

264

(82)

(80)

 

(67)

(97)

 

(108)

(120)

 

 

 

 

 

 

 

 

 

 

 

 

LEFT

A

 

FRONT

C

D

B

 

 

E

F

 

 

FRONT

LEFT

B

C

 

A

D

FIGURE 6 - UNIT 6 POINT LOAD

NOTE:(xxx)indicates dimensionsin milimeters

41" 24"

(1040) (610)

FIGURE 5 - UNIT 4 POINT LOAD

LEFT

FRONT

FIGURE 7 - UNIT CENTER OF GRAVITY

10

Unitary Products Group

Image 10
Contents Installation Manual 50 Hz Single Package Heat Pump High EfficiencyTable of Contents List of Figures List of Tables General Safety ConsiderationsInspection Renewal Parts ReferenceApprovals Ton York Model Number Nomenclature NomenclatureInstallation Safety Information InstallationPreceding Installation Unit Voltage Limitations LocationPoint Load Weight Unit WeightsRigging and Handling Unit Clearances ClearancesDetail B BttomPower Rear Duct Dimensions Ductwork Duct Covers Predator Roof Curb Dimensions Compressors Thermostat WiringControl Wire Sizes FiltersPower Wiring Detail Electronic Thermostat Field WiringGroundlug Electrical Data 7-1/2 TON HP Electrical Data 10 TON HPPhysical Data Factory Installed Options Field Installed AccessoriesElectric Heat Accessory Electric Heat OptionElectric Heat Minimum Supply AIR Enthalpy SET Point Chart Indoor AIR Quality AQSupply AIR Limitations Blower RotationBelt Tension Belt Adjustment Blower Performance 7-1/2 TON Standard Motor Side Duct Metric Blower Performance 10 TON Standard Motor Side Duct Imperial Blower Performance 10 TON Standard Motor Side Duct MetricBlower Performance 10 TON Optional Motor Side Duct Imperial Blower Performance 10 TON Optional Motor Side Duct MetricBlower Performance 7-1/2 TON Standard Motor Downshot Metric Blower Performance 10 TON Standard Motor Downshot Imperial Blower Performance 7-1/2 TON Optional Motor Downshot MetricBlower Performance 10 TON Standard Motor Downshot Metric Blower Performance 10 TON Optional Motor Downshot Imperial Indoor Blower SpecificationsBlower Performance 10 TON Optional Motor Downshot Metric Method ONE AIR BalanceChecking AIR Quantity Method TWOSupply AIR Drive Adjustment DRY Coil Delta PCFM Additional Static Resistance ImperialAdditional Static Resistance Metric M3SSequence of Operations Overview OperationMotor Sheave Datum Cooling Sequence of OperationCooling Operation Errors Compressor Protection Safety ControlsReset Heating Sequence of OperationSTART-UP Post Start Check List Operating InstructionsSuperheat Charging Method Superheat Charging Cooling Superheat 7-1/2 TONCooling Superheat 10 TON TroubleshootingPredator Flash Codes Unit Control Board Flash Codes Unit Control BoardCooling Troubleshooting Guide Page Page Unitary 5005 Norman Products York Group Drive 73069