Site Preparation

Incoming power supply requirements

NOTE: This equipment requires three-phase electrical service. Electrical service must conform to national and local electrical codes. The equipment must be grounded.

NOTE: To facilitate routing of main power supply wiring, run parallel wires for the main power connections.

Ductwork

Provide supply and return ducting at the site to connect to the supply and return ductwork on the EcoBreeze System.

See the ductwork drawings in submittal package for recommendations for ducting sizes and supply and return duct configurations.

Water supply

Supply water requirements. The water supply must be clean, potable water. The inlet water pressure provided to the unit must be between 207 and 448 kPa (30 and 65 psig). If the water pressure available is less than 207 kPa (30 psig), a booster pump (not supplied) may be needed to operate the equipment properly. If the water pressure available is higher than 448 kPa (65 psig), use an external pressure regulator (not supplied).

NOTE: Installation of back flow prevention and a water hammer arrestor is recommended.

NOTE: For 50 Hz models, use the pipe adapters to make the connections. See “Water supply connection” on page 18.

NOTICE

DAMAGE TO EQUIPMENT

External water piping must have adequate freeze protection and must be correctly applied based on local climatic conditions and best practices. Any exposed piping must be electrically heat-traced and insulated (supplied by others).

Failure to follow these instructions can result in equipment damage.

Foundation

Provide a foundation for the EcoBreeze System as recommended in the submittal package. Corner supports must have clamp connectors installed to secure the EcoBreeze Frame. See “Position the EcoBreeze” on page 14. Intermediate supports must have vibration damper pads installed on the top surface before the frame is placed on the permanent supports.

See EcoBreeze Frame Install Kit installation instructions for additional information.

8

EcoBreeze System Installation

Image 12
Contents Installation Manual EcoBreeze SystemSchneider Electric IT Corporation Legal Disclaimer Contents Mechanical Connections Electrical ConnectionsSafety General InformationStoring the equipment before installation Inspecting the EquipmentModel Identification Model identification label locationFrames ModulesAccess Door and Panel Operation Hazard of Electric ShockComponent Identification Description Quantity 20 ft 40 ftEcoBreeze Frame and Modules Item DescriptionModule front Remote display interfaceIncoming power supply requirements Ductwork Site PreparationWater supply FoundationEnvironment Piping/plumbing diagram Refrigeration Service access Wall or Other ObstructionWeights and Dimensions FrameInstallation Lifting and RiggingMechanical Connections Position the EcoBreezeUnwrap the equipment Remove the tension rods Lower Module drop-down box Water supply connection Drain AIR GAP Electrical Connections Power supply to EcoBreeze Frame Hazard to Equipment and PersonnelDDC Panel K4 N4 G4 198 193 195 190 196 197 126Building Management System Page Page Worldwide Customer Support