Mechanical Connections
Install the EcoBreeze Frame per the EcoBreeze Frame Install Kit instructions.
Position the EcoBreeze
NOTE: The power and plumbing connections for the EcoBreeze Frame are located on the end where the unpacking sheet is placed on the protective wrap. Typically this is the end that will face the building.
1.Ensure that clamp connectors and vibration damper pads are installed per the EcoBreeze Frame Install Kit instructions.
2.Use a crane with sufficient lifting capacity to place the EcoBreeze onto the permanent supports. Typically the end of the frame with plumbing and power connections is placed nearest to the building.
3.Using a
na3561a
14 | EcoBreeze System Installation |