Schneider Electric ACECFR20101SE, ACECFR20200SE, ACECFR40200SE Inspecting the Equipment

Page 6

Inspecting the Equipment

Inspect for missing components. All shipped loose components are identified by part number and description on the bill of lading. Ensure each item is present before accepting delivery of the unit.

Filing a claim. If damage has occurred, or if shipped loose parts are missing, report it immediately to the delivering carrier and note the problem on the receiving copy of the bill of lading. Failure to do so will result in replacement parts and repairs being billed to the customer.

In case of shipping damage, do not operate the equipment. Keep all packaging for inspection by the shipping company and contact Schneider Electric.

Storing the equipment before installation

WARNING

DAMAGE TO EQUIPMENT OR PERSONNEL

Do not remove tension rods until the EcoBreeze™ Frame is placed and secured on its supports.

Move the EcoBreeze Frame directly from the truck to its permanent foundation or supports. If it must be stored temporarily, it must be placed on a flat and level surface to avoid damage.

Leave the protective plastic wrap in place until you are prepared to install the equipment.

Failure to follow these instructions can result in death, serious injury, or equipment damage.

Heavy: Ensure the lifting equipment has sufficient capacity for the load.

The recommended tools for moving the equipment include the following:

Crane

(Frame,

ductwork)

2

EcoBreeze System Installation

Image 6
Contents Installation Manual EcoBreeze SystemSchneider Electric IT Corporation Legal Disclaimer Contents Mechanical Connections Electrical ConnectionsSafety General InformationStoring the equipment before installation Inspecting the EquipmentFrames Model IdentificationModel identification label location ModulesAccess Door and Panel Operation Hazard of Electric ShockComponent Identification Description Quantity 20 ft 40 ftEcoBreeze Frame and Modules Item DescriptionModule front Remote display interfaceWater supply Incoming power supply requirements DuctworkSite Preparation FoundationEnvironment Piping/plumbing diagram Refrigeration Service access Wall or Other ObstructionWeights and Dimensions FrameInstallation Lifting and RiggingMechanical Connections Position the EcoBreezeUnwrap the equipment Remove the tension rods Lower Module drop-down box Water supply connection Drain AIR GAP Electrical Connections Power supply to EcoBreeze Frame Hazard to Equipment and PersonnelDDC Panel K4 N4 G4 198 193 195 190 196 197 126Building Management System Page Page Worldwide Customer Support