Schneider Electric ACECFR40101SE, ACECFR20101SE Service access, Wall or Other Obstruction

Page 15

Service access

Install a service platform (not supplied) to facilitate maintenance activities. Regular maintenance activities require a of minimum 1219 mm (48 in.) clearance on all sides to remove, maneuver, and install Modules and components.

1219 (48)

1219 (48)

1219 (48)

1219 (48)

na3526a

NOTE: Consider local soil conditions, codes, and loading when determining appropriate support footings.

To prevent short cycling of outdoor air, each EcoBreeze Frame must have a minimum of 1219 mm (48 in.) clearance on each side, totaling 2438 mm (96 in.) between Frames, and 1219 mm (48 in.) at the end of the Frame.

1219 (48)

1219 (48)

2438 (96)

1219 (48)

 

WALL OR OTHER OBSTRUCTION

na3677a

 

* Dimensions are shown in millimeters with inches in parentheses.

EcoBreeze System Installation

11

Image 15
Contents EcoBreeze System Installation ManualSchneider Electric IT Corporation Legal Disclaimer Contents Electrical Connections Mechanical ConnectionsGeneral Information SafetyInspecting the Equipment Storing the equipment before installationModules Model IdentificationModel identification label location FramesHazard of Electric Shock Access Door and Panel OperationDescription Quantity 20 ft 40 ft Component IdentificationItem Description EcoBreeze Frame and ModulesRemote display interface Module frontFoundation Incoming power supply requirements DuctworkSite Preparation Water supplyEnvironment Piping/plumbing diagram Refrigeration Wall or Other Obstruction Service accessFrame Weights and DimensionsLifting and Rigging InstallationPosition the EcoBreeze Mechanical ConnectionsUnwrap the equipment Remove the tension rods Lower Module drop-down box Water supply connection Drain AIR GAP Electrical Connections Hazard to Equipment and Personnel Power supply to EcoBreeze FrameDDC Panel 126 K4 N4 G4 198 193 195 190 196 197Building Management System Page Page Worldwide Customer Support