Schneider Electric ACECFR40200SE, ACECFR20101SE, ACECFR20200SE Power supply to EcoBreeze Frame

Page 26

Power supply to EcoBreeze Frame

DANGER

HAZARD OF ELECTRIC SHOCK, EXPLOSION, OR ARC FLASH

Turn off all power supplying this equipment before working on the equipment. All electrical work must be performed by licensed electricians. Practice Lockout/Tagout procedures. Do not wear jewelry when working with electrical equipment.

Failure to follow these instructions will result in death or serious injury.

WARNING

HAZARD TO EQUIPMENT AND PERSONNEL

Only Schneider Electric authorized personnel may energize the equipment.

Failure to follow these instructions can result in death, serious injury, or equipment damage.

1.Use a punch tool to create an access hole as needed for power supply wires entering the main power enclosure.

2.Attach the conduit connector to the access hole on the main power enclosure.

NOTE: A service loop is factory-installed in the main power enclosure.

3.If permitted by local and national codes, route the cable to the disconnect switch as shown. If local and national codes do not permit service loops, make all connections per code.

4.Connect the power wiring to the disconnect switch. Connect the phases as marked next to the disconnect switch.

5.Connect the ground wire to the grounding lug beside the disconnect switch.

L1 L2

L3 GND

SUPPLY

BLOWER

ACCESS

na3490a

22

EcoBreeze System Installation

Image 26
Contents Installation Manual EcoBreeze SystemSchneider Electric IT Corporation Legal Disclaimer Contents Mechanical Connections Electrical ConnectionsSafety General InformationStoring the equipment before installation Inspecting the EquipmentFrames Model IdentificationModel identification label location ModulesAccess Door and Panel Operation Hazard of Electric ShockComponent Identification Description Quantity 20 ft 40 ftEcoBreeze Frame and Modules Item DescriptionModule front Remote display interfaceWater supply Incoming power supply requirements DuctworkSite Preparation FoundationEnvironment Piping/plumbing diagram Refrigeration Service access Wall or Other ObstructionWeights and Dimensions FrameInstallation Lifting and RiggingMechanical Connections Position the EcoBreezeUnwrap the equipment Remove the tension rods Lower Module drop-down box Water supply connection Drain AIR GAP Electrical Connections Power supply to EcoBreeze Frame Hazard to Equipment and PersonnelDDC Panel K4 N4 G4 198 193 195 190 196 197 126Building Management System Page Page Worldwide Customer Support