NOTE: Separate the drain line from the EcoBreeze Frame and the external drain line by a

50 mm (2 in.) air gap in order to prevent back up of contaminated water into the cooling system.

AIR GAP

na3564a

NOTE: Pitch the external drain piping at a minimum of 25 mm (1 in.) per 3048 mm (10 ft) towards the wastewater drain.

20

EcoBreeze System Installation

Image 24
Contents Installation Manual EcoBreeze SystemSchneider Electric IT Corporation Legal Disclaimer Contents Mechanical Connections Electrical ConnectionsSafety General InformationStoring the equipment before installation Inspecting the EquipmentModel Identification Model identification label locationFrames ModulesAccess Door and Panel Operation Hazard of Electric ShockComponent Identification Description Quantity 20 ft 40 ftEcoBreeze Frame and Modules Item DescriptionModule front Remote display interfaceIncoming power supply requirements Ductwork Site PreparationWater supply FoundationEnvironment Piping/plumbing diagram Refrigeration Service access Wall or Other ObstructionWeights and Dimensions FrameInstallation Lifting and RiggingMechanical Connections Position the EcoBreezeUnwrap the equipment Remove the tension rods Lower Module drop-down box Water supply connection Drain AIR GAP Electrical Connections Power supply to EcoBreeze Frame Hazard to Equipment and PersonnelDDC Panel K4 N4 G4 198 193 195 190 196 197 126Building Management System Page Page Worldwide Customer Support