Stovax PR0741 manual GAS Supply, Ventilation, AIR Vents Must not be Restricted

Page 15

INSTALLATION INSTRUCTIONS

SITE REQUIREMENTS

2.5Ensure that no naked flame or incandescent part of the fire bed projects beyond the vertical plane of the fireplace opening.

2.6The fire must not be installed in any room that contains a bath or shower.

2.7Ensure clearances to combustible materials - see diagram 3.

3

Dimensions given are to the frame of the fire.

AR0707

2.8The maximum depth of combustible shelf is 150mm at a minimum height of 150mm above the frame.

Refer to the appropriate Frame Instructions regarding additional wall strengthening for the frame.

3.GAS SUPPLY

3.1Before installation, ensure that the local distribution conditions (identification of gas and pressure) and the adjustment of the fire are compatible.

3.2Ensure that the gas supply is capable of delivering the required amount of gas, and is in accordance with the rules in force.

3.3This fire is supplied complete with a factory fitted isolation device incorporated into the inlet connection, no further isolation device is therefore required.

4.VENTILATION

It is important to ensure that any national ventilation requirements are taken into account during the installation of this fire.

4.1 This fire has a nominal input not exceeding 7.0kw and therefore does not normally require any additional permanent ventilation.

If, however, spillage is detected when commissioning the fire, there may be insufficient natural ventilation and additional ventilation may be required.

For ventilation requirements in the Republic of Ireland, it will be necessary to refer to the relevant rules in force.

AIR VENTS MUST NOT BE RESTRICTED.

15

Image 15
Contents Studio& Logic E-box Contents GAS CHECK APPLIANCE COMMISSIONING CHECKLISTFLUE CHECK Pass FailTurning the Fire OFF User InstructionsGeneral Lighting the FireCleaning the E-studio Cleaning the logic-e boxStudio Arrangement of Fuel BED Components AR1769 ADVICE ON HANDLING AND DISPOSAL OF FIRE CERAMICS Logic E-BOXArrangEMENT of fuel bed Components Large Medium Small Pebble Layout Running Installation detailsOxygen depletion sensor Flame failure deviceP8691CFCHUC Installation InstructionsTechnical Specification Studiomodels 8691CFCHUCHolyrood Spanish Finish Arts FrameOverall External Dimensions Plan View Site Requirements Flue and Chimney RequirementsFire Location GAS Supply VentilationAIR Vents Must not be Restricted Installation of the GAS Supply InstallationControl Upgrade Safety PrecautionsCable Retention Method Installation of the FireScrew Fixing Method Fitting the Decorative Inner panelAR1931 Logic E-BOX arrangEMENT of fuel bed components AR1364 Pebble Layout Installation / Commissioning Lighting the fireCommissioning Servicing Instructions ServicingServicing Requirements Studio & Logic E-BOX Servicing Instructions Fault Finding Charts Fault Finding Charts Piezo Replacing PartsGeneral Ignition LeadPilot injector Ignition electrode Thermocouple Ods pilot unitGas valve Mag unitMain injector Spare parts list-E-STUDIO Spare parts list Logic E-BOXChanging between gas types Service Records