Roberts Gorden HE20ST Operation, Tubing may still be hot, Heater Lockout Indication Optional

Page 63

SECTION 14: OPERATION

SECTION 14: OPERATION

DANGER

 

WARNING

 

Electrical Shock Hazard

Explosion Hazard

Burn Hazard

Cut/Pinch Hazard

Disconnect electric

Turn off gas supply to

Allow heater to cool

Wear protective gear

heater before service.

before service.

during installation,

before service.

 

 

operation and service.

 

 

Tubing may still be hot

More than one

 

Edges are sharp.

disconnect switch may

 

after operation.

be required to

 

 

 

disconnect electric from

 

 

 

heater.

 

 

 

Heater must be

 

 

 

connected to a properly

 

 

 

grounded electrical

 

 

 

source.

 

 

 

Failure to follow these instructions can result in death, electric shock, injury or property damage.

Figure 33: Sequence of Operation Chart

KEY TO

SYMBOLS

Thermostat

Fan

Pressure

P Switch

Neon

Ignition

Gas

Valve

Flame

Sensing

Lockout Alarm

Signal (optional)

T0

T1

T2

T3

T4

T5

T6

T7

T8

P

 

 

 

 

 

 

 

 

Fan Neon

 

 

 

 

 

 

 

 

Burner Neon

 

 

 

 

 

 

 

 

 

 

Tp

 

 

Tp

 

Ts

 

 

10 sec

 

 

10 sec

 

10 sec

 

 

40 sec max.

 

 

Interruption of main

 

Burner Lockout

11 sec typical

 

 

flame sensing

 

signal received after

 

 

 

 

 

 

 

3 ignition trial

 

 

 

 

 

 

 

 

failures

NOTE: If the heater operates for more than 24 hours continuously, the ignition module will automatically recycle the burner to ensure that all safety functions are still in working condition.

14.1 Heater Lockout Indication (Optional)

In case of flame loss during operation of the heater, the burner control unit goes to lockout mode after three ignition trials. At this stage a signal or closed relay will enable the ROBERTS GORDON® controller, BMS system, etc. to indicate precisely which heater has failed. This can be done by two options.

14.1.1 Heater Lockout Indicator by Connector

A 230 V signal is provided which enables the ROBERTS GORDON® controller, BMS system, etc. to indicate the heater that has failed. An additional wire has to be installed from the heater lockout indicator connector to the monitoring computer. See Page 56, Section 13.5.

57 of 73

Image 63
Contents Owner If you smell gasPage Roberts-Gordon Europe Limited Table of ContentsPage Table of Figures Bottom and Back Panel Label PlacementPage Product Approval Heater Safety Control Side Label Placement Installer Responsibility Low Level User InstructionsNational Standards and Applicable Codes Clearances to Combustibles Clearances Data Linear and Double Linear ModelHE40ST HE45ST HE50ST HE45ST HE50ST HE15ST HE30DLHE30UT HE15UTHE20UT HE25UTTUBE, Protective Grille TUBE, Opposite 45 TiltMajor Component Descriptions General Suspension Details Typical Suspension Details Linear & Double Linear Heater Installation Linear Standard Parts ListDescription Linear General Assembly Overview HE15ST f HE20ST HE25ST f HE35ST HE40ST fHE45ST HE50ST f Double Linear Standard Parts List Double Linear General Assembly Overview HE60DL HE70DL f HE30DL fClosed Burner Tube InstallationCoupling and Tube Assembly Open1 Coupling and Tube Assembly 2 Coupling and Tube AssemblyTighten slide bar as shown below Tube Clamp Package Installation Hanger Option a Option BFan Tube Weld Spot Coupling Tee Tube Standard Parts List Tube Heater InstallationLockwasher 6mm Blackheat HE Tube Assembly OverviewHE15UT g HE20UT g HE30UT HE35UT gHE45UT g Burner Tube and Fan Tube Installation U-tube Hanger Placement1 Tube Clamp Package Installation U-tube Support Bracket Assembly InstallationTube, Standard Tube, Opposite Orient coupling so that Impact block is U-tube Installation Tube InstallationReflector 02750303 Reflector Support Strap 03050000 Screw #8 x 3/4 Multiburner Configuration & Installation Typical Manifold Layout Linear and U-Tube Configuration Burner & FAN Installation Burner InstallationStandard Fan Assembly Linear & U-tube Fan Installation IP55 Fan Assembly1 Double Linear Fan Installation Double Linear Fan InstallationNon-Return Valve Condensate Drain AssemblyOptional Heater Accessories 2 Side Reflector Installation Reflector Side Extension Installation 1 Bracket InstallationStep Tube Cover InstallationDistance a Extension 2 Frame Shield Installation3 Grille Installation 2 Grille End Cap Installation3 Mesh Guard Connection Sports Hall Guard Installation2 Fastener Installation 1 Grille InstallationUndershield Installation 10.6.1 Hanger Installation Undershield InstallationAdjust Undershield Height Wall Mounting Hardware InstallationVenting and Fresh AIR Supply Air Supply Requirements Outside Combustion Air SupplyCommon Duct Air Supply with Flue ConfigurationsGAS Piping Correct Positions Incorrect Positions Wrong InstallationTypical External Wiring Diagram Linear or U-Tube WiringTypical External Wiring Diagram Multiburner Typical External Wiring Diagram Double Linear OptionInternal Wiring Diagram Tubing may still be hot Heater Lockout Indicator by ConnectorOperation and service OperationSystem Checks Heater Lockout Indicator by Volt Free ConnectorTesting Commissioning MultiburnerServicing Instructions Automatic Flame Control Unit Pressure SwitchMaintenance Checklist ElectrodeGas Line Vent PipeOutside Air Inlet TubesTroubleshooting U-Tube Troubleshooting Flow Chart Linear, Double LinearTroubleshooting Flow Chart Linear, Double Linear and U-Tube Troubleshooting Flow Chart MultiburnerTroubleshooting Flow Chart Multiburner Manometer 4 3 2 1 0 1 2 3 4 5 Manifold Gas Pressure SettingReplacement Parts V2 W3 Description Quantity Viewer Window Replacement Package P/NDoor Gasket Replacement Package P/N Gas Valve Replacement Package P/NSpecifications Linear Heater Double Linear HeaterTube Heater Burner Specifications Standard Burner SpecificationsModels HE15 HE20 HE25 HE30 HE35 HE40 HE45 HE50 Page Page Maintain Clearance Side Clearance below