Heat & Glo LifeStyle 8000CF-OAK-IPI, 8000CFLP-OAKIPI Top Vent Vertical Termination Two Elbows

Page 27

Top Vent - Vertical Termination - (continued)

Two Elbows

 

V1

H1 Maximum

V2

V1 + V2

Minimum

1 ft.

305 mm

3 ft.

914 mm

*

*

 

*

 

 

 

 

 

 

 

 

2 ft.

610 mm

6 ft.

1.8 m

*

*

 

*

 

 

 

 

 

 

 

 

4 ft.

1.2 m

12 ft.

3.7 m

*

*

 

*

V1 + V2 + H1 = 50 ft. (15.2 m) Max.

*No specific restrictions on this value EXCEPT V1 + V2 + H1 cannot exceed 50 ft. (15.2 m)

V2

Figure 7.11

H1

V1 = 1 ft. (305 mm) Min.

V1

Three Elbows

V2

 

V1

H1+ H2

V2

V1+ V2 Minimum

H1+ H2 Maximum

1 ft.

305 mm

3 ft.

914 mm

*

*

*

3 ft.

914 mm

2 ft.

610 mm

6 ft.

1.8 m

*

*

*

6 ft.

1.8 m

4 ft.

1.2 m

12 ft.

3.7 m

*

*

*

12 ft.

3.7 m

 

 

 

 

 

 

 

 

 

H1 + H2 = 17 ft. (5.2 m) Maximum

V1 + V2 + H1 + H2 = 50 ft. (15.2 m) Maximum

V1 = 1 ft. (305 mm) Minimum

H1

H2

V1

 

 

INSTALLED

 

HORIZONTALLY

Figure 7.12

Heat & Glo • 8000CF-OAK-IPI2059-900 Rev. R • 6/09

27

Image 27
Contents What to do if you smell gas HOT SurfacesHot glass will cause burns Congratulations Homeowner Reference InformationXxxxxxxx User Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingLimited Lifetime Warranty Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Clear Space Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Fan Kit optionalGAS Valve Lighting Instructions IPIFinal inspection by What to do if YOU Smell GASFrequently Asked Questions Issue SolutionsAfter Fireplace is Lit Remote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningLogs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingEither cobrahead or SIT Typical Appliance System Getting StartedAny such action may cause a fire hazard Design and Installation ConsiderationsTools and Supplies Needed Inspect Appliance and ComponentsSelecting Appliance Location Framing and ClearancesMinimum Framing Dimensions Constructing the Appliance ChaseClearances Mantel and Wall Projections Combustible MantelsCombustible Mantel Legs or Wall Projections Vent Termination Minimum Clearances Termination Locations= Vent Terminal = AIR Supply Inlet = Area Where Terminal is not PermittedUse of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyV1 Minimum H1 + H2 Maximum Vent Diagrams Top Vent Horizontal Termination One ElbowTwo Elbows V1 Minimum H1 MaximumV1 Min H1 Max V2 Min H2 Max V1 + V2 Min H1 + H2 Max Top Vent Horizontal Termination Three ElbowsVertical Top Vent ChartTop Vent Vertical Termination Two Elbows H1 Maximum V1 + MinimumH1+ H2 V1+ V2 Minimum H1+ H2 Maximum Required Vent Clearances and FramingPipe Clearances to Combustibles Heat Shield Above First 900 ElbowWall Penetration Framing Combustible Wall PenetrationNon-Combustible Wall Penetration Pipe DVP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Temporary Access Panel Appliance PreparationAttaching Sheetrock Ledges Securing and Leveling the Appliance Installing the Fiberglass GasketChecking Pilot Plate Completing Grate Set-upAssemble Pipe Sections Installing Vent PipeAttach Vent to the Firebox Assembly Assemble Vent SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Rotate Seams for DisassemblyAssemble and Install Storm Collar Install Metal Roof FlashingHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapAnsi Z223.1 and CAN/CGA-B149 installation codes Install Horizontal Termination CapGas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsIntellifire Ignition System Wiring Optional Accessories RequirementsIntellifire Pilot Ignition IPI Wiring Diagram Electrical Service and RepairWall Switch Installation for Fan Optional Junction Box InstallationFacing Material FinishingAppliance Setup Ember Placement Install the Optional RefractoryInstall the Log Assembly Log Assembly LOGS-8OAKHeat & Glo 8000CF-OAK-IPI 2059-900 Rev. R 6/09 Air Shutter Settings Install the MeshInstall Trim and/or Surround Air Shutter SettingTroubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System Ues to spark, and main Appliance Dimension Diagram Reference MaterialsLocation Inches Millimeters DVP vent components Vent Components DiagramsHorizontal Termination Cap DVP-TRAPCOOL-ADD RF6M RF12MBEK DVP-BEK2 DVP-TRAPFL305 mm DVP-TB1Service Parts Log Set AssemblyService Parts List StockedAt Depot Valve Assembly Contact Information