B. Assemble Slip Sections

Slide the inner flue of the slip section into the inner flue of the pipe section and the outer flue of the slip section over the outer flue of the pipe section. See Figure 10.5.

Slide together to the desired length.

Pilot hole

Figure 10.5 Slip Section Pilot Holes

Maintain a 1-1/2 in. (38 mm) overlap between the slip section and the pipe section.

Secure the pipe and slip section with two screws no longer than 1/2 in. (13 mm), using the pilot holes in the slip section. See Figure 10.6.

Figure 10.6 Screws into Slip Section

Continue adding pipe as necessary following instructions in “Assembling Pipe Sections.”

NOTICE: If slip section is too long, the inner and outer flues of the slip section can be cut to the desired length.

C. Secure the Vent Sections

Vertical runs must be supported every 8 ft. (2.44 m) after the 25 ft. (7.62 m) maximum unsupported rise.

Horizontal sections must be supported every 5 feet (1.52 m).

Vent supports or plumbers strap (spaced 120º apart) may be used to support vent sections. See Figures 10.7 and 10.8.

Wall shield firestops may be used to provide horizontal support vent sections.

WARNING! Risk of Fire, Explosion or Asphyxiation! Improper support may allow vent to sag and separate. Use vent run supports and connect vent sections per in- stallation instructions. DO NOT allow vent to sag below connection point to appliance.

120º

Figure 10.7 Securing Vertical Pipe Sections

120º

Figure 10.8 Securing Horizontal Pipe Sections

36

Heat & Glo • 8000CF-OAK-IPI2059-900 Rev. R • 6/09

Image 36
Contents What to do if you smell gas HOT SurfacesHot glass will cause burns Congratulations Homeowner Reference InformationXxxxxxxx Table of Contents User GuideAppliance Setup TroubleshootingFinishing Reference MaterialsLimited Lifetime Warranty Limited Lifetime Warranty Listing and Code Approvals Installation of Carbon Monoxide Detectors Requirements for the Commonwealth of MassachusettsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Fixed Glass Assembly Remote Controls, Wall Controls and Wall SwitchesFan Kit optional Clear SpaceLighting Instructions IPI Final inspection byWhat to do if YOU Smell GAS GAS ValveFrequently Asked Questions Issue SolutionsAfter Fireplace is Lit Maintenance and Service Maintenance Tasks-HomeownerGlass Cleaning Remote ControlMaintenance Tasks-Qualified Service Technician Gasket Seal and Glass Assembly InspectionVenting LogsEither cobrahead or SIT Getting Started Typical Appliance SystemDesign and Installation Considerations Tools and Supplies NeededInspect Appliance and Components Any such action may cause a fire hazardFraming and Clearances Selecting Appliance LocationMinimum Framing Dimensions Constructing the Appliance ChaseClearances Mantel and Wall Projections Combustible MantelsCombustible Mantel Legs or Wall Projections Termination Locations Vent Termination Minimum Clearances= Area Where Terminal is not Permitted = Vent Terminal = AIR Supply InletVent Information and Diagrams Approved PipeVent Table Key Use of ElbowsVent Diagrams Top Vent Horizontal Termination One Elbow Two ElbowsV1 Minimum H1 Maximum V1 Minimum H1 + H2 MaximumTop Vent Horizontal Termination Three Elbows V1 Min H1 Max V2 Min H2 Max V1 + V2 Min H1 + H2 MaxChart Vertical Top VentTop Vent Vertical Termination Two Elbows H1 Maximum V1 + MinimumH1+ H2 V1+ V2 Minimum H1+ H2 Maximum Vent Clearances and Framing Pipe Clearances to CombustiblesHeat Shield Above First 900 Elbow RequiredWall Penetration Framing Combustible Wall PenetrationNon-Combustible Wall Penetration Install the Ceiling Firestop Pipe DVPInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Temporary Access Panel Appliance PreparationAttaching Sheetrock Ledges Installing the Fiberglass Gasket Securing and Leveling the ApplianceCompleting Grate Set-up Checking Pilot PlateInstalling Vent Pipe Attach Vent to the Firebox AssemblyAssemble Vent Sections Assemble Pipe SectionsAssemble Slip Sections Secure the Vent SectionsRotate Seams for Disassembly Disassemble Vent SectionsInstall Metal Roof Flashing Assemble and Install Storm CollarInstall Vertical Termination Cap Heat Shield Requirements for Horizontal TerminationInstall Horizontal Termination Cap Ansi Z223.1 and CAN/CGA-B149 installation codesGas Information Fuel ConversionGas Pressure Gas ConnectionWiring Requirements Intellifire Ignition System WiringOptional Accessories Requirements Electrical InformationElectrical Service and Repair Intellifire Pilot Ignition IPI Wiring DiagramJunction Box Installation Wall Switch Installation for Fan OptionalFinishing Facing MaterialAppliance Setup Install the Optional Refractory Ember PlacementLog Assembly LOGS-8OAK Install the Log AssemblyHeat & Glo 8000CF-OAK-IPI 2059-900 Rev. R 6/09 Install the Mesh Install Trim and/or SurroundAir Shutter Setting Air Shutter SettingsTroubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System Ues to spark, and main Appliance Dimension Diagram Reference MaterialsLocation Inches Millimeters Vent Components Diagrams DVP vent componentsDVP-TRAP Horizontal Termination CapRF6M RF12M BEK DVP-BEK2DVP-TRAPFL COOL-ADDDVP-TB1 305 mmLog Set Assembly Service PartsService Parts List StockedAt Depot Valve Assembly Contact Information