ÎG. Install Vertical Termination Cap

Attach the vertical termination cap by sliding the inner collar of the cap into the inner flue of the pipe section while placing the outer collar of the cap over the outer flue of the pipe section.

Secure the cap by driving three self-tapping screws (supplied) through the pilot holes in the outer collar of the cap into the outer flue of the pipe (see Figure 10.15).

TERMINATION CAP

(1 of 3)

STORM

COLLAR

SCREWS

CAULK

Figure 10.15

H.Heat Shield Requirements for Horizontal Termination

WARNING! Risk of Fire! To prevent overheating and fire, heat shields must extend through the entire wall thick- ness.

DO NOT remove the heat shields attached to the wall shield firestop and the horizontal termination cap (shown in Figure 10.16).

Heat shields must overlap 1-1/2 in. (38 mm) mini- mum.

There are two sections of the heat shield. One section is factory-attached to the wall shield firestop. The other section is factory-attached to the cap. See Figure 10.16.

If the wall thickness does not allow the required 1-1/2 in. (38 mm) heat shield overlap when installed, an extended heat shield must be used.

If the wall thickness is less than 4 in. (102 mm), the heat shields on the cap and wall shield firestop must to be trimmed. A minimum 1-1/2 in. (38 mm) overlap MUST be maintained.

Use an extended heat shield if the finished wall thickness is greater than 7-1/4 in. (184 mm).

The extended heat shield may need to be cut to length maintaining sufficient length for a 1-1/2 in. (38 mm) overlap between heat shields.

Attach the extended heat shield to either of the existing heat shields using the screws supplied with the extended heat shield. Refer to vent components diagrams in the back of this manual.

Rest the small leg on the extended heat shield on top of the pipe section to properly space it from the pipe section.

Important Notice: Heat shields may not be field constructed.

Heat & Glo • 8000CF-OAK-IPI2059-900 Rev. R • 6/09

39

Image 39
Contents What to do if you smell gas HOT SurfacesHot glass will cause burns Congratulations Homeowner Reference InformationXxxxxxxx User Guide Table of ContentsReference Materials Appliance SetupTroubleshooting FinishingLimited Lifetime Warranty Limited Lifetime Warranty Listing and Code Approvals Requirements for the Commonwealth of Massachusetts Installation of Carbon Monoxide DetectorsGas Fireplace Safety Operating Instructions User GuideYour Fireplace Clear Space Fixed Glass AssemblyRemote Controls, Wall Controls and Wall Switches Fan Kit optionalGAS Valve Lighting Instructions IPIFinal inspection by What to do if YOU Smell GASFrequently Asked Questions Issue SolutionsAfter Fireplace is Lit Remote Control Maintenance and ServiceMaintenance Tasks-Homeowner Glass CleaningLogs Maintenance Tasks-Qualified Service TechnicianGasket Seal and Glass Assembly Inspection VentingEither cobrahead or SIT Typical Appliance System Getting StartedAny such action may cause a fire hazard Design and Installation ConsiderationsTools and Supplies Needed Inspect Appliance and ComponentsSelecting Appliance Location Framing and ClearancesMinimum Framing Dimensions Constructing the Appliance ChaseClearances Mantel and Wall Projections Combustible MantelsCombustible Mantel Legs or Wall Projections Vent Termination Minimum Clearances Termination Locations= Vent Terminal = AIR Supply Inlet = Area Where Terminal is not PermittedUse of Elbows Vent Information and DiagramsApproved Pipe Vent Table KeyV1 Minimum H1 + H2 Maximum Vent Diagrams Top Vent Horizontal Termination One ElbowTwo Elbows V1 Minimum H1 MaximumV1 Min H1 Max V2 Min H2 Max V1 + V2 Min H1 + H2 Max Top Vent Horizontal Termination Three ElbowsVertical Top Vent ChartTop Vent Vertical Termination Two Elbows H1 Maximum V1 + MinimumH1+ H2 V1+ V2 Minimum H1+ H2 Maximum Required Vent Clearances and FramingPipe Clearances to Combustibles Heat Shield Above First 900 ElbowWall Penetration Framing Combustible Wall PenetrationNon-Combustible Wall Penetration Pipe DVP Install the Ceiling FirestopInstall Attic Insulation Shield Flat Ceiling InstallationVaulted Ceiling Installation Temporary Access Panel Appliance PreparationAttaching Sheetrock Ledges Securing and Leveling the Appliance Installing the Fiberglass GasketChecking Pilot Plate Completing Grate Set-upAssemble Pipe Sections Installing Vent PipeAttach Vent to the Firebox Assembly Assemble Vent SectionsSecure the Vent Sections Assemble Slip SectionsDisassemble Vent Sections Rotate Seams for DisassemblyAssemble and Install Storm Collar Install Metal Roof FlashingHeat Shield Requirements for Horizontal Termination Install Vertical Termination CapAnsi Z223.1 and CAN/CGA-B149 installation codes Install Horizontal Termination CapGas Connection Gas InformationFuel Conversion Gas PressureElectrical Information Wiring RequirementsIntellifire Ignition System Wiring Optional Accessories RequirementsIntellifire Pilot Ignition IPI Wiring Diagram Electrical Service and RepairWall Switch Installation for Fan Optional Junction Box InstallationFacing Material FinishingAppliance Setup Ember Placement Install the Optional RefractoryInstall the Log Assembly Log Assembly LOGS-8OAKHeat & Glo 8000CF-OAK-IPI 2059-900 Rev. R 6/09 Air Shutter Settings Install the MeshInstall Trim and/or Surround Air Shutter SettingTroubleshooting Symptom Possible Cause Corrective ActionIntellifire Ignition System Ues to spark, and main Appliance Dimension Diagram Reference MaterialsLocation Inches Millimeters DVP vent components Vent Components DiagramsHorizontal Termination Cap DVP-TRAPCOOL-ADD RF6M RF12MBEK DVP-BEK2 DVP-TRAPFL305 mm DVP-TB1Service Parts Log Set AssemblyService Parts List StockedAt Depot Valve Assembly Contact Information