Vertical Through-the-Roof Installation

Chateau™

Max. Height

40' (12 m)

Min. Height

20' (6 m)

Max. 20' (6 m)

Pipe Straps Every 3’ (914mm)

Max. 8' (2.4m)

4

1 + 2 + 3 + 4 = 270°

3

12

Minimum 2’ (610mm)

Before Any Elbow

FP1244a

Fig. 28 Support straps for horizontal runs.

Up to two (2) 30° or 45° elbows may be used within the horizontal run. For each 30° or 45° elbow used on the horizontal level the maximum horizontal length must be reduced by 18” (457 mm). Example: Maximum horizontal length

0 x 30° or 45° elbows = 10’ (3 m)

1x 30° or 45° elbows = 8’6” (2.6 m)

2 x 30° or 45° elbows = 7’ (2.1 m)

A minimum of an 12’ (3.7 m) vertical rise.

Two sets of 30° or 45° elbows offsets within these vertical installations. From 0 to a maximum of 8’ (2.4 m) of vent pipe can be used between elbows. (Fig. 29)

SKCS8 must be used to support offsets. (Fig. 32) This application will require that you first determine the roof pitch and use the appropriate starter kit. (Refer to Venting Components List)

The minimum height of the vent above the highest point of penetration through the roof is 2’ (610 mm). (Fig. 33)

 

 

 

 

 

FP1245a

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

FP1245a

 

 

Fig. 29 Typical offset application.

Vertical Through-the-Roof Installation

1.Locate your fireplace.

2.Plumb to center of the (8”) flue collar from ceiling above and mark position.

3.Cut opening equal to 14¹⁄” x 14¹⁄” (368 mm x 368 mm).

4.Proceed to plumb for additional openings through the roof. In all cases, the opening must provide a minimum of 1¹⁄” (38 mm) clearance to the vent pipe, i.e., the hole must be at least 14¹⁄” x 14¹⁄” (368 mm x 368 mm).

5.Place fireplace into position.

6.Place firestop(s) SKFS2A or Attic Insulation Shield AIS-SK into position and secure. (Figs. 30, 31)

7.Install roof support (Fig. 32) and roof flashing making sure upper flange of flashing is below the shingles.

8.Install appropriate pipe sections until the venting is above the flashing.

9.Seal around the pipe.

10.Add additional vent lengths for proper height. (Fig. 33)

22

20011956

Image 22
Contents INSTALLER/CONSUMER SAFETY INFORMATION Installation Instructions and Homeowner’s ManualModel: DVT38IN, DVT44IN ChateauChateau Table of Contents20011956 DVT38IN / DVT44IN Certified To Installation & Operating InstructionsChateau 20011956Chateau Fireplace Dimensions - DVT38INFireplace Dimensions - DVT44IN 20011956Clearance to Combustibles ChateauLocating Your Fireplace MantelsFinal Finishing HearthFraming and Finishing ChateauGas Inlet and Manifold Pressures Gas Line InstallationGas Specifications High ElevationsControl System Control System InstallationElectrical Junction Box ChateauChateau Special Feature for Cold Climates20011956 MODE Remote Control Transmitter Operating InstructionsON H/L ChateauChateau Setting F / C ScaleSetting Desired Room Temperature Manual FunctionSETTING “LOCK-OUT”- CP CONTINUOUS PILOT FEATURECP CHILDPROOF FEATURE ChateauOperational Notes Thermostatic Updating FeatureChateau 20011956Location of Vent Termination General VentingChateau 20011956Chateau Canadian Installations1US Installations2 18” 458 mm for non-vinylsoffitsTermination Clearances Chateau20011956 Horizontal Termination General Information Assembling Vent PipesSK8 Venting Pipes Vertical TerminationHorizontal Venting Applications Sidewall ApplicationsUse of the Restrictor Plates in ChateauSTEP Sidewall InstallationChateau STEPSTEP Chateau20011956 for Vertical Venting Applications Vertical Through-the-Roof ApplicationsUse of Restrictor Plate ChateauChateau Vertical Through-the-RoofInstallation20011956 Chateau Attic InstallationCeiling Installation Min 2 610mmComponent Chimney ComponentsChateau DescriptionRestrictor Plate Installation Glass Frame Assembly RemovalGlass Cleaning Operating InstructionsAppliance Ceramic Refractory InstallationChateau Kit ModelDVT38IN Logs Log, Lava Rock and Ember PlacementChateau 20011956DVT44IN Logs Chateau20011956 9.Position the Log Rear Left Chateau20011956 12. Position the Log Front Middle Right Chateau20011956 Fig. 48 DVT38IN logset complete Chateau20011956 Fig. 49 DVT44IN logset completeDVT38 Flame CharacteristicsChateau DVT4420011956 Trim InstallationChateau Fig. 53 Trim frame in placebefore Lighting the Appliance For Your Safety, Read the Following WarningsLighting & Operating Instructions Lighting InstructionsAmerican Flame Gas Control System TroubleshootingChateau 20011956Main flame will not light Chateau20011956 What to Check American Flame Gas Control System Error CodesChateau What to CheckFuel Conversion Instructions Conversion PrecautionsConversion Procedure ChateauConverting the Gas Control Valve Chateau20011956 Table Table 2 Air Shutter SettingsPilot Flame Adjustment Injector Orifice Size MatrixChateau MaintenanceCleaning the Control System 20011956Chateau DVT38IN, DVT44INFor Units GFYN5Q0, GFYN500 20011956Description DVT38IN, DVT44IN continuedChateau DVT38INDescription DVT38IN, DVT44IN continuedChateau DVT38INCeramic Refractory Kits AccessoriesBack-upBattery Kit ChateauChateau 20011956LIMITED LIFETIME WARRANTY LIMITED LIFETIME WARRANTYIF WARRANTY SERVICE IS NEEDED BASIC ONE-YEARWARRANTYEfficiency Ratings CFM Corporation