Munchkin 399M manual Fill and Purge Heating System

Page 19

PIPING

C.FILL AND PURGE HEATING SYSTEM

Attach the hose to balance and purge hose connector or drain valve and run hose to near- est drain

Close the other side of the balance and purge valve or the shut off valve after the drain.

Open first zone balance and purge or drain valve to let water flow out the hose. If zone valves are used, open the valves one at a time manually. (Note: please check valve manu- facturer’s instruction prior to opening valves manually, so as not to damage the valve.)

Manually operate fill valve regulator. When water runs out of the hose, while it’s connect- ed to the balance and purge valve or drain you will see a steady stream or water (with no bubbles). Close balance and purge valve or drain to stop the water from flowing. Disconnect the hose and connect it to next zone to be purged.

Repeat this procedure for additional zones (one at time).

Upon completion, make sure that the fill valve is in automatic position and each zone balance and purge or shut off is in an open position and zone valves are positioned for automatic operation.

CAUTION

For installation that incorporates standing Iron Radiation and systems with manual vents at the high points. Follow above section and starting with the nearest manual air vent, open vent until water flows out, then close vent. Repeat procedure, working your way toward furthest air vent. It may be necessary to install a basket strainer in an older system where larger amounts of sediment may be present. Annual cleaning of the strainer may be necessary.

WARNING

Use only inhibited propylene glycol solutions which are specially formulated for hydronic systems. Ethylene glycol is toxic and can attack gaskets and seals used in hydronic systems.

1.Glycol in hydronic applications which is specially formulated for this purpose includes inhibitors which prevent the glycol from attacking metallic system components. Make certain that the system fluid is checked for the correct glycol concentration and inhibitor level.

2.The glycol solution should be tested at least once a year and as recommended by the glycol manufacturer.

3.Anti-freeze solutions expand more than water. For example a 50% by volume solution expands 4.8% in volume for a temperature increase from 32° F to 180° F, while water expands 3% with the same temperature rise. Allowances must be made for this expansion in the sys- tem design.

4.A 30% mixture of glycol will result in a BTU output loss of 15% with a 5% increase in head against system circulator.

5.A 50% mixture of glycol will result in a BTU output loss of 30% with a 50% increase in head against system circulator.

CAUTION

It is highly recommended that you carefully follow the glycol manufacturer’s recommended concentrations, expansion requirements and maintenance recommendations (pH additive breakdown, inhibitor reduction, etc.). You must carefully figure the additional friction loss in the system as well as the reduction in heat transfer co-efficients.

19

Image 19
Contents What to do if YOU Smell GAS Munchkin High Efficiency 399M Commercial BoilerUsing this Manual Using this ManualTable of Contents HOW IT Operates Munchkin Ratings and DimensionsPart 1. General Information General InformationDimensions PRE-INSTALLATION Requirements Electrical Connection Part 2. ElectricalGeneral Information / Electrical Pressure Relief ValveElectrical Electrical / GAS Connection Part 3. GAS ConnectionGAS Table GAS ConnectionGAS Connection GAS PipingMunchkin Burnertech GAS Valve Combustion SettingsVenting the Munchkin in 4 or 6 Plastic Pipe Part 4. VentingVenting Approved Venting MaterialsVenting Important Note Fittings or Piping Equivalent Feet Longer Vent Runs Using a Combination 4 to 6 PipeHeater Removal from a Common Vent System Diagrams for Sidewall VentingDiagram for Vertical Venting Hydronic Piping with Circulators or Zone Valves Part 5. PipingVenting / Piping Condensate RequirementsCirculator Sizing PipingFill and Purge Heating System Piping Illustrations Piping Symbol LegendZone valves Make-up water Zone valves Mixing valve Zone valves Make-up water Piping Space heating zone circuit Zone Circulators Make-up water PB1 PB2 PB1 PB2 Lighting Instructions Part 6. START-UP ProceduresSTART-UP Procedures Items to be Checked Before Lighting the MunchkinOperating Instructions Adjusting the Temperature on the Munchkin DisplayStatus Menu Test ModeTo Turn OFF GAS to Appliance Sequence of Operation START-UP Procedures / ServicingMunchkin Temporary Fault Condition Part 7. ServicingServicing Munchkin Fault Requiring Manual ResetServicing Remedy Call Factory for further assistance Resistance Tables Maintenance Part 8. MaintenanceLeaks Munchkin Controller Control Wiring LayoutMaintenance Maintenance Page Page Heat Transfer Products, Inc LP-121 REV /20/04