Munchkin 399M manual Piping, Circulator Sizing

Page 18

PIPING

pound. Threaded connections are 2” NPT Brass nipples located on the left hand side of unit.

2.Connect the system supply marked “Heater Out”, make sure to install with pipe sealant com- pound. Threaded connections are 2” NPT Brass nipples located on the left hand side of the unit.

3.Install Purge and Balance Valve or shut off valve and drain on system return to purge air out of each zone.

4.Install a Back Flow preventor on the Cold Feed Make-Up Water line.

5.Install a Pressure Reducing Valve on the Cold Feed Make-Up Water line, (15 PSI nominal on the system return). Check Temperature and Pressure Gauge which should read minimum pressure of 12 PSI.

6.Install a circulator on system supply. Make sure the circulator is properly sized for the system and friction loss.

7.Install an Expansion Tank on the system supply. Consult the tank manufacturer’s instruction for specific information relating to tank installation. Size the expansion tank for the required system volume and capacity.

8.Install an Air Elimination Device on the system supply.

9.Install a drain valve at the lowest point of the system. Note: The Munchkin can not be drained completely of water without purging the unit with an air pressure 15 PSI.

10.The Safety Relief Valve is installed at the factory located on the right hand side of Munchkin. Pipe the discharge of safety relief valve to prevent injury in the event of pressure relief. Pipe the discharge to a drain. Provide piping that is the same size as the safety relief valve outlet. Never block the outlet of safety relief valve.

See the piping illustrations included in this section, Figs. 5-3 to 5-11 for suggested guidelines in piping the Munchkin heater with either zone valves or circulator pumps.

*Please note that these illustrations are meant to show system piping concept only, the installer is responsible for all equipment and detailing required by local codes.

B. CIRCULATOR SIZING

The Munchkin Heat Exchanger does have pressure drop which must be considered in your system design. Refer to the graph below for pressure drop through the Munchkin Heat Exchanger.

 

32

 

 

 

 

 

 

 

 

 

30

 

 

 

 

 

 

 

 

 

28

 

 

 

 

 

 

 

 

 

26

 

 

 

 

 

 

 

 

Head

24

 

 

 

 

 

 

 

 

22

 

 

 

 

 

 

 

 

20

 

 

 

 

 

 

 

 

of

 

 

 

 

 

 

 

 

18

 

 

 

 

 

 

 

 

Feet

 

 

 

 

 

 

 

 

16

 

 

 

 

 

 

 

 

14

 

 

 

 

 

 

 

 

in

 

 

 

 

 

 

 

 

12

 

 

 

 

 

 

 

 

Friction

 

 

 

 

 

 

 

 

10

 

 

 

 

 

 

 

 

8

 

 

 

 

 

 

 

 

 

6

 

 

 

 

 

 

 

 

 

4

 

 

 

 

 

 

 

 

 

2

 

 

 

 

 

 

 

 

 

0

 

 

 

 

 

 

 

 

 

5

10

15

20

25

30

35

37.5

40

Flow in Gallons per Minute

MUNCHKIN 399M

Circulator Sizing Sizing Chart

BOILER

TACO P/N

GRUNDFOS P/N

Bell & Gossett

399M

1400-50

UPS 32-160

PL-55

*THE RECOMMENDED CIRCULATORS ARE BASED ON 1 GPM PER 10,000 BTU/HR W/20

Figure 5-1

18

Image 18
Contents Munchkin High Efficiency 399M Commercial Boiler What to do if YOU Smell GASUsing this Manual Using this ManualTable of Contents General Information Munchkin Ratings and DimensionsPart 1. General Information HOW IT OperatesDimensions PRE-INSTALLATION Requirements Pressure Relief Valve Part 2. ElectricalGeneral Information / Electrical Electrical ConnectionElectrical Part 3. GAS Connection Electrical / GAS ConnectionGAS Piping GAS ConnectionGAS Connection GAS TableCombustion Settings Munchkin Burnertech GAS ValveApproved Venting Materials Part 4. VentingVenting Venting the Munchkin in 4 or 6 Plastic PipeVenting Important Note Longer Vent Runs Using a Combination 4 to 6 Pipe Fittings or Piping Equivalent FeetDiagrams for Sidewall Venting Heater Removal from a Common Vent SystemDiagram for Vertical Venting Condensate Requirements Part 5. PipingVenting / Piping Hydronic Piping with Circulators or Zone ValvesPiping Circulator SizingFill and Purge Heating System Piping Symbol Legend Piping IllustrationsZone valves Make-up water Zone valves Mixing valve Zone valves Make-up water Piping Space heating zone circuit Zone Circulators Make-up water PB1 PB2 PB1 PB2 Items to be Checked Before Lighting the Munchkin Part 6. START-UP ProceduresSTART-UP Procedures Lighting InstructionsAdjusting the Temperature on the Munchkin Display Operating InstructionsTest Mode Status MenuTo Turn OFF GAS to Appliance Part 7. Servicing START-UP Procedures / ServicingMunchkin Temporary Fault Condition Sequence of OperationMunchkin Fault Requiring Manual Reset ServicingServicing Remedy Call Factory for further assistance Resistance Tables Part 8. Maintenance MaintenanceLeaks Control Wiring Layout Munchkin ControllerMaintenance Maintenance Page Page Heat Transfer Products, Inc LP-121 REV /20/04