Lochinvar 45000, 260000 service manual Electrical connections, Terminal Strip Wiring

Page 34

Installation & Service Manual

5Electrical connections

This appliance is wired for 120 VAC service. The appliance, when installed, must be electrically grounded in accordance with the requirements of the authority having jurisdiction or in the absence of such requirements, with the latest edition of the National Electrical Code ANSI/NFPA No. 70. When the unit is installed in Canada, it must conform to the CSA C22.1, Canadian Electrical Code, Part 1 and/or local Electrical Codes.

1.All wiring between the appliance and field installed devices shall be made with type T wire [63° F(35° C) rise].

2.Line voltage wire exterior to the appliance must be enclosed in approved conduit or approved metal clad cable.

3.The pump must run continuously when the appliance is being fired.

4.To avoid serious damage, DO NOT energize the appliance until the system is full of water. Serious damage may result.

5.Provide the unit with proper overload protection.

6.Install a wall thermostat on the inside wall. DO NOT install the thermostat in an area affected by drafts, sunlight, light fixtures, hot or cold water pipes or near a fireplace. See “Room Thermostat or Remote Thermostat Connection to Terminal Strip” (this page), for proper wiring connection.

Boiler Operating Temperature Control

The operating temperature control is located in the control panel, behind the control panel front access door. The sensing element for the operator is placed in a bulbwell installed in the heat exchanger. Carefully observe the inlet water temperature on the initial boiler on cycles. The exact temperature set point is based on your system’s requirements. Turn the control set point dial to the desired operating water temperature. Observe the boiler discharge temperature after each set point adjustment to ensure proper operation.

Room Thermostat or Remote Thermostat Connection to Terminal Strip

A room thermostat or remote temperature control may be connected to the boiler. The room thermostat should be installed on an inside wall, away from the influences of drafts, hot or cold water pipes, lighting fixtures, televisions, sun rays or fireplaces. Follow the manufacturers instructions supplied with the thermostat for proper installation and adjustment. The boiler is equipped with a terminal strip on the left side of the control panel to allow easy connection (FIG. 5-1).

Remove the jumper between the R and W terminals on the terminal strip. Refer to the chart in this section (Table 5A) to determine maximum allowable length and wire gauge recommended to connect the switching contacts of the room thermostat to the R and W terminals on the terminal strip. Connection to the terminal strip will allow the room thermostat to make and break the 24VAC boiler control circuit turning the boiler on and off based on the room ambient temperature requirements. Set the boiler operating temperature control as described in this section.

B

A

Figure 5-1_Terminal Strip Connections

TABLE - 5A

TERMINAL STRIP WIRING

 

Wire Gauge

Maximum

 

 

Allowable Length

 

 

 

 

 

 

 

 

 

12 GA

100 ft.

 

 

 

 

 

 

14 GA

75 ft.

 

 

 

 

 

 

16 GA

50 ft.

 

 

 

 

 

 

18 GA

30 ft.

 

 

 

 

 

Auxiliary Device Connection to Terminal Strip

A terminal connection strip is provided for ease of connection for Power Venting Systems, see FIG. 5-1, inset A.

A field supplied powered venter or powered louver/damper may be connected to the Solution boiler via a terminal strip located on the left side of the unit, see FIG. 5-1, inset B.

A 24 VAC relay can be powered from this location when a call for heat has been established. A device proving switch can be interlocked back to the appliance to ensure its operation before the appliance is allowed to fire.

Reference the wiring diagram on page 50 of this manual.

34

Image 34
Contents Models 45,000 260,000 Btu/hr Contents Warranty Please read before proceedingCodes Solution Boiler =B=R Rating RatingsSolution How it works Temperature and pressure gaugeSolution How it works Solution How it works Determine boiler location Location of unit3Combustion Air Direct from Outside 6Combustion Air from Outside Single Opening Minimum Recommended Combustion AIR Supply to Equipment Room Conventional Negative Draft Venting System VentingVent Pipe Sizes Venting Vertical Vent Termination Clearances Less from Ridge From Parapet WallVent Materials Masonry Chimney InstallationSidewall Venting Negative Draft Fan Assisted VentingAutomatic Vent Damper 7Vent Damper and Vent Damper Terminal BlockGas Supply Gas Pressure Test Gas connectionsGas Connection Install Piping to Control Gas PipingGas Manifold Pressure Adjustment Procedure 2WrenchChecking Gas Supply Pressure 4Gas Supply PressureVenting of Combination Gas Valves Combination Gas ValvesTwo Stage Burner Control System Water connections Water Flow Switch if equippedRelief Valve Minimum Required Flow For Heating Boiler Typical Heating Boiler InstallationsLow Water Cutoff if equipped General Plumbing RulesSystem Temperature Rise Chart Piping of the Boiler SystemWater Connections Heat Exchanger Pressure Drop ChartCirculator Pump Requirements Primary/Secondary Boiler Piping Circulator Pump SpecificationsCirculator Pump Operation Full Flow Application Low Temperature Bypass RequirementsBoiler Flow Rates Primary / Secondary Piping Make UP WaterMake UP Water 6Multiple Boilers Zoned with Circulators Full System Flow From System8Single Boiler Full System Flow with Low Temperature Bypass Electrical connections Terminal Strip WiringBoiler Operating Temperature Control Auxiliary Device Connection to Terminal StripTemperature Adjustment AMP Draw DataMaximum SET Point Determination Maximum Set Point DeterminationWiring of Remote Sensors Outdoor Air Temperature SensorInstallation of Remote Sensors Outdoor Air Reset Option Additional Temperature ControlsBlocked Vent and Flame Roll-Out / Flame Interlock Switch 7Blocked Vent Switch LocationInitial Start-up Pre-start ChecklistStart-up Lighting Instructions for Spark Ignition Pilot ModelsOperating Instructions Safety Shutoff Test for Spark Ignition Pilot SystemTo Turn Off Gas to Appliance Water Treatment Intermittent Pilot Spark Ignition SystemFreeze Protection Ignition and Control TimingsOwner maintenance Maintenance Maintenance and annual startupService technician See the User’s Information Manual for instructionsMaintenance Check Expansion Tank Check Relief ValveHeat Exchanger / Burner Access Check All WiringCheck Control Settings Perform Start-up and ChecksInspection and Cleaning Breathing Fresh airGas Train and Controls Review with ownerInspection of Heat Exchanger Waterways Water Circulating PumpTroubleshooting Troubleshooting Guide M9 Solution BoilersWiring Diagram M9 Unit 45,000 260,000 Btu/hr Models DiagramsSchematic Diagram M9 Unit 45,000 260,000 Btu/hr Models