Figure 5: Recommended Water Piping for Zone Valve Zoned Heating Systems

D. Install Drain Valve in return piping. See Figure 5.

E.Oil, grease, and other foreign materials which accumulate in new hot water boilers and a new or reworked system should be boiled out, and then thoroughly flushed. A qualified water treatment chemical specialist should be consulted for recommendations regarding appropriate chemical compounds and concentrations which are compatible with local environmental regulations.

F. After the boiler and system have been cleaned and flushed, and before refilling the entire system add appropriate water treatment chemicals, if necessary, to bring the pH between 7 and 11.

G.Fill entire heating system with water and vent air from system. Use the following procedure on a Series

Loop System equipped with zone valves. (See Figure

5).

1.Close isolation valve in boiler supply piping.

2.Isolate all circuits by closing zone valves or balancing valves.

3.Attach a hose to hose bib located just below isolation valve in boiler supply piping. (Note

- Terminate hose in five gallon bucket at a suitable floor drain or outdoor area).

4.Starting with one circuit, open zone valve.

5.Open hose bib.

6.Open fill valve (Make-up water line should be located directly above isolation valve in boiler supply piping).

7.Allow water to overflow from bucket until discharge from hose is bubble free for 30 seconds.

8.Open zone valve to the second zone to be purged, then close the first. Repeat this step until all zones have been purged, but always have one zone open. At completion, open all zone valves.

9.Close hose bib, continue filling the system until the pressure gauge reads 12 psi. Close fill valve. (Note - If make-up water line is equipped with pressure reducing valve, system will automatically fill to 12 psi.

10.Open isolation valve in boiler supply piping.

11.Remove hose from hose bib.

10

Image 10
Contents Ledv Series 81433101R16-1/10 Price $3.00Important Information Read Carefully Page Table of Contents Water Content 6.1 gallons Pre-Installation Do not drop boiler. Do not bump boiler jacket II. Unpack Boiler Against floor Minimum Clearances to Combustible Materials III. Water Piping and Trim Page Page IV. Venting / Air Intake Piping General GuidelinesVent Pipe Part Numbers Intake Terminal LocationVent Installation Vent Connector, Assembled Air Intake Installation Direct Vent only See Figure Page Electrical Electrical and Sequence of OperationsSequence of Operations Beckett Burner Schematic Wiring Diagram Page General VI. Oil PipingSingle-pipe Oil Lines Two-Pipe Installation Two-Pipe Oil LinesVII. System Start-up Always Inspect Installation Before Starting BurnerAdjusting Settings Ii. DisplayLED Error Codes Control Operating CharacteristicsBurner START-UP Check / Adjust OIL Pressure Riello BF Burner SettingsInstall Pressure Gauge Remove Test Plug in Flue CollarHints on Combustion Simulate flame failure Simulate power failureTest Controls Simulate ignition failurePage Firetubes and Combustion Chamber Section Viii Service and CleaningBurner Low water cutoff if so equipped Avoid Breathing Fiber Particulates and Dust IX. Repair Parts Ledv Boiler Trim & ControlsLedv Boiler Jacket & Insulation Ledv Bare Boiler Assembly PartsRepair KitVent Beckett Afii Oil Burner Repair Part Beckett Afii Burner Replacement Parts Service Record Low Water Cut Off Lwco on Hot Water Boilers Wiring of Typical LwcoLwco Location Limited Warranty