Burnham 81433101R16-1/10 manual IV. Venting / Air Intake Piping, General Guidelines

Page 12

IV. Venting / Air Intake Piping

A.General Guidelines

1.Vent system installation must be in accordance with these instructions and applicable provisions of local building codes. Contact local building or fire officials about restrictions and installation inspection in your area.

2.The LE®DV Series is designed as a Direct Vent boiler. In this configuration, all air for combustion is supplied directly to the burner from outdoors and flue gases are vented directly outdoors (through wall). See Figures 10 and 11. The LEDV may be side-wall vented with combustion air supplied from indoors. This configuration may be used in installations where infiltration provides adequate air for combustion and ventilation. Flue gases are still vented directly outdoors (through wall).

3.For minimum clearances to combustible materials refer to Figure 2.

4.Maximum wall thickness that vent terminal may be installed through is 10 inches.

WARNING

DO NOT locate vent terminal where exposed to prevailing wind. Moisture and ice may form on surfaces around vent termination. To prevent deterioration, surfaces should be in good repair (sealed, painted, etc.).

5.Locate the vent terminal so vent pipe is short and direct, and at a place on the exterior wall that complies with the minimum distances as specified in

Figure 8 and listed below. The vent terminal must be located:

a.Not less than 12 inches above grade plus snow accumulation (as measured to the nearest edge of terminal).

b.Not less than 3 feet to center of terminal above any forced air inlet located within 10 feet.

c.Not less than 1 foot to center of terminal horizontally from any door, window or gravity air inlet.

d.Not less than 7 feet to center of terminal above a public walkway.

e.Not less than 3 feet to center of terminal from an inside corner of an L-shaped structure.

f.Not less than 1 foot from nearest surface of terminal to a roof soffit.

g.Not directly above, or not less than 6 feet horizontally from an oil tank vent or gas meter.

h.Not less than 2 feet from nearest surface of terminal to an adjacent building.

Figure 8: Vent Terminal Location

12

Image 12
Contents Ledv Series 81433101R16-1/10 Price $3.00Important Information Read Carefully Page Table of Contents Water Content 6.1 gallons Pre-Installation II. Unpack Boiler Do not drop boiler. Do not bump boiler jacketAgainst floor Minimum Clearances to Combustible Materials III. Water Piping and Trim Page Page IV. Venting / Air Intake Piping General GuidelinesVent Pipe Part Numbers Intake Terminal LocationVent Installation Vent Connector, Assembled Air Intake Installation Direct Vent only See Figure Page Electrical and Sequence of Operations ElectricalSequence of Operations Beckett Burner Schematic Wiring Diagram Page VI. Oil Piping GeneralSingle-pipe Oil Lines Two-Pipe Installation Two-Pipe Oil LinesAlways Inspect Installation Before Starting Burner Adjusting SettingsVII. System Start-up Ii. DisplayControl Operating Characteristics LED Error CodesBurner START-UP Riello BF Burner Settings Install Pressure GaugeCheck / Adjust OIL Pressure Remove Test Plug in Flue CollarHints on Combustion Simulate power failure Test ControlsSimulate flame failure Simulate ignition failurePage Section Viii Service and Cleaning Firetubes and Combustion ChamberBurner Low water cutoff if so equipped Avoid Breathing Fiber Particulates and Dust IX. Repair Parts Ledv Boiler Trim & ControlsLedv Boiler Jacket & Insulation Ledv Bare Boiler Assembly PartsRepair KitVent Beckett Afii Oil Burner Repair Part Beckett Afii Burner Replacement Parts Service Record Wiring of Typical Lwco Low Water Cut Off Lwco on Hot Water BoilersLwco Location Limited Warranty