Maintenance is an essential part of the safe and efficient operation of the boiler and ensures its durability. It should be performed according to the instructions given in current legislation. Perform combustion analysis regularly in order to check the operating efficiency of the boiler and to make sure the combustion is within the boundaries set by current legislation.

Before beginning maintenance work:

-Disconnect the appliance from the electricity supply by turning the external bipolar switch to the “OFF” position;

-Remove the fuse;

-Close the gas valve and the central heating and domestic hot

water system valves.

After the work has been completed the initial settings will be restored.

General comments

It is recommended that the following inspections be carried out on the boiler at least once a year:

1.Check the seals in the water part and, if necessary, replace the gaskets and restore the seal to perfect working order.

2.Check the seals in the gas part and, if necessary, replace the gaskets and restore the seal to perfect working order.

3.Visually check the overall condition of the boiler.

4.Visually check the combustion and, if necessary, disassemble and clean the burner.

5.Following the inspection detailed in point “3”, disassemble and clean the combustion chamber, if necessary.

6.Following the inspection detailed in point “4”, disassemble and clean the burner and injector, if necessary.

7.Cleaning the primary heat exchanger

8.Make sure the following heating safety devices are operating correctly:

-temperature limit safety device.

9.Make sure that the following gas part safety devices are operating correctly:

-absence of gas or flame safety device (ionisation).

10.Check the efficiency of the domestic hot water production process (test the flow rate and temperature).

11.Perform a general inspection of the boiler operation.

12.Remove oxide from the detection electrode using an emery cloth.

13.After servicing, complete the relevant Service Interval Record section of the Benchmark Checklist located on page 54 of this manual.

14.These checks are not exhaustive. Further mechanical, electrical and combustion maintenance checks may be required.

15.Analyse combustion, see page 33.

Operational test

After having carried out the maintenance operations, fill the heating circuit at a pressure of approximately 1.5 bar and release the air from the system.

Fill the domestic hot water system at the same time.

-Begin operating the boiler.

-If necessary, release the air from the heating system again.

-Check the settings and make sure all the command, adjustment and monitoring parts are working correctly.

-Check the flue system is sealed and operating correctly.

Draining procedures

The heating system must be drained using the following procedure:

-Switch off the boiler, make sure the external bipolar switch is in the OFF position;

-Loosen the automatic air relief valve;

-Open the system drain off cock and collect the escaping water in a container;

-Empty the water from the lowest points of the system (where applicable).

If the system is to be left inactive in areas where the room temperature may fall below 0°C during winter, we recommend that anti-freeze

liquid is added to the water in the heating system in order to avoid the need for repeated draining; when this liquid is used make sure it is compatible with the stainless steel used for the bodywork of the boiler. We recommend the use of anti-freeze products which contain PROPYLENE GLYCOLS as these inhibit corrosion and that they are used in conjunction with the anti-scaling and anti-corrosion function, in the quantities suggested by the manufacturer, at the mimimum temperature.

Regularly check the pH level of the water/anti-freeze mix in the boiler circuit and replace it when the value measured is lower than the limit prescribed by the manufacturer.

DO NOT MIX DIFFERENT TYPES OF ANTI-FREEZE.

The manufacturer will not be held liable for any damage caused by the appliance or the system due to the use of inappropriate anti-freeze substances or additives.

Draining the domestic hot water system (E-COMBI)

Every time there is a danger of freezing, the domestic hot water system must be drained as follows:

-Shut off the water mains inlet valve;

-Open all the hot and cold water taps;

-Empty the water from the lowest points of the system (where applicable).

WARNING

Before handling, empty all components which may contain hot water, performing bleeding where necessary.

Descale the components in accordance with the instructions provided on the safety data leaflet supplied with the product used, make sure the room is well ventilated, wear protective clothing, avoid mixing different products, and protect the appliance and surrounding objects. Seal all openings used to take a gas pressure reading or to make any gas adjustments.

Make sure that the nozzle is compatible with the supplied gas.

If a smell of burning is detected or smoke is seen leaking from the appliance, or there is a smell of gas, disconnect it from the electricity supply, shut off the gas valve, open the windows and call for technical assistance.

Cleaning the primary exchanger

The inside of the primary exchanger is accessed by removing the burner. Wash with water and detergent using a non-metallic rifle-type brush, rinse with water.

The trap is accessed by emptying the condensate bowl located in the bottom section. Wash with water and detergent.

Replace the condensate collection bowl in its housing.

NB: In the event of prolonged of the appliance, the trap must be filled before being used again.

A lack of water in the siphon is dangerous and may cause exhaust gases to be released into the atmosphere.

Combustion Analyses

Details for flue gas analyses can be found on page 33.

Using a suitable calibrated combustion analyser, perform a combus- tion check. The CO2 valus can be found on page 33.

if the vlues are correct the CO/CO2 ratio must be less than 0.004. Where combustion readings cannot be achieved carrefully check items such as the burner, heat exchanger, flue system for defect.

Once satisfactors readings hane been achieved complete the relevant service interval record selection of the Benchmark Commissioning Checklist at the rear of this publication.

33

Image 33
Contents Combi 24/30/38 System24/30 Maintenance InstallationMaintenance guide OverviewTo the Installer OverviewBenchmark Scheme Advice for the installer Symbols used on the data plateCE labelling Noisiness during operation Safety regulationsPersonal injury caused by falling from a height Personal injury caused by knocks, stumbling etcControl panel Product descriptionOverall view Flue connector W. Flow switch Manual air ventMinimum clearances Overall DimensionsModel E-COMBI Technical DataModel E-SYSTEM Installation System Controls Flushing and Water TreatmentLocation Boiler is equipped with a stainless steel heat exchangerCondensate Discharge Installing the Boiler Connecting the boiler to the systemMethod of positioning the boiler on the wall Safety Valve Discharge and Condense Outlet Gas connection Is connected to the 3 bar safety relief valveConnection for Filling Loop Mbar Manual air vent Burner Water circuit diagramSecondary heat exchanger Pressure relief valve By-pass Condensate trap Circuit filterConnecting the Flue Vertically from a terminal on the same wall180 Fitting the Coaxial Flue 60 / 100 Horizontal Contents4x Screws 2x SealsFitting the Coaxial Flue Ø 60 / 100 Vertical Fitting the 5 Flue Ø 80 / 125 Horizontal/verticalFitting the Twin Pipe Ø80 120 180 Type of air suction/flue gas exhaust ducting Table of flue gas exhaust duct lengthsExhaust-air m Type Combustion air intake from outsideElectrical connections Power supply cablePeripheral unit connection 120Room Thermostat / Remote Clock Connection Connector TA on Terminal blockDisplay Electrical diagramCommissioning Electricity supply Initial preparationFilling the Heating System Filling of the DHW System Combi onlyMeasure the gas inlet pressure. standing + warming pressure First ignition operationCheck the type of gas and change the gas if necessary Analyse the combustion see Adjust the central heating ignition delay Setting Regulating the central heating ignition delay Adjust the setting on the front panel Irst ignitionGas setting Checking the gas settingTest function and combustion analysis Minimum gas flow combustion analysisBoiler protection devices Maintenance General access Maintenance guideMin Tools TimeElectrical unit Control box access Tools Time MinFuse Tools Time Open the control box as above Remove the fuseDisplay P.C.B Tools Time Main P.C.B Tools TimeHydraulic Unit Right hand hydraulic block assemblyDraining Tools Time Way valve unit Tools TimePrimary water pressure sensor Tools Time Automatic air vent Tools TimePump Tools Time Filter Tools Time W. Flow Switch assembly E-COMBI Tools TimeSecondary Heat Exchanger E-COMBI Tools Time Left hand Hydraulic block assemblyUnscrew the condense trap from the condense body Condensate Trap Tools Safety valve TimeTemperature Sensor By-Pass Assembly Tools TimeMain Heat Exchanger Tools Time Manual Air vent Tools TimeIsolate the gas supply. Remove the four ChangerFan Burner unitElectrodes Spark generatorBurner Power Length VenturiFan Gas valve By-pass & Safety valve Annual Maintenance Plate heat exchangerFlow switch operation Central heating filterProbe problem Fault finding Overheat InsufficientEeprom Error ErrorGAS Boiler System Commissioning Checklist Service 1 Date Service ProviderService 3 Date Service 5 DateShort List 420010275800