Ariston E-COMBI 24 30 38 Fault finding Overheat Insufficient, Circulation, Insufficient water

Page 52

maintenance guide

Fault finding

Overheat

 

 

 

Insufficient

Water pressure

circulation

 

 

 

 

Bleed heat exchanger

 

 

 

Pump operation

 

 

 

CH return filter for blockages

 

 

 

Circulation around boiler (blockages)

 

 

 

ntc temperature sensors

 

 

 

 

Insufficient water

Water pressure gauge for correct pressure

(request filling)

 

 

 

 

Check for waterleaks on the entire system

 

 

 

 

CH Flow temp.

Check connections and wiring to temp

probe circuit open/

sensors

short circuit

 

 

 

CH Flow temp.

Resistance values of temp sensors

probe circuit open/

 

short circuit

 

 

 

Heating delivery

Details in maintenance guide in installation

probe problem

manual

 

 

 

 

Floor thermostat

Check terminals TA2 for presence of link

contact open

wire

 

 

 

 

EEPROM Error

Check the EEPROM connection onto the

 

pcb

 

 

Communication

Check connection and wiring onto all

error

devices, main and display pcb

 

 

Main PCB error

 

 

 

 

 

Too many (>5)

Identify reason for lockout from table and

resets in 5 minutes

check for relevant faults

 

 

 

 

No Flame detected

Insufficient working gas pressure

 

 

1st Ignition failed

Spark electrode/wiring connectors

 

 

2nd Ignition failed

Ignition electrode/wiring connectors

 

 

Flame cut-off

Spark generator/wiring connectors

 

 

 

Check flue system for correct assembly/

 

termination

 

 

 

Check earth

 

 

 

Gas valve

 

 

 

CO2 settings

 

 

 

Soft light rate

 

 

Flame detected

Ignition electrode/wiring connectors

with gas valve

 

closed

 

 

 

 

Ignition electrode wiring connection onto

 

main pcb

 

 

 

 

Flame lift

Insufficient working gas pressure

 

 

 

Check flue system for correct assembly/

 

termination

 

 

 

CO2 settings

 

 

 

 

Thermofuse open

Check wiring and connections to

 

thermofuse

 

 

 

Check integriry of main heat exchanger

 

 

 

 

Fan speed error

Check fan

 

 

 

Check wiring connections from fan to pcb

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

52

Image 52
Contents Combi 24/30/38 System24/30 Installation MaintenanceMaintenance guide OverviewOverview To the InstallerBenchmark Scheme Symbols used on the data plate Advice for the installerCE labelling Safety regulations Noisiness during operationPersonal injury caused by falling from a height Personal injury caused by knocks, stumbling etcProduct description Control panelFlue connector W. Flow switch Manual air vent Overall viewOverall Dimensions Minimum clearancesTechnical Data Model E-COMBIModel E-SYSTEM Installation Flushing and Water Treatment System ControlsLocation Boiler is equipped with a stainless steel heat exchangerCondensate Discharge Connecting the boiler to the system Installing the BoilerMethod of positioning the boiler on the wall Is connected to the 3 bar safety relief valve Safety Valve Discharge and Condense Outlet Gas connectionConnection for Filling Loop Mbar Water circuit diagram Manual air vent BurnerSecondary heat exchanger Pressure relief valve By-pass Condensate trap Circuit filterVertically from a terminal on the same wall Connecting the Flue180 60 / 100 Horizontal Contents Fitting the Coaxial Flue4x Screws 2x SealsFitting the 5 Flue Ø 80 / 125 Horizontal/vertical Fitting the Coaxial Flue Ø 60 / 100 VerticalFitting the Twin Pipe Ø80 120 180 Table of flue gas exhaust duct lengths Type of air suction/flue gas exhaust ductingExhaust-air m Type Combustion air intake from outsidePower supply cable Electrical connectionsPeripheral unit connection 120Connector TA on Terminal block Room Thermostat / Remote Clock ConnectionElectrical diagram DisplayCommissioning Initial preparation Electricity supplyFilling the Heating System Filling of the DHW System Combi onlyFirst ignition operation Measure the gas inlet pressure. standing + warming pressureCheck the type of gas and change the gas if necessary Analyse the combustion seeSetting Regulating the central heating ignition delay Adjust the central heating ignition delayAdjust the setting on the front panel Irst ignitionChecking the gas setting Gas settingTest function and combustion analysis Minimum gas flow combustion analysisBoiler protection devices Maintenance Maintenance guide General accessMin Tools TimeControl box access Tools Time Min Electrical unitFuse Tools Time Open the control box as above Remove the fuseMain P.C.B Tools Time Display P.C.B Tools TimeRight hand hydraulic block assembly Hydraulic UnitWay valve unit Tools Time Draining Tools TimeAutomatic air vent Tools Time Primary water pressure sensor Tools TimePump Tools Time W. Flow Switch assembly E-COMBI Tools Time Filter Tools TimeLeft hand Hydraulic block assembly Secondary Heat Exchanger E-COMBI Tools TimeCondensate Trap Tools Safety valve Time Unscrew the condense trap from the condense bodyBy-Pass Assembly Tools Time Temperature SensorManual Air vent Tools Time Main Heat Exchanger Tools TimeIsolate the gas supply. Remove the four ChangerBurner unit FanSpark generator ElectrodesPower Length Venturi BurnerFan Gas valve Annual Maintenance Plate heat exchanger By-pass & Safety valveFlow switch operation Central heating filterFault finding Overheat Insufficient Probe problemEeprom Error ErrorGAS Boiler System Commissioning Checklist Service Provider Service 1 DateService 3 Date Service 5 DateShort List 420010275800