Greenheck Fan 470654 manual Installation

Page 7
Spreader Bar

Installation

Concrete Slab

The first step in unit installation is to pour a concrete slab capable of holding the unit weight as a base. The slab should have a proper gravel drainage bed.

Concrete Slab Dimensions

Housing Size

A

B

C

D

E

20

64

64

42

40

40

 

 

 

 

 

 

30

77

76

42

52

53

 

 

 

 

 

 

40

78

135

42

54

111

 

 

 

 

 

 

50

87

180

42

63

153

 

 

 

 

 

 

All dimensions are shown in inches.

NOTE

If optional service platform is included, a minimum of 42 inches must be added to Dimension B.

Building Wall

Approx. Stand Feet Locations

 

 

 

 

 

 

 

 

 

 

 

Concrete Slab

 

 

ControlUnitSide

withRequiredservice onlyplatform

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

A

 

 

 

 

 

 

D

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

E

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

12

 

 

 

 

12

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

B C

Concrete Slab and Unit Footprint

Service and Access Clearance

The slab should be positioned to allow 3 feet of clearance on the control end of the unit and 2 feet of clearance on the other three sides. Housing size 50 requires 3 feet of clearance on both ends because of filters access. Note that the concrete forms a 1 foot wide apron on all four sides of the unit unless a 42 in. extension is added to the control end of the unit.

Clearance to Combustibles

 

Floor

Top

 

Sides

Ends

Insulated/

0 in.

0 in.

 

0 in.

0 in.

Units

(0 mm)

(0 mm)

 

(0 mm)

(0 mm)

Non Insulated

0 in.

6 in.

 

6 in.

6 in.

Units

(0 mm)

(152.4 mm)

 

(152.4 mm)

(152.4 mm)

Clearance to combustibles is defined as the

minimum distance required

between the heater and adjacent combustible surfaces to ensure the adjacent surface’s temperature does not exceed 90 degrees above the ambient temperature.

Burner/Blower Section

Use a crane and a spreader bar hooked to the factory lifting lugs (shown below) to lift and center the unit onto the filter stand section. The sections should be caulked together.

Install Ductwork

This table shows the duct sizes and straight lengths recommended for optimal performance (AMCA Publication 201-90). Using duct sizes less than recommended will affect fan performance. Good duct installation practices should be followed for the remaining ductwork.

Recommended Supply Ductwork Sizes

VSU

Duct Size

Straight Duct Length

Blower Size

(in.)

(in.)

 

 

 

108

10x13

32

 

 

 

109

14x13

38

 

 

 

110

16x14

42

 

 

 

112

18x16

48

 

 

 

115

19x16

49

 

 

 

118

24x22

64

 

 

 

120

28x28

79

 

 

 

218

68x24

114

 

 

 

220

68x26

118

 

 

 

225

104x37

175

 

 

 

230

104x37

203

 

 

 

Model VSU Make-Up Air 7

®

Image 7
Contents Model VSU General Safety Information Installation, Operation and Maintenance ManualHandling Inspection and Maintenance during StorageReceiving UnpackingTable of Contents Subassemblies Product OverviewOpen View Burner, Blower and Control Center SectionControl Center Burner SubassemblyDampers Installation Installation of Optional Service Platform Complete InstallationService Platform Material List Figure C AssemblyInstallation of Electrical Wiring Install Additional Regulator if Required Installation of Direct Gas PipingDetermine the Supply Gas Requirements Installation of Building Pressure Control optional Unit Model Number Start-Up ChecklistCheck blower rotation Check for vibration Supply fan RPM Start-Up Blower Check the Supply Gas Pressure Check the Optional High and Low Gas Pressure SwitchesStart-Up Direct Gas Set-Up Optional ComponentsMeasuring the Pressure Drop Maximum firing rate adjustmentSet the Burner Air Pressure Differential Set the Maximum Firing RateSet the Minimum Firing Rate Regulators and Modulating ValvesFlame Signal Check Pilot Ignition Set the Unit’s Operating TemperatureMaxitrol Series 44 9 Terminals The Maxitrol Modulating Variable Volume OperationOperation VAV Units optional SpeedElectrical Sequence Exhaust Fan Contact S1 Closed optional Operation Recirculating Units optionalOperation Electrical Recirculation OperationHeat Contact Closed Flame Safeguard FSG Sequence3a. Heat Contact S4 Closed Pilot Ignition 3b. Heat Contact S4 Closed Direct SparkBlower Does Not Operate TroubleshootingMotor Overamps Too Much Airflow Insufficient AirflowExcessive Noise or Vibration Does not attempt to light No visible spark Heater Does Not Operate Pilot IgnitionAttempts to light, but no pilot visible spark Between 0.625 and 0.675 in. WC? Visible pilotHeater Does Not Operate Direct Spark Attempts to light, but no flame Visible spark Wheels Maintenance RoutineBelt Drives MotorsMaintenance Fall Reference Typical Gas Train Layout with Direct Spark Ignition Control Center Layout Dirty Filter SwitchFan Relay allows power to pass to energize motor starter Heat Relay allows power to pass to heating controlsWarranty Maintenance LogDateTime AM/PM