Step 2.

Set the gas appliance in its desired location. Drop a plumb bob down from the ceiling to the position of the appliance flue exit, and mark the location where the vent will penetrate the ceiling. Drill a small hole at this point. Next, drop a plumb bob from the roof to the hole previously drilled in the ceiling, and mark the spot where the vent will penetrate the roof. Determine if ceiling joists, roof rafters, or other framing will obstruct the venting system. You may wish to relocate the appliance, or to offset, as shown in Figure 5.13 to avoid cutting load bearing members. When location is determined, drill small hole.

PLUMBER'S TAPE

CONNECTED TO

WALL STRAP

WALL

STRAP

TWO 45 DEGREE

ELBOWS

Figure 5.13

Step 4.

Assemble the desired lengths of pipe and elbows necessary to reach from the appliance up through the round support box. Ensure that all pipe and elbow connections are in their fully twist-locked position. Assemble as instructed.

Step 5.

Cut a hole in the roof centered on the small drill hole placed in the roof in Step 2. The hole should be of sufficient size to meet the minimum requirements for clearance to combustibles, as specified. Continue to assemble lengths of pipe and elbows necessary to reach from the ceiling support box/wall thimble up through the roof line. Galvanized pipe and elbows may be utilized in the attic, as well as above the roofline. The galvanized finish is desirable above the roofline, due to its higher corrosion resistance.

NOTE:

(1) If an offset is necessary in the attic to avoid obstructions, it is important to support the vent pipe every 3 ft. (914mm) to avoid excessive stress on the elbows, and possible separation. Wall straps are available for this purpose,

Figure 5.13.

(2)Whenever possible, use 45° elbows, instead of 90° elbows. The 45° elbow offers less restriction to the flow of flue gases and intake air.

Step 6.

Slip the flashing over the pipe section(s) protruding through the roof. Secure the base of the flashing to the roof with roofing nails. Ensure the roofing material overlaps the top edge of the flashing as shown in Figure 5.15. Verify that the chimney is the required height above the roof (see roof pitch table, Figure 4.3 on page 8).

Step 3.

To install the round support box/wall thimble cover in a flat ceiling, cut a 10 in. (254mm) square hole in the ceiling, centered on the hole drilled in Step 2. Frame the hole as shown in Figure 5.14.

CEILING JOISTS

FRAMING

ROUND CEILING

SUPPORT BOX/WALL

THIMBLE COVER

1-1/2 in. (38mm) LONG

WOOD SCREWS

Figure 5.14

SHINGLES OVERLAP ON

TOP EDGE OF FLASHING

CAP AND STORM COLLAR NOT SHOWN FOR CLARITY

Figure 5.15

Page 16

Quadra-Fire • Columbia Bay • 250-5195 Rev. K

10/08

Image 16
Contents What to do if you smell gas COLBAY-FS-BDo not Discard this Manual Do DiscardnotSerial Number Barcode Model Name Test Lab Report NoTable of Contents 1Listing and Code Approvals BELOW. Keep Clear of ALL Obstructions Requirements for the Commonwealth of MassachusettsManufacturer Requirements Design & Installation Considerations Getting StartedInspect Appliance & Components Tools and Supplies NeededSelecting Appliance Location Appliance Location and ClearancesClearances 4Termination Locations Vent Termination Minimum ClearancesAlcove Applications Vent Information Venting ComponentsUse of Elbows Measuring StandardsVenting Guidelines How to Use the Vent GraphVertical Distance From Appliance to To the 90 Elbow Horizontal Termination Step Wallline Thimble Fold Strap Here Sheet Metal Screw Vertical Termination Direct Vent PipeStep Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Top Adapter Flex Pipe Sheet Metal Screws StepExisting Masonry Chimney Retro Connector Fuel Conversions Gas InformationConverting to LP Gas Valve Regulator Replacement Gas Pressures Gas Connection PressureCheck for GAS Leaks Recommendation for Wire Connecting to the ApplianceStanding Pilot Ignition System Wiring Electrical InformationThermopile GAS Pilot Ignitor Thermocouple Appliance Setup AccessoriesBrick Installation Door Crown Installation Remove Shipping MaterialsInstall NEW Brick SET Positioning the LogsGlass Door Replacement Mineral WoolBlower Installation BlackVertical Damper Adjustment Shutter AdjustmentBefore Lighting Appliance Operating InstructionsControls For Your Safety Read Before Lighting Lighting ApplianceFrequently Asked Questions After Appliance is LitTroubleshooting Symptom Possible Cause Corrective ActionBe Placed in this Opening Maintaining and Servicing Your Appliance After servicingMaintenance Tasks Inspect Service and Maintenance Log Appliance Dimension Diagram Reference MaterialsVent Components Diagram SLP Series Vent ComponentsVent Components List MiscellaneousLog Set Assembly Part number list on followingAt Depot StockedPedestal Components StockedDepot Valve ComponentsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Serial Number Date Purchased Date Installed Dealer Telephone Columbia Bay Direct Vent Gas Appliance