2. Cathedral Ceiling

Step 1.

Follow installation Steps 1 and 2 under vertical installation section, pages 15-16.

Step 2.

Remove shingles or other roof covering as necessary to cut the rectangular hole for the support box. Cut the hole 1/8 in. (3mm) larger than the support box outline.

Step 3.

Lower the support box through the hole in the roof until the bottom of the support box protrudes at least 2 in. (51mm) below the ceiling (Figure 5.18). Align the support box both vertically and horizontally with a level. Temporarily tack the support box in place through the inside walls and into the roof sheathing.

Figure 5.19

LEVEL

CATHEDRAL CEILING SUPPORT BOX

Step 6.

Place the support clamp (provided with the support box) inside the support box (at the bottom), and secure to the pipe section. The clamp allows the support box to support the weight of the pipe sections. Continue to add pipe sections until you are above the roofline.

Step 7.

CUT HOLE 1/8 in. (3mm) GREATER IN SIZE THAN PATTERN OF SUPPORT BOX AS IT IS PROJECTED ONTO ROOF LINE

Figure 5.18

Step 4.

2 in. (51mm)

MIN. BELOW FINISHED CEILING

Complete the cathedral ceiling installation by following the same procedures outlined in steps 7 through 9 for vertical installations, page 17.

Step 8.

Install the black trim collar around the outside of the cathedral ceiling support box (Figure 5.20). The two pieces of the trim collar slide over one another to allow for easy adjustment around the support box. Using the six screws provided, secure the four corners and the overlapping sections of the trim collar to the ceiling. You may want to predrill the holes for the overlapped sections for ease of installation.

Using tin snips, cut the support box from the top corners down to the roofline, and fold the resulting flaps over the roof sheathing (Figure 5.19). Before nailing it to the roof, run a bead of non-hardening mastic around the top edges of the support box to make a seal between it and the roof. Clean out any combustible material from inside the support box.

Step 5.

Assemble the desired lengths of pipe and elbows necessary to reach from the appliance up through the round support box. Ensure that all pipe and elbow connections are in their fully twist-locked position. Assemble as instructed.

TRIM COLLAR

CATHEDRAL

CEILING

SUPPORT SCREWS

BOX

Figure 5.20

Page 18

Quadra-Fire • Columbia Bay • 250-5195 Rev. K

10/08

Image 18
Contents Do not Discard this Manual What to do if you smell gasCOLBAY-FS-B Do DiscardnotSerial Number Barcode Model Name Test Lab Report NoTable of Contents 1Listing and Code Approvals Requirements for the Commonwealth of Massachusetts BELOW. Keep Clear of ALL ObstructionsManufacturer Requirements Inspect Appliance & Components Design & Installation ConsiderationsGetting Started Tools and Supplies NeededAppliance Location and Clearances Selecting Appliance LocationClearances 4Termination Locations Vent Termination Minimum ClearancesAlcove Applications Use of Elbows Vent InformationVenting Components Measuring StandardsHow to Use the Vent Graph Venting GuidelinesVertical Distance From Appliance to To the 90 Elbow Horizontal Termination StepWallline Thimble Fold Strap Here Sheet Metal Screw Vertical Termination Direct Vent PipeStep Twist-lock the vent cap and seal Cathedral Ceiling Class a Metal Chimney Top Adapter Flex Pipe Sheet Metal Screws StepExisting Masonry Chimney Retro Connector Gas Information Fuel ConversionsConverting to LP Gas Valve Regulator Replacement Gas Pressures Gas Connection PressureCheck for GAS Leaks Standing Pilot Ignition System Wiring Recommendation for WireConnecting to the Appliance Electrical InformationThermopile GAS Pilot Ignitor Thermocouple Brick Installation Door Crown Installation Appliance SetupAccessories Remove Shipping MaterialsInstall NEW Brick SET Positioning the LogsGlass Door Replacement Mineral WoolBlower Installation BlackVertical Damper Adjustment Shutter AdjustmentOperating Instructions Before Lighting ApplianceControls For Your Safety Read Before Lighting Lighting ApplianceFrequently Asked Questions After Appliance is LitTroubleshooting Symptom Possible Cause Corrective ActionBe Placed in this Opening Maintaining and Servicing Your Appliance After servicingMaintenance Tasks Inspect Service and Maintenance Log Appliance Dimension Diagram Reference MaterialsVent Components Diagram SLP Series Vent ComponentsVent Components List MiscellaneousLog Set Assembly Part number list on followingAt Depot StockedDepot Pedestal ComponentsStocked Valve ComponentsCONDITIONS, Exclusions & Limitation of Liability Limited Lifetime Warranty Serial Number Date Purchased Date Installed Dealer Telephone Columbia Bay Direct Vent Gas Appliance