GTO SL-1000, SL-2000 Determining the Mounting Position and Mounting the Operator

Page 17

DETERMINING THE MOUNTING POSITION AND MOUNTING THE OPERATOR

STEP 2

 

 

Illustration B

Install chain brackets at each end of the gate on the inside

 

(operator side) of the gate (see Overview Illustration, page.

 

12). Position the tops of chain brackets no more than 6Ó above

String

the bottom corners of the gate frame and secure with U-bolts

QuickReleasePin

(see Illustration B). The chain brackets will work on gate

ChainBracket

3

4

1

 

frames 1

/ " to 2 /2" in diameter or square tube gates. The U-

 

bolts provided will work on 2" diameter pipe gate frames.

 

Illustration C

 

 

Chain Bracket

 

positionbracketsothatstring

 

 

 

 

willbeapproximately7"to10"

 

 

fromgroundlevelatthepointwhere

 

 

theoperatorwillbemounted

 

 

STEP 3

 

 

Insert a quick release pin into the center slot in each of the chain

Quick Release Pin

String

brackets (see Illustration C). Tie a string to the end of each quick

release pin so that the string is tight between the two chain brackets (the

 

 

string will be used to align the operator). The string should be 7Ó-10Ó

 

 

from the ground (see Illustration B). The chain brackets can be adjusted

 

 

up or down on the gate to achieve the proper height. The goal here is

 

 

to set the height of the operator so that when the housing is in place it

 

 

will clear the ground by 1Ó to 4Ó (see Illustration E).

Illustration D

 

Center point between posts

 

Fence Post

CL

Fence Post

 

Chain Sprockets

 

 

Gate

 

Roller

 

Roller

 

String

Operator

 

(centered between post)

 

STEP 4

 

 

 

Find the center point between the two roller/fence posts (see Illustration D). This should coincide with the position of the center point of the operator. Dig a hole approximately 12Ó x 28Ó wide x 28Ó deep. Place the operator in the hole on its legs and position the bottom idler sprockets on the top of the string and level the unit (see Illustration E). Make sure operator is level and plumb. With the unit level and in place, pour the concrete and let set for 24 hours (checking the level periodically) before proceeding to the next step.

BEFORE POURING CONCRETE: 1] Make sure operator is centered between roller posts and aligned with string; and, 2] Determine method of installing conduit for wiring (see page 13)!

Illustration E

Level

!

!

Sprockets

Ground Level

String 7" to 10" above ground

Housing

1" to 4" clearance

14

Image 17
Contents Automatic Gate Operator Vehicular Gate Operator Class Categories When You Know Multiply By To Find SymbolTable of Contents Important Safety Instructions Before Installation For the InstallerII. During Installation For the System DesignerIII. After Installation Secondary Means of Protection Against Entrapment Entrapment Alarm UL 325No ONE should Cross the Path of the Moving Gate For the CONSUMER/END UserPoint hazard Required Safety Precautions for GatesSeries Moving Gate Can Cause Injury Or Death GTO PRO SL-1000 Series Technical Specifications GTO PRO SL-2000 Series Technical Specifications Parts Identification Gate Preparation Single Gate Operator InstallationOverview of Operator Installation Mounting the Legs on the Slide Gate Operator Recommended Wiring and USE of ConduitOperator side of the gate see Overview Illustration, Determining the Mounting Position and Mounting the OperatorTo Open the Gate Manually Installing the ChainInstallation of the GTO Transformer Powering the SystemConnecting the Battery Estimated Maximum Number of Cycles Per Day Solar Zones and Gate ActivityStep 18VAC Another see Illustration KRight Control Board SettingsPotentiometers Setting the Personal Transmitter Code FCC Regulation Mounting the ReceiverIf your gate opens from Right to Left Adjusting the Limit SwitchesHowever, if your gate opens from Left to Right Counter ClockwiseConnecting Additional Safety Devices Connecting Safety DevicesWHT White Used with GRN Green Connecting AccessoriesBLU Blue Used with GRN Green ORG Orange Used with GRN GreenAttaching the Housing Is especially important for safety devices MaintenanceMaintenance Trouble Shooting GuideConnected to these terminals System Test SpecificationsWarranty and Repair Service Limited Two Year WarrantyInstructions for the Installation Dual Slide Gate System Second Gate Auxiliary Operator Parts & Hardware Dual Gate System InstallationControl Unit This Step is for SL-2000/ 2200 Installation only Wiring the Second OperatorRefer to the illustrations on the next Setting the Control Board for Dual Gate InstallationsStep GTO Digital Keypad F300 Accessories Available Through Your DealerACCESS-ORIES Replacement Batteries Installation of this operator conforms to Class Installation Check List

SL-1000, SL-2000 specifications

The GTO SL-2000 and SL-1000 are advanced gate operators designed for efficient and reliable automation of heavy-duty swing gates. These models are renowned for their robust construction and innovative technologies that enhance both performance and security.

The SL-2000 is particularly suited for large, dual-swing gates weighing up to 2,000 pounds, making it a perfect choice for commercial and industrial settings. In comparison, the SL-1000 is designed for lighter gates that weigh up to 1,000 pounds, suitable for residential and light commercial applications. Both models are engineered to provide smooth, quiet operation, which is vital for residential areas where noise reduction is essential.

One of the standout features of both the SL-2000 and SL-1000 is their advanced DC motor technology. This allows for variable speed operation, providing a slower, more controlled movement during the opening and closing cycles. Such functionality not only enhances safety but also minimizes wear and tear on the gate mechanism, ensuring longevity.

Both models are equipped with obstacle detection technology that halts the gate's movement if an obstruction is encountered. This safety feature helps prevent accidents and damage, a critical aspect in environments where individuals and vehicles are present.

In terms of installation, the GTO SL series is designed for ease of use, featuring a straightforward setup process with clear instructions and minimal tools required. Additionally, the SL-2000 and SL-1000 include a built-in rechargeable battery backup, ensuring that the gate operates even during power outages.

Security is a top priority with both gate operators. They incorporate rolling code technology in their remote controls, which changes the access code with each activation, significantly reducing the risk of unauthorized access. Furthermore, the SL series supports multiple remote controls, allowing for convenient access for users while maintaining security.

Durability is another hallmark of the GTO SL-2000 and SL-1000. Both operators are built with weather-resistant materials, ensuring they can withstand various environmental conditions. This resilience makes them a solid investment for long-term use.

In conclusion, the GTO SL-2000 and SL-1000 are state-of-the-art gate operators that combine cutting-edge technology with superior safety features, making them a reliable choice for enhancing the automation of swing gates in diverse applications. Their ease of installation, robust construction, and advanced functionalities are significant advantages for property owners seeking secure and efficient access solutions.