Hague Quality Water Intl 60 SERIES manual Installation Steps and Start-Up Procedures

Page 10

Installation Steps and Start-Up Procedures

Step 1 Prepare the Placement Area

A.Make sure the placement area is clean.

B.Turn off the electricity and water supply to the water heater. For gas water heaters, turn the gas cock to “Pilot.”

C.Examine the inlet plumbing to ensure that the pipe is not plugged with lime, iron, or any other substance. Clean or replace plugged plumbing.

D.Make sure the inlet/outlet and drain connections meet the applicable state and local codes.

E.Check the arrows on the bypass valve to ensure that the water flows in the proper direction.

See Bypass Valve.

Caution: Do not plumb the appliance in backward.

F.Place the appliance in the desired location using Figure 2 as a guide.

G.For most installations, install the appliance after the pressure tank and any water filter appliance or water meter and before the water heater unless otherwise recommended. When installing a carbon filter for well water, place the filter after any water conditioning

appliance unless otherwise recommended.

Caution: If less than 10' of pipe connects the water treatment appliance(s) to the water heater, install a check valve between the water treatment appliance and the water heater as close to the water heater as possible. Ensure that the water heater has an adequately rated temperature and pressure safety relief valve.

H.For outside installations, the appliance should be enclosed so it is protected from the weather.

Softener

Brine Tank

Figure 2: Appliance Placement

WaterMax 60 Series Owner’s Manual

11/10/2008

10

Image 10
Contents Series Year Limited Warranty Number Owner Pays forContents General Information For Owner’s ReferenceGetting Maximum Efficiency From the Appliance Six-Button ControllerSix-Button Controller, Controller Part Function Set Regeneration Time Customer Settings Set Time of Day Set Number of PeopleChecklist Before Installation Iron Type DescriptionPrecautions Do NotInstallation Steps and Start-Up Procedures Prepare the Placement AreaInstallation Steps and Start-Up Procedures, Plug in the Transformer Set Up the ControllerCheck for Leaks Add Water to the Brine TankComplete the Installation Bypass ValveBlending Valve Setting and Using the ControllerRegenerate Button Service Settings Meaning Possible Values CommentsService Settings, Display Meaning Possible Values CommentsSee 72-96 Hour Mode 1-Timer Mode Operating ModesMode 1 Timer Mode Setting Chart 62AKQMode 2 Demand Delayed Mode Setting Chart NA, See Mode 1 Setting ChartSalt Depths Modes 1Replenishment Procedure 62AJQ Replenishment ProcedureTools and Materials Needed Refill Tank With Water 62AJQ Replenishment Procedure,Add Replenishment Media Replace Fill PlugDetermine Monthly Usage 61AAN WaterMax Iron Filter Sizing FormulaRegeneration Cycle Frequency Worksheet Water ExampleIron Filter and Potassium Feeder Installation Guide Iron Filter and Potassium Feeder PlacementStart-Up Procedures for 4-oz Potassium Permanganate Feeder Cabinet and Cover Assemblies Assembly and PartsIncorrect Correct Assembly and Parts, Brine Tank AssemblyCabinet and Assemblies Description QuantityInjector Assembly Injector Assembly93223 Injector 93810 InjectorScreen ThroatBypass Assembly Bypass AssemblySensor Wire HousingPiston Assembly AssemblyDrive End Cap Assembly Drive End Cap AssemblyDrive Motor Valve Housing90217 93238 Drive GearBrine Valve Housing Assembly Concave side Static O-RingFlow Control Brine90843 0.5 gpm End CapH2086 Drain Line Drain End Cap AssemblyRetainer Safety Shutoff Assembly Safety Shutoff AssemblySafety Shutoff Valve Elbow Installation Safety Shutoff Valve Elbow InstallationFill Plug Assembly Fill PlugTroubleshooting Problem Possible Cause SolutionTroubleshooting, Number or Letter Reading Model NumbersEfficiency Statements Letter Media Type62AMQ1 62APQ1 WaterMax Water Conditioner SpecificationsSeries 63MAQ1 63BEQ1,2 63MXQ1 62AJQ3WaterMax Filter Specifications Filter PurposeCertificates Certificates, Certificates, Page Page Series