Frymaster FPH1721 Power Requirements, Model Voltage Phase Wire MIN AWG Amps PER LEG Service Size

Page 13

EH1721 SERIES ELECTRIC FRYERS

CHAPTER 2: INSTALLATION INSTRUCTIONS

3.Close fryer drain-valve and fill frypot with water to the bottom OIL LEVEL line.

4.Boil out frypot prior to first use. See Frypot Boil-Out instructions in Section 2.4.

5.Drain, clean, and fill frypot(s) with cooking oil. See Section 2.5, Equipment Setup and Shutdown Procedures.

2.3 Power Requirements

DANGER

Copper wire suitable for at least 167°F (75°C) MUST be used for power connections.

MODEL

VOLTAGE

PHASE

WIRE

MIN.

AWG

 

AMPS PER LEG

 

 

 

SERVICE

SIZE

(mm2)

L1

 

L2

L3

17 kW

208

3

3

6

(16)

48

 

48

48

17 kW

240

3

3

6

(16)

41

 

41

41

17 kW

480

3

3

6

(16)

21

 

21

21

17 kW

220/380

3

4

6

(16)

26

 

26

26

17 kW

240/415

3

4

6

(16)

24

 

24

24

17 kW

230/400

3

4

6

(16)

25

 

25

25

 

 

 

 

 

 

 

 

 

21 kW

208

3

3

4

(25)

58

 

58

58

21 kW

240

3

3

4

(25)

51

 

51

51

21 kW

480

3

3

6

(16)

25

 

25

25

21 kW

220/380

3

4

6

(16)

32

 

32

32

21 kW

240/415

3

4

6

(16)

29

 

29

29

21 kW

230/400

3

4

6

(16)

30

 

30

30

DANGER

The electrical power supply for this appliance MUST be the same as indicated on the rating and serial number plate located on the inside of the fryer door.

DANGER

This appliance MUST be connected to the voltage and phase specified on the rating and serial number plate located inside the fryer door.

DANGER

All wiring connections for this appliance MUST be made in accordance with the wiring diagrams furnished with the equipment. Wiring diagrams are located inside the fryer door.

2-5

Image 13
Contents EH1721, BIH1721 & FPH1721 Series Hour Service HotlineApril Canada Page Table of Contents General Safety InformationComputer Information Shipping Damage Claim ProcedureAfter Purchase Service InformationDefinitions Service PersonnelEH1721 Series Electric Fryers Installation Instructions EH1721 Series Electric Fryers Installation Instructions Do not block the area around the base or under the fryers Electrical Grounding RequirementsAustralian Requirements Fryer InstallationModel Voltage Phase Wire MIN AWG Amps PER LEG Service Size Power RequirementsFrypot Boil Out Shutdown Equipment Setup and Shutdown ProceduresClean Inside and Outside of Fryer Cabinet- Daily Cleaning FryerEH1721 Series Electric Fryers Preventative Maintenance Built-in Filtration Periodic/Annual MaintenanceStainless Steel Care Assembling the Filter Filtration PreparationFiltering Tools Daily Filtration OperationPan Preparation Operating the FilterPlace the filter paper over top of pan EH1721 Series Electric Fryers BUILT-IN Filtration Replace the crumb tray in the pan Filter Operation Frypot refilling with filtered oil EH1721 Series Electric Fryers BUILT-IN Filtration Drain-flush handle blue location Introduction EH1721 Series Electric Fryers Operator TroubleshootingActivate TroubleshootingProbable Causes Control and Heating ProblemsOpen Drain Basket Lift Problems Probable Causes Error Messages and Display Problems Probable CausesBuilt-in Filtration Problems Probable Causes Filter pump won’t Recommended Spare Parts Service Hotline