Frymaster 45 Series manual Disconnect Grounding wire

Page 13

6.When the cooking oil/shortening temperature reaches 325ºF (162ºC), turn the flexible shaft slowly clockwise until the burner shuts off.

7.Allow the fryer to sit for a few minutes, then slowly turn the flexible shaft counterclockwise un- til the burner lights.

8.Repeat steps 6 and 7 at least three times to ensure an accurate setting is obtained. The Thermo- stat Control is considered to be properly calibrated when the burner lights as the cooking oil/shortening cools to 325ºF (162ºC)—not when the burner shuts off as the temperature rises.

9.Once the calibration point of 325ºF (162ºC) is determined, allow the burner to cycle on and off at least 3 times to be sure it will light at the calibrated temperature.

10.After the calibration is complete, place the fryer power switch in the OFF position and discon- nect the fryer from the electrical supply.

11.Carefully replace the thermostat shaft extension, ensuring that the stop screw is pointed straight up. Tighten the stop screw and locking nut and the setscrew, being careful not to rotate the flexi- ble shaft.

CAUTION

The thermostat flexible shaft must not be rotated while installing the thermostat

shaft extension!

When handling the thermostat, do not rotate the shaft more than two turns in either

direction. Doing so will cause damage to the thermostat.

12.Close the fryer control panel and replace the screws the upper corners.

13.Reinstall the thermostat knob with its pointer aligned with the 325ºF (162ºC) index mark on the temperature dial.

14.Reconnect the fryer to the electrical supply.

1.8Replacing Fryer Components

1.8.1 Replacing the Controller or Computer

1.Disconnect the fryer from the electrical power supply.

2.Unscrew the two control panel screws. The control panel is hinged at the bottom and will swing open from the top.

3.Unplug the fryer wiring harness from the back of the controller/computer and disconnect the grounding wire.

Unplug

harness

Disconnect

grounding wire

1-7

Image 13
Contents Gas Fryers Hour Service HotlineCanada Page Series GAS Fryers Service and Parts Manual Table of Contents Parts List This page Intentionally Left Blank Functional Description Interface Boards 806-3548, 806-5490, Series Interface Board LED Diagnostic Lights Accessing Fryers for Servicing CE Standard Burner Manifold Gas Pressures Adjusting the Pilot FlameCalibrating the Thermostat Control Cleaning the Gas Valve Vent TubeDisconnect Grounding wire Replacing the Temperature Probe Unplug Harness Disconnect Grounding wire Page Disconnect fryer from electrical and gas supplies Bend clip to release thermopile Replacing the Frypot Troubleshooting and Problem Isolation Ignition Failures CE Standard For Incoming Gas Pressures Improper Burner FunctioningImproper Temperature Control Computer-Related Problems Filtration Problems Sediment Particle Oil Flow Up for reverse Down for Forward Basket Lift Malfunctions Leakage ProblemsBell Crank Basket Lift Simplified Schematic Manual Push-Button BINDING/JAMMING Problems Bell Crank Basket Lift Simplified Wiring Diagram Modular Basket Lift Simplified Wiring Diagram Interpretation of Digital Controller Lights Troubleshooting GuidesVerify that the ON/OFF switch is in the on positon Pin 6? Xfmr Troubleshooting the Gas Valve Troubleshooting the Thermostat Troubleshooting the Temperature Probe Probe Resistance Chart Plan Wiring Diagram Wiring DiagramsPlan Wiring Diagram CE 230V MJ45 W/COMPUTER and Basket Lift Plan Wiring Diagram CE FM/MJ 45 W/0 Computer Inset A-A Plan Wiring Diagram Series Basket Lift System Plan Wiring Diagram Series Basket Lift System This page Intentionally Left Blank Series GAS Fryers Service and Parts Manual Parts List Parts BellCrankBasket LiftComponent Modular Basket Lift 208-250V ConfigurationMount, Modular Basket Lift Burner Assembly Component Parts Component Cabinet Assemblies and Component Parts MJ45 Batteries Enameled use 902-9324SP for side with access openingsFM145 Filter on Left FM45 Batteries with Built-In FiltrationComponent Filter Magic II Add-On Cabinet Components Side, Left Cabinet, w/Access Openings CASTERS, LEGS, and Associated Hardware Components Page Complete Shield Assemblies Complete Box Assembly This page Intentionally Left Blank Page Component Controller Assemblies Thermostat Controllers Set Screw Controller Assemblies Other than Thermostat Controllers Door Assembly DrainSystem Components Component Component Filter Magic II Filter Pan AssembliesFrypot Assemblies and Component Parts OIL Component Through March April 2001 and Later Power Shower Assembly Temperature PROBE, THERMOSTATS, and Related Components Wiring Assemblies and Harnesses Wiring ASSEMBLIES/HARNESSES and Remote Cable AssembliesPower Cords Wiring CONNECTORS, PIN TERMINALS, and Power CordsThis page Intentionally Left Blank Service Hotline